A GUIDE FOR THE SPECIFICATIONS AND PAYMENT OF STOCKPILED MATERIALS

Step-by-step instructions for specifying and processing stockpile payments in construction contracts. Learn how to assess payments accurately and efficiently with practical examples and tips.

dahlquist
Download Presentation

A GUIDE FOR THE SPECIFICATIONS AND PAYMENT OF STOCKPILED MATERIALS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. A GUIDE FOR THE SPECIFICATIONS AND PAYMENT OF STOCKPILED MATERIALS Kevin Hanlon, PE Civil Engineer II Contracts Section

  2. Step 1 is to select the contract list located Under the “File” tab Step 2 is to highlight the contract that the stockpile payment is to be assessed towards

  3. Step 2: Select the “Add” Icon Step 1: Select the ‘stockpile” icon

  4. Click the “next” button

  5. Step 2; From the Stockpile Description window, select one of the Descriptions (It doesn’t matter which description, just pick one, and each Description can only be chosen once)and then hit Next. Step 1; click on the down arrow from the Stockpile Description

  6. From the Stockpile Description window, type the description of the stockpile, this will appear in under the “Comments” heading on the Stockpiles main page. For Example “stockpile payment for 503 reinf steel”

  7. Must enter a Transaction Comment, then select “Next” at the bottom of the page. Enter the payment amount for the stockpile, if more than one stockpile transaction, enter the sum of all the bills.

  8. Select the “Add Item” link and the item list for your contract will appear

  9. Ensure that the Project number and Category are correct Select the item that the stockpile is going to be assessed towards by double clicking on the line item

  10. If the Transaction Amount is for more than one stockpile item, add more items by selecting this add item link Input the Assigned Dollar Amount, if there is only one stockpile item, then the Assigned Dollar Amount will be equal to the Transaction Amount, if more than one stockpile item, the Assigned Dollar Amount will be the portion of the Transaction amount dedicated towards the highlighted Item on this page. Select “next” to continue

  11. You must input either the “Recovery Factor” or “Recovery Quantity”. The Policy is to use the fastest Recovery Quantity available. Select “Finish” will save this Stockpile transaction

  12. At this point the Stockpile Transaction is complete, The Stockpile payment will automatically appear on the next estimate and the recovery of the Stockpile payment will also occur automatically as quantities are posted towards the item(s).