1 / 11

IENG 451 - Lecture 23

IENG 451 - Lecture 23. Jidoka: Reliability, Quality, Poke Yoke. House of Lean. CUSTOMER FOCUS. Hoshin Planning, Takt, Heijunka Involvement, Lean Design, A3 Thinking. JUST IN TIME. JIDOKA. INVOLVEMENT. Standardized Work 5S TPM Kaizen Teams Suggestions Safety Activities

Download Presentation

IENG 451 - Lecture 23

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IENG 451 - Lecture 23 Jidoka: Reliability, Quality, Poke Yoke IENG 451 Operational Strategies

  2. House of Lean CUSTOMER FOCUS Hoshin Planning, Takt, Heijunka Involvement, Lean Design, A3 Thinking JUST IN TIME JIDOKA INVOLVEMENT Standardized Work 5S TPM Kaizen Teams Suggestions Safety Activities Hoshin Planning • Poke Yoke • Zone Control • Visual Order (5S) • Problem Solving • Abnormality Control • Separate Human & Machine Work • Involvement • Flow • Heijunka • Takt Time • Pull System • Kanban • Visual Order (5S) • Robust Process • Involvement STANDARDIZATION Visual Order (5S) Hoshin Planning Standardized Work Kanban, A3 Thinking STABILITY Jidoka, Heijunka, Kanban Standardized Work, 5S, TPM IENG 451 Operational Strategies

  3. Jidoka Concept – Sakichi Toyoda Jidoka has been defined as “automation with a human mind” • Humans make mistakes • Since humans work in the system, you can never eliminate mistakes • Machines make defects • Since machines are supervised by humans, use the humans to find and fix the machines that make defects • “… thus Zero defects is absolutely possible.” – Shigeo Shingo IENG 451 Operational Strategies

  4. Jidoka Human Error Rates: Dennis (2015) p. 126 IENG 451 Operational Strategies

  5. Jidoka Concept • Really, we are leveraging on Process Capability: • Old World Mfg – produce as much and as fast as possible. Replace defective products when someone complains. • New World Mfg – NEVER pass on a defective product. Stop the line and fix the process … and continually improve the process • By continually strengthening Jidoka, we are improving our process capability, and putting our firm in a better position for the future. • Focus on improving process capability (Poke Yoke) – by investigating defect causes and fixing the machines that cause them and by eliminating human mistakes • Focus on containing defects (Zone Control)– by having people find defects and containing them within the zone of control IENG 451 Operational Strategies

  6. Poke Yoke Most Common Errors: • Missing Process Steps • Process Errors (does not meet standard) • Mis-set Work Pieces (piece set backwards) • Missing Parts • Wrong Parts • Faulty Machine Operation • Adjustment Error (depth of cut stop set wrong by operator) • Equipment Set Up Wrong • Tools / Fixtures / Jigs Inadequately Prepared A Good Poke Yoke either prevents these or makes an error obvious: • Simple, with a long life • Highly reliable • Low cost • Designed for workplace conditions IENG 451 Operational Strategies

  7. Poke Yoke Examples A Good Poke Yoke either prevents errors or makes an error obvious: • Humans are not good at simple, repetitive motions (like sorting clips) • Machines can do the same action repeat ably IENG 451 Operational Strategies

  8. Poke Yoke Examples A Good Poke Yoke either prevents errors or makes an error obvious: • Humans are not good at dull tasks (like orienting rivets) • Simple additions to machines can do the task 100% of the time. IENG 451 Operational Strategies

  9. Poke Yoke Examples A Good Poke Yoke either prevents errors or makes an error obvious: • In the temporary case, a human could orient the bottle caps. But to do it long term, would be a waste of the human capacity to solve problems. • A three stage, simple addition to the machine can do the task 100% of the time at a lower cost. IENG 451 Operational Strategies

  10. Jidoka Implementation Involvement is Everything: people love to solve problems. • SMART Goals: • Simple • Measurable • Achievable • Reasonable (relevant) • Trackable • Motivation: • Extrinsic Motivation – comes from physical rewards • Monetary • Gifts • Intrinsic Motivation – comes from personal satisfaction • Recognition by peers • Personal growth (skills development) & self-actualization (self-accomplishment) • Contribution to a broader / larger goal IENG 451 Operational Strategies

  11. Questions & Issues IENG 451 Operational Strategies

More Related