1 / 20

High- Tc Superconducting Link Status of Task 7.5 FP7 Meeting at LASA-Milano

High- Tc Superconducting Link Status of Task 7.5 FP7 Meeting at LASA-Milano. Ballarino , CERN for the Task 7.5 Collaboration CERN, Bruker , Columbus, University of Southampton LASA , 18-09-2012. Outline. Task description C able concept Progress since last meeting (April 2012):

darci
Download Presentation

High- Tc Superconducting Link Status of Task 7.5 FP7 Meeting at LASA-Milano

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. High-Tc Superconducting LinkStatus of Task 7.5FP7 Meeting at LASA-Milano Ballarino, CERN for the Task 7.5 Collaboration CERN, Bruker, Columbus, University of Southampton LASA, 18-09-2012

  2. Outline • Task description • Cable concept • Progress since last meeting (April 2012): • Cabling machines • Test station • Status of activity vs final deliverable • Conclusions

  3. Task 7.5: High-Tc link Deliverable of Task 5 - as described in the Eucard Grant Agreement: Superconducting link, 20 m long, containing 48 HTS cables rated at 600 A - DC .The Task includes design and assembly activities – but not the test of the final prototype The final application for LHC (P7) consists of two superconducting links, each about 500 m long, with the same configuration of the prototype CERN will test the 20 m long prototype in nominal operating conditions

  4. Cable concept Elaboration of a cable concept that enables the use of pre-reacted superconductors available in the form of tape: MgB2, YBCO and BSCCO 2223 The HTS cable design adopted for power transmission lines appeared not to be suitable for this specific application - few tapes and many cables in the same cryogenic envelope

  5. Cable Concept Three HTS tapes per cable interleaved withcopper strips 4 mm 1 mm + 600 A - 600 A

  6. Cable/Link Concept (2/2) 24 × 2 × 600 A • 2 kg/m • 200 mHTS/mcable Link: multi-cable assembly in cryostat Multi-cable assembly

  7. Prototype twisted-pair cables characterization(CERN and SOTON) Type-5: MgB2 Type-3: Y-123 Type-2: Bi-2223 Type-1: Bi-2223 2×4.4 kA ! • Measurement performed on • twisted-pair cables made • from different conductors • No cabling degradation • observed (< 2 %) • Good homogeneity of Ic of • cables in the same in the • same twisted pair ( 2 %) Self-field, Length of cables = 2 m NB The Ic in the plot refers to one single cable of the twisted pair unit

  8. Cabling machine (1/2) For the controlled assembly of long cables a dedicated cabling machine has been designed, assembled and fully commissioned at CERN

  9. Cabling machine (2/2) Rotating machine for the twisting of insulated cables Design and assembly completed. To be commissioned in October 2012.

  10. Test station

  11. Test Station – SM 18 CERN laboratory Refrigerator: 6 kW @ 4.5 K (18 kW for test of LHC magnets) 25 000 LHe Dewar

  12. Test Station @ CERN: Conceptual Design RT Cryostatwith current leads Cryostatwith superconducting cables

  13. Test Station @ CERN: Conceptual Design RT LHe Instrumentation DAQ Quench Protection GHe 4.5 K Tv m ≤ 10 g/s 5 K ≤ Tv ≤ 70 K GHe LHe, 4.5 K Vacuum Insulation

  14. Test Station @ CERN

  15. Test Station @ CERN

  16. Test station at CERN • The two cryostats are fully assembled • The cryostat with the leads has beencommissioned – pressure and leak • tested, cooled-down to nominal conditions, operated at some 3.5 kA and • warmed up • The cryostat of the superconducting link was successfully leak tested last • week, and it will be pressure tested this week • The connection of the two cryostats is planned to take place this month. • A first cool-down, with a 20 m long twisted pair YBCO cable already • integrated the in cryostat of the superconducting link, is planned to take • place in October 2012

  17. Status of activity vs final deliverable • The 20 m long semi-flexible cryostat with a supporting system and • purpose-built terminations, is available today at CERN • A 20 m long 48 HTS cable assembly can be ready by end 2012 – when • also the rotating cabling machine will have been commissioned • This two components make the superconducting link which is the • deliverable of the Task 7.5 • In addition: • By the end of the year, the test station will have been fully commissioned • and 20 m long cables will have been tested in He gas in a variable • temperature range. The test of a 20 m long prototype will follow

  18. Is the Task 7.5 on schedule ? Yes Assembly of prototype link: planned to be ready by end 2012.

  19. Conclusions • A new cable concept has been proposed. Validation of the proposed • twisted-pair concept was done with the assembly and characterization of • short prototype MgB2, YBCO and BSCCO 2223 cables • Two cabling machines have been designed and constructed for the • controlled cabling of the 20 m long HTS twisted-pair cables • A new test station has been constructed at CERN for the test of the 20 m • long prototype link • The task is on schedule – a full prototype is planned to be available by end • 2012. The test in nominal operating conditions will follow. • Single twisted-pair cables, 20 m long, will be measured this year

  20. Thanks for your attention !

More Related