1 / 23

ERCOT LTSA

ERCOT LTSA. RPG 10/17/08. Introduction. Objective Year of study General procedure Transmission reliability Economic analysis Assumptions. Reliability Study Model Development. Vintage Load Summer peak 90-10 forecast (83,500MW; 9,200MW flat) Growth rates

darrius
Download Presentation

ERCOT LTSA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERCOT LTSA RPG 10/17/08

  2. Introduction • Objective • Year of study • General procedure • Transmission reliability • Economic analysis • Assumptions

  3. Reliability Study Model Development • Vintage • Load • Summer peak • 90-10 forecast (83,500MW; 9,200MW flat) • Growth rates • Future transmission and generation projects • Planned generation with I.A. as at July 31, 2008

  4. Reliability Study Approach • Sub-area/Region-based • North East • Houston • South Central • Valley • Transmission network reliability • Applicable generation • Bulk power needs

  5. Sub-area details • Northeast sub-area • Major load centers: DFW metro; IH-20, IH-35, IH-45 corridors, Brazos county • 31,600MW load • Generation resources (33,000MW) • 10,400MW coal, 800MW wind, 130MW hydro, Comanche nuclear plants (2,350MW), Kiamichi, 600MW DC tie. • Key future projects • CREZ: West Krum – Anna, Willow Creek – Hicks, Navarro – Central C, Sam Switch – Central C, etc. • Lufkin – Nacogdoches 345kV line. • Bosque Power Expansion, Oak Grove.

  6. Sub-area details

  7. Sub-area details • Houston sub-area • Major load centers: Houston metro, Galveston, Freeport. • 18,450MW load • 18,750MW generation • 2,500MW coal, 0 wind, 0 hydro • Key future projects • Rothwood • Zenith • Kuykendahl • Cedar Bayou 4

  8. Sub-area details

  9. Sub-area details • South-Central sub-area • 7,200MW load • 9,500MW generation • 6,000MW coal, 250MW hydro • Key future projects • Salado – Clear Springs double ckt 345kV • CREZ: Kendall – Gillespie - Newton • Sandow 5

  10. Sub-area details

  11. Sub-area details • Valley sub-area • Major load centers: Corpus Christi, Laredo, Brownsville-McAllen • 5,350MW [6,600MW] load • 5,775MW [11,050MW] generation • 4,200MW gas; 550MW wind, 100MW hydro, [STP nuclear] • Key future projects • Miguel – Lobo 345kV • Nueces Bay #7 re-powering

  12. Sub-area details

  13. Sub-area details • Western ERCOT sub-area • Major load centers: Abilene, Odessa, Wichita Falls. • 4,100 MW load • 13,700MW generation • 220MW DC tie, 4,500MW gas; 630MW coal • Key future projects • CREZ transmission only • Reactive compensation

  14. Reliability Criteria - Voltage

  15. Reliability Analysis • AC contingency-based • Generation dispatches (age, size, location, influence, DC ties, VFT) • Outages/unavailability • Age; size; location. • Problem categories • Wide area bulk power transfer • Local area regional problems • No assessment of adequacy (LOLE, location, type) of available generation

  16. Reliability Analysis • Dispatch scenarios • Generation deficient area • 10% unavailability to assess import sensitivity • Generation surplus area • 10% unavailability modeled using target gens • Hydro and wind resources not included • Monitor interface loading and voltage sensitivity

  17. Reliability Findings • Northeast sub-area

  18. Reliability Findings • Houston sub-area

  19. Reliability Findings • South-central sub-area

  20. Reliability Findings • Valley sub-area

  21. Reliability Findings • Western ERCOT sub-area • No analysis performed. CREZ analysis deemed adequate until further clarity is established.

  22. Next Steps • Align findings with results from economic analysis • Discuss fixes with Transmission Owners to develop solution alternatives

  23. Economic analysis • The economic viability of different projects are being evaluated using a base case and several change cases: • High load case • High natural gas price case ($11/MMBtu) • Two cases for different levels of expansion/construction of new nuclear plants • High wind case (in excess of CREZ scenario 2 wind) • New technologies (solar, energy storage, plug-in hybrids) • Carbon tax

More Related