1 / 17

Cost Estimating Post Hurricanes: A Review of the Challenges Karl D. Bartholomew, P.E., ASA

Cost Estimating Post Hurricanes: A Review of the Challenges Karl D. Bartholomew, P.E., ASA Director. September 2006. Process Industries Cost Escalation. A review of pre-hurricane construction How did the hurricanes impact costs? What’s happening now?

dale
Download Presentation

Cost Estimating Post Hurricanes: A Review of the Challenges Karl D. Bartholomew, P.E., ASA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cost Estimating Post Hurricanes: A Review of the Challenges Karl D. Bartholomew, P.E., ASA Director September 2006

  2. Process Industries Cost Escalation • A review of pre-hurricane construction • How did the hurricanes impact costs? • What’s happening now? • Were Hurricanes Katrina and Rita responsible for cost escalation for onshore process facilities today? • Lessons for the future: levels of cost estimate accuracy

  3. What was happening pre-hurricane? • Materials and resources were already being strained • Number of announced projects in pipeline for engineering and front-end work in refining and petrochemicals ($95 B in North American refining alone) • Rising costs not limited to just U.S. Gulf Coast • Cost overruns in Alberta Oil Sands; Middle East petrochemicals • Refinery construction cost indices up 11% Jan 2004 vs. Jan 2006

  4. What was happening pre-hurricane? • Bulk commodities, steel prices were up • In large part to China, India, U.S. • Freight costs much higher due to higher oil prices • Cost escalation pressures were already in place before Katrina and Rita

  5. The hurricanes hit – how did that impact costs? • Immediate draw on commodity resources • Lumber, cement, drywall, cleaning materials • Onshore process operations impacted by both water and wind damage • Costs incurred to restore process operations: • Debris cleanup • Inspection & replacement of damaged rotating equipment, electrical, instrumentation • Inspection and repair of steel (corrosion) • Repair of damaged vessels, insulation

  6. Cost Impact of hurricanes • Labor market saw biggest change • Quick rise in bare labor rates • Living costs • Added benefits (per diems) • 2 stories of hurricane impact: • Barber quits cutting hair, buys dump truck, contracts with FEMA at 000s/week to haul debris • Laborers changing job sites if offers catered meals vs. box lunches

  7. More hurricane impact • Draw on specialty craft labor from Corpus Christi up to Midwest • Insulators, scaffolding see 2X increase in rates • Contractors throwing $ at the problem trying to fix everything for everyone • Another story – refiner’s concern wasn’t getting scaffolding up, but getting it down if another storm hit

  8. Some costs were unexpected • Extended living costs over a long time was something nobody anticipated • Some vendors used warranty issues to force full replacements even if the item worked • Rotating equipment, control systems • Facilities that didn’t have up to date drawings & specs of what was actually at their plants incurred substantial engineering & design costs • Some facilities in better shape on this due to OSHA requirements • Some facilities took this as opportune time to improve/upgrade their plants (“urban renewal”) • Has led to some contract coverage issues

  9. Outlook for next year • Most E&C companies have full shops • due to major expansion wave underway in refining • Steel & fabrication shops essentially full • Bidding war for experienced staff • Labor rates continue to escalate but at lower rate

  10. Where are we today? • Biggest impact we see is on delivery schedules • Lead times for major forged reactor vessels have gone from 24 months to 40+ months (for high pressure processes) • Engineering front end design schedules increasing by 2X • Hurricanes gave us a new ‘set point’ which appears to be stabilizing at much higher labor rates • Expectation that rate growth will flatten before resuming typical growth

  11. Equipment Lead Time

  12. Equipment Escalation

  13. Were the hurricanes the main culprits? • For the onshore process industry – NO • Cost pressures already building up • Katrina/Rita kicked down the door of building escalation not only in the Gulf Coast but has created impacts around the world, particularly for experienced engineering, construction and operating resources. • Cost pressures will continue for next several years, but not at the extreme post-hurricane growth

  14. Accuracy of Cost Estimates • Accuracy of estimate is directly related to level of effort (time) spent • Association of Advancement of Cost Engineering (AACE) provides guidelines for accuracy vs. work effort $ $$ $$$ $$$$ $$$$$$$$

  15. Level of Work for Cost Estimates

  16. Work effort for +/- 20%-30% • 5%-10% of engineering design is complete • For $100 million project ~ $0.8-1.5 million • Factored estimate based on major equipment • Vendor verified major equipment prices • Preliminary allowances for offsites (utilities, infrastructure) • Historical % for professional services, indirects

  17. Cost Estimate Deliverables S = Started P = Preliminary C = Complete The AACE International Recommended Practice for Cost Estimate Classification, Joint Cost Management Societies Proceedings, Larry R. Dysert, CCC

More Related