1 / 11

Renewable RFP Process Update September 26, 2007

Renewable RFP Process Update September 26, 2007. Background. Renewable RFP issued – February 2007 Responses received – April 2007 Responses reduced to short-list – July 2007 Due diligence – July/August Contract negotiations – August/September. Responses to RFP.

Download Presentation

Renewable RFP Process Update September 26, 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Renewable RFP Process Update September 26, 2007

  2. Background • Renewable RFP issued – February 2007 • Responses received – April 2007 • Responses reduced to short-list – July 2007 • Due diligence – July/August • Contract negotiations – August/September

  3. Responses to RFP • 23 Projects proposed by 17 developers • Two projects from outside Kansas • All responses were wind energy projects • Per MWh prices ranged from ~$35 - $70 • Proposals were for both ownership and PPA’s

  4. Review Team • Greg Greenwood, Team Leader • Westar Energy employees from the following areas: • Generation resource planning • Environmental • Finance • Transmission • Legal • Regulatory • HDR Engineering • Black & Veatch • Les Evans, KEPCO, VP Power Supply • Alan Pollom, The Nature Conservancy

  5. Evaluation Criteria to Make Short-List • Public/Community Acceptance • Environmental Compatibility/Acceptance • Credit Risk • Levelized Cost -Revenue Requirements (PPA or Ownership) • Transmission Upgrade Costs • Wind Turbine Equipment Evaluation • Developer Experience

  6. Short-list Process • Seven projects remained after initial screening process • Short-list project developers invited to half-day due diligence sessions in Topeka • Refined selection criteria used to reduce short-list to 500 MW’s to begin negotiations

  7. Evaluation Criteria - Short-List to Negotiations • Environmental Analysis/ Public Acceptance 5% • Production Tax Credit Certainty 5% • Credit Risk 5% • Levelized Cost -Revenue Requirements (PPA or Ownership) 35% • Transmission Costs 15% • Developer Construction Experience 10% • Wind Turbine Equipment Evaluation 15% • Developer Interview 10%

  8. Selection Process • Absolute project score did not always determine projects selected due to: • Transmission constraints • Wind diversity goals • Excess turbine diversity • Other

  9. Ownership vs. PPA • Our analysis showed little cost difference to customers • Ultimate answer to economics question can’t be known today • Our conclusion - - Diversity of ownership reduces risk for Westar and its customers • Targeting ~50% ownership, 50% PPA’s in 500 MW portfolio

  10. Contract Negotiations • Negotiating with four developers currently for 500MW of Wind • Contracts near completion - - But not complete • Filing for predetermination of rate treatment planned no later than October 1st • KCC decision requested by yearend

  11. Wind RFP Highlights • Cost per MWh (levelized) ranged from $35 - $70 • Selected 500 MW portfolio – low $40’s/MWh • Costs exclude dispatch inefficiency and assumes PTC’s are extended • 300MW’s of wind energy currently scheduled to be online in 2008 • Public announcement of specific projects expected soon

More Related