1 / 7

Project News Richard Goodwin Nigel Williams

Project News Richard Goodwin Nigel Williams. 20 th May 2008. Issues identified. Some RDA concerns / perceptions e.g. missed dates, constant change to Data Dictionary Testing of core Status with YF Need for stability Expectation of Target go-live build Dates

cutter
Download Presentation

Project News Richard Goodwin Nigel Williams

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project News Richard GoodwinNigel Williams 20th May 2008

  2. Issues identified Some RDA concerns / perceptions e.g. missed dates, constant change to Data Dictionary Testing of core Status with YF Need for stability Expectation of Target go-live build Dates Content, expectation of full system? Need to focus on the target go live build Too many commitments - team spread thin Not sure we have identified everything that needs to be in place to achieve sign-off of MCIS Need more visibility across all teams as a whole, re.: Compliance checks, plans for live use Impacts on changes on local teams Local team plans, MCIS team plans

  3. Shift Focus to getting a signed-off system Postpone implementation preparation activities in RDAs except ONE & YF (NB: does not mean stopping work on payment interfaces, web service, or AWM’s SQL to XML conversion solution) Create detailed Release Plan, including external milestones relevant to sign-off (e.g. PIG meetings), and manage against it Mark Swan to focus on UAT; Anne Smith to focus on Release Plan & Release Management Be clear what’s in scope and what’s a change to the plan Manage changes: assess functional, technical & stakeholder impact – where possible before change happens, so we have choices Establish go-live criteria for RDAs, CA, MA & AA Establish criteria for, & evidence needed to obtain, S.R.O.’s sign-off

  4. Key actions: Design & Build Definition of target go-live release What’s in it What’s not in it, and why / how RDAs can go live without those functions (e.g. what’s the workaround?) Agree that definition with ONE, YF, CA, MA, other RDAs, MCIS S.R.O. Build only the inclusions plus fixes sufficient to achieve sign-off Clear process & responsibilities for incorporating requirements, or other changes

  5. Key actions: Testing Script coverage matrix (what scripts have been run for each release) Use matrix (gaps) & knowledge of what’s changed in a build, to prioritise script execution Track defect levels: no. open & no. fixed, by severity, trend in volume being raised (tailing off?) Brief, regular meetings of development & testing – for system test & for UAT– to align fixing activity & build timings to tester need Ensure evidence capture arrangements are sufficient

  6. Stakeholder Management Improve communication with RDAs Greater transparency around our progress – should give increased confidence Explain why we have to change things that affect them – in terms their (business & IT) staff can understand– explain what impact assessment has been done, and involve them in process Quantify changes so their understanding of the impact will be realistic Keep them posted. Explain delays Copy FDs on the weekly report, and pick out key messages in the covering email Identify who in the team will assess & manage the stakeholder impact of changes in plan, scope etc.

  7. Steering and Sign-off Confirm the following group will sign-off UAT and ask them to act as a Release Board: Richard Goodwin, MCIS S.R.O. (Chair) Giles Southwell/Naomi Charlton, Head of Organisational Performance, One NorthEast (who will sign-off ONE’s Go-Live decision) (to be confirmed) Adrian Green, European Funding Manager, Yorkshire Forward (who will sign-off YF’s Go-Live decision) Margaret Lees, CLG EPP, Head of Managing Authority Kim Humberstone, CLG Finance, Head of Certifying Authority Karan Price, CLG Internal Audit Service, Head of Audit Authority Nigel Williams, CLG EPP Programme Manager Ensure this group’s acceptance criteria are understood Create Acceptance Report as a vehicle for their sign-off Instigate high-level monthly report to the PIG Consider OGC Gateway 4 Review (Readiness for Service) – how would timing relate to MCIS roll-out across RDAs?

More Related