Successful Completion of Six-Cavity Test with the HINS Accelerator

Successful Completion of Six-Cavity Test with the HINS Accelerator. Six-Cavity Beam Line. HINS six-cavity beam line constructed on the east side of MDB. Beam line can test concept of driving multiple cavities with a single RF amplifier.

dani
Download Presentation

Successful Completion of Six-Cavity Test with the HINS Accelerator

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Successful Completion of Six-Cavity Test with the HINS Accelerator

  2. Six-Cavity Beam Line • HINS six-cavity beam line constructed on the east side of MDB. • Beam line can test concept of driving multiple cavities with a single RF amplifier. • Significant cost savings may be realized by using fewer RF power amplifiers.

  3. Vector (I/Q) Modulator: Modulates phase and amplitude independently: With  = (2 - 3)/2  = (2 + 3)/2 Output power ~ cos2() Output phase ~  water load circulator Four Port Hybrid Input → 2 1 2 Phase Shifters Output :← to circulator and cavity 3 3 4

  4. LLRF System Setup • RF Feedback on RFQ amplitude and phase • Feed forward learning correction of Ferrite Vector Modulators

  5. Vector Modulator Configuration

  6. Cavity Probe Signals • RFQ RF Feedback ON • FVM Control OFF • Beam ON (7 mA) Magnitude (MV) Phase (degrees) Beam Off at 300 us *Buncher 1, Cavity 2, and Cavity 3 were detuned so that the FVM’s have enough dynamic range to compensate disturbances.

  7. Cavity Probe Signals • RFQ RF Feedback ON • FVM Control ON • Beam ON (7 mA) Magnitude (MV) Phase (degrees) *Cavity 1 FVM correction did not completely converge due to limited dynamic range of FVM

  8. RFQ Magnitude and Phase Regulation • RFQ RF Feedback ON • FVM Control ON • Beam ON RFQ Magnitude RFQ Phase +/-1% Pulse to Pulse Average of RMS Error (50 Pulses) Pulse to Pulse Average of RMS phase Error = 0.0147 degrees Pulse to Pulse Average of RMS magnitude Error = 0.0207%

  9. Beam Energy Stability • Difference between green and red trace show time-of-flight between diagnostic line BPMs. • Energy scale is ~1.4keV/degree for time of flight BPM measure-ments. Plot shows noise level of about 10keV for 3MeV beam.

  10. Contributors • AD • HowiePfeffer • GeorgeKrafczyk • Mike Kucera • Brad Claypool • Jim Patrick • AndreyPetrov • Bill Marsh • Charlie Briegel • Dennis Nicklaus • Denise Finstrom • Carl Schumann • Stan Johnson • Todd Johnson • Aisha Ibrahim • Roger Tokarek • Duane Voy • Nathan Eddy • Peter Prieto • Andrea Saewert • Lionel Prost • AD • Bob Webber • Jim Steimel • Bruce Hanna • Vic Scarpine • Alex Chen • Bruce Popper • Maurice Ball • AbhishekDeshpande • Dave Peterson • Ralph Pasquinelli • Elmie Evans-Peoples • Wai-Ming Tam • Brian Chase • JulienBranlard • Paul Joireman • Ed Cullerton • Vitale Tupikov • Philip Varghese • Chris Jensen • Kevin Martin • Steve Hays • APC • Robyn Madrack • Dave Wildman • HenrykPiekarz • Jean-Paul Carneiro •  Al Moretti • Nikolai Mokhov • TD • Giorgio Apollinari • Gennady Romanov • TimergaliKhabiboulline • IouriTerechkine • Leonardo Ristori • Tom Page • Tom Nicol

  11. HINS RF Distribution