EC Integration Schedule. ~ 2 months delay. Stack B (EC C). Start stacking New target dates: B: 17 May A: 31 May. Stack B (EC A). Stack A (EC C). 8-planes at CERN. IDEAL DELIVERY OF FE to equip 8p as we stack We assume ~10 w.d. for installation and data acquisition per 8- 16-plane
E N D
EC Integration Schedule ~ 2 months delay Stack B (EC C) Start stacking New target dates: B: 17 May A: 31 May Stack B (EC A) Stack A (EC C) M. Capeans
8-planes at CERN IDEAL DELIVERY OF FE to equip 8p as we stack We assume ~10 w.d. for installation and data acquisition per 8- 16-plane 6.06 ----- 8p B1 9.07 --- 8p B2 9. 08 ---- 8p B3 30.06 --- 16 p A1 10.08 --- 16p A2 3x 8p B 2x 16p A M. Capeans
Next delivery of wheels by mid July 3x 8p B 3x 8p B 2x 16p A 2x 16p A M. Capeans
Complete schedule FE delivery(Stacking delay is recovered in next delivery, by mid July: EC meets TC dates) 23 d 30 d M. Capeans