Air and Ozone Sparging of TCE Using a Directionally Drilled Horizontal Well Site 86, Camp Lejeune

Air and Ozone Sparging of TCE Using a Directionally Drilled Horizontal Well Site 86, Camp Lejeune. Mark Strong, P.E. CH2M HILL Christopher Bozzini , P.E. CH2M HILL Daniel Hood, NAVFAC Mid-Atlantic Bob Lowder, MCB Camp Lejeune EMD. Camp Lejeune Background.

dalmar
Download Presentation

Air and Ozone Sparging of TCE Using a Directionally Drilled Horizontal Well Site 86, Camp Lejeune

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Air and Ozone Sparging of TCE Using a Directionally Drilled Horizontal WellSite 86, Camp Lejeune Mark Strong, P.E. CH2M HILL Christopher Bozzini, P.E. CH2M HILL Daniel Hood, NAVFAC Mid-Atlantic Bob Lowder, MCB Camp Lejeune EMD

  2. Camp Lejeune Background • Second largest U.S. Marine Corps Base in the Country • Camp Lejeune was established near the city of Jacksonville, N.C, in 1942. • Base covers 236 square miles • CERCLA site since 1989 • 22 Operable Units (OUs), 97 Sites.

  3. Site Location and History • Site 86 is associated with three former waste oil ASTs, used during the 70s and 80s • Over the course of several investigations since 1992, the solvent plume migrated away from the source area and now extends several hundred feet off-site Bld. 25

  4. Pilot Test Objectives • Prevent further migration of the TCE plume off-site • Evaluate air (and ozone) distribution using a horizontal well • Determine if ozone and/or air sparging can reduce TCE impacts to below regulatory standards within one year

  5. TCE in Plume in 2002 (30-35’ bgs)

  6. TCE in Plume in 2002 (40-45’ bgs)

  7. TCE in Plume in 2002 (50-55’ bgs)

  8. Site 86 Cross Section

  9. Directional Drill Rig On-Site

  10. Air Sparge ‘Screen” 4” SDR 11 HDPE Pipe 0.020 Inch Wide Slots 0.5% Open Area

  11. Directional Sparge Well Layout Total Length of Drill = 950’ Total Slotted Length - 350’

  12. Compressor and Ozone Generator Temporary Buildings (Connex Boxes)

  13. Ozone Generator Chiller

  14. Air Compressor, Receiver, Gas Cooler

  15. Ozonia Generator (CFV-03, 60 ppd, air feed) Photo courtesy Ozonia North America

  16. Baseline TCE Concentrations, Feb ‘05 30-35 ft bgs

  17. Baseline TCE Concentrations, Feb ‘05 40-45 ft bgs

  18. Baseline TCE Concentrations, Feb ‘05 50-55 ft bgs

  19. Schedule • Three Months of Air Sparging (120-140 cfm) • One Month of “Rebound” Monitoring • Six Months of Ozone Enhanced Air Sparging (~ 7000 ppmv) • Three Months of “Rebound” Monitoring (Recently Completed)

  20. Ozone Injection Performance • Ozone production began in late July, 2005 • Intermittent operation from July to December • Mechanical issues: desiccant dryer and chiller • Total aggregate run time ~ 2-1/2 months (50% up time) • Total mass of ozone delivered ~ 3900 pounds

  21. Average TCE ConcentrationsZone “A” Monitoring Wells (30-35’ Screen Depth)

  22. Average TCE ConcentrationsZone “B” Monitoring Wells (40 - 45’ Screen Depth)

  23. Average TCE ConcentrationsZone “C” Monitoring Wells (50 - 55’ Screen Depth)

  24. Discussion • SVE was not conducted because of low permeability overburden; trace levels of TCE measured in shallow vapor during operation (ppbv) • Air was diverted horizontally by overburden; air bubbling was observed 300 feet from the well • Lateral propagation of air “fingering” was estimated to be 50 feet on either side of the well, as indicated by dissolved oxygen concentrations • Negligible increases in dissolved chloride from baseline levels

  25. Conceptual Model

  26. Example Dissolved Oxygen and ORP Trend

  27. Summary of Analytical Data

  28. Conclusions • 90% average reduction of TCE within three months in wells with baseline TCE > 50 μg/L • 99% average reduction within one year in wells with baseline TCE > 50 μg/L • No significant rebound after three months (greater than 25 µg/L) • Distance of influence ~ 50 ft on both sides of the well (as indicated by DO measurements) • Possible contribution of ozone to TCE mass reduction inconclusive - low TCE concentrations and limited period of operation

  29. Summary of Costs • $750K Total Budget • Horizontal Well, Compressed Air System, Container, Electrical ~ $250K • Ozone System and Container ~ $300K • Monitoring ~ $100K • O&M ~ $100K