An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RIGA, 26 September 2007 Quality workshop Grant Contracts Irina Kabenina Cross-Border Cooperation & Neighbourhood Programmes EU-Russia Cooperation Programme

  2. 8th Call for Proposals 19 contracts: • 1 project - 12 months duration • 1 project – 17 months • 2 projects – 18 months • 1 project – 19 months • 1 project - 22 months • 2 projects – 23 months • 11 projects – 24 months

  3. 9th Call for Proposals 10 contracts: • 2 projects – 18 months • 1 project – 21 months • 7 projects – 24 months First pre-financing has been paid

  4. 8th Call for Proposals • 16 projects need to submit Interim reports by now • 3 projects submitted so far • 1 project submitted Narrative report only • 5 projects preferred to send update reports (1 still not received)

  5. General Observations • Preparation of application • Contract signature • Implementation • Reporting

  6. Preparation of applications • Involvement of partners in design, responsibilities, budget • Number of partners, level of experience in projects • Language

  7. Lengthy approval/contracting procedure by the Commission: format of DoA/budget differ in application and contract • Different timing in contracting (ERDF/Tacis) • Delayed start of projects, delayed timetable/mismatch of activities Approval, Contract signature

  8. Implementation • Management at the level of project: overall LP/Tacis LP • Management in partner country/institution: multiple partnership • Very busy timetable • Knowledge of procedures by partners • National/local specificities: procurement, per diems, accounting • FAQs • Training

  9. Implementation Most frequent problems/questions: • How to make changes in the budget? • How often to report about changes in the budget? • How to confirm co-financing to the financing authority? • What to do if a Partner falls out? • Sample of an agreement among partners. • How to transfer money to a Russian Partner, especially to an administration? • Is it possible to advance money to a Russian partner?

  10. Implementation • Project management by LP • Project management by a consultant

  11. Reporting (external funding) Why delays? • Difference in reporting periods/requirements Interreg/Tacis • Many partners – delayed reporting by the partners • No distinction between internal/external funding • Difficulties in communication/language • Interim audit

  12. Reporting (external funding) • Too complicated forms? • Confusing requirements? • Less respect?

  13. Visibility Disclaimer !“The project is co-funded by the European Union “ !"This publication has been produced with the assistance of the European Union. The contents of this publication is the sole responsibility of … and can in no way be taken to reflect the views of the European Union."

  14. Best practice • Read carefully the contract, its Annexes • Read carefully Manual of Procedures • Keep regular contact with the EC Delegation (Contracting Authority), especially in case of doubts • Provide training to your partners for correct reporting purposes • Keep regular records of the expenditure • Use EU Visibility Guidelines!!! • Provide timely reports • Include with every report required information