1 / 13

September 26, 2007

Kansas Renewable Energy and Energy Efficiency Conference Wind 2007 RFP Update John Grimwade - Sr. Director Strategic Planning and Development. September 26, 2007. About KCP&L. KCP&L’s Comprehensive Energy Plan provides a balanced approach to meeting the region’s energy needs.

dannon
Download Presentation

September 26, 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Kansas Renewable Energy and Energy Efficiency ConferenceWind 2007 RFP UpdateJohn Grimwade - Sr. Director Strategic Planning and Development September 26, 2007

  2. About KCP&L

  3. KCP&L’s Comprehensive Energy Plan provides a balanced approach to meeting the region’s energy needs

  4. Spearville Wind Energy facility

  5. Comprehensive Energy Plan – Renewable Energy Additions • KCP&L’s original plan had targeted for 200 MW of wind additions by the 2008 timeframe • Through the collaborative workshops this amount was reduced in the base Comprehensive Energy Plan to 100 MW with a commitment for the stakeholders to consider a second 100 MW in 2008.

  6. KCP&L’s 2007 Wind RFP • Multiple options were requested to address alternatives for location timing, quantity and ownership structure • Both Kansas and Missouri sites were requested • Minimum of 100 MW of wind powered generation to be on-line by October 1, 2008 • Options for additional 300 MW of wind powered generation to be on-line by October 1, 2012 • Asked for both PPA and Build/Transfer alternatives

  7. RFP Timeline • Issue Press Release and RFP • March 29, 2007 • RFP’s due to KCPL • June 15, 2007 • RFP Evaluation Process • June - August, 2007 • Seek Regulatory and Stakeholder consensus • September – October, 2007 • Contract Negotiations • September - October, 2007 • Projected Construction Start Date • 2Q, 2008 • Projected Last Turbine On-line Date • 4Q, 2008 • Post 2008 Construction Activity Dependent Upon RFP Proposals

  8. KCP&L Received strong interest for projects to be completed in 2008 and from 2009-2012 • Missouri Proposals Received • Two proposals were received that offered a 2008 on-line date • Five proposals were received that offered a 2009 or later on-line date • Kansas Proposals Received • Nine proposals were received that offered a 2008 or 2009 on-line date • Seven proposals were received that offered a 2009 or later on-line date

  9. Screening Methodology – 2008 On-line Proposals • Preliminary Screening • High Level Analysis – Evaluated all proposals based on multiple factors • Assessed unacceptable risk for completion or operation of the project • BTA Proposals – Moved to final screening evaluation if they passed the High Level Analysis • PPA Financial Analysis – Ranked the PPA proposals from lowest cost to highest cost for proposals in each state then performed High Level Analysis • Transmission Service Impact Analysis – KCPL hired an independent engineering firm to perform a load flow analysis on those proposals that were moved to the final screening evaluation process • Final Screening – Using the financial and generational data provided in each proposal, along with the results of the transmission service impact analysis, a 20-year Net Present Value Revenue Requirements (NPVRR) analysis was performed to evaluate the impact of each proposal against a No Wind base case.

  10. The cost to install 100 MW of new wind capacity has increased 55% over 2003 cost estimates

  11. Financial Analysis of 2008 vs. 2009 Projects

  12. Required Renewables Estimate - Missouri & Kansas Utility Under Bingaman

  13. And the winner is???

More Related