Schedule and Coordination of the technical stop

Schedule and Coordination of the technical stop. January 12th 2010 K. Foraz. Aim of this technical stop. Repairs the nQPS connectors Perform all activities needed for 6kA Commission machine for 6kA. Baseline schedule. Organization. From electrical lock out ph1 to unlock out.

dawson
Download Presentation

Schedule and Coordination of the technical stop

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Schedule and Coordination of the technical stop January 12th 2010 K. Foraz Technical Stop Coordination

  2. Aim of thistechnical stop • Repairs the nQPSconnectors • Perform all activitiesneeded for 6kA • Commission machine for 6kA Technical Stop Coordination

  3. Baseline schedule Technical Stop Coordination

  4. Organization • From electrical lock out ph1 to unlock out 1. Request User MEF 4. Inform & coordinate 2. Check 3. Check & Implement Edit ADI’s HCC LMC -K. Foraz

  5. MEF-LPC Website LMC -K. Foraz

  6. List of activities Is presented at each meeting • nQPSConnectors, incl. work preparation, repairs, quality, ELQA • Non conformities solving • Electrical activities – Non conformities solving • Still TBC Cable change in PM45 • Collimation: TDI – waiting from test results • Cooling and Ventilation • Kickers: AGK , IPOC hardware, OASIS, LVDT, PFN… • BLM & BPM repairs • Power converters • Cryogenics: DFB’s filters, NC on CV891, valves, tunnel instr., cold compressors…. • ODH (minors:panels…) Technical Stop Coordination

  7. List of activities • Maintenance & Inspection • Lift maintenances • Cooling and Ventilation • Power converters • ODH • Access system • Others • Safety signalization for the cryo valves • TZ76 dampers • Radmon collimation • TIM tests • TOTEM – request a 3rd week • Survey Low-Beta • Commissioning of the tomograph • Protection of 600A current leads Technical Stop Coordination

  8. nQPSstatus • Tableau JCG Technical Stop Coordination

  9. Otheractivitiesprogress • Electrical activities – Non conformities solving On schedule • Lift maintenances done • Safety signalization for the cryo valves finished tomorrow • TZ76 dampers will be finished this week • Collimation Pt 3 & pt7 in progress • Tests have been done on TDI, waiting for action/no action • TIM tests in progress • Ventilation: control &/ repairs in progress • TOTEM in progress (requesting a 3rd week) • Survey Low-Beta in progress (60%) • Kickers activities in progress • BLM consolidation in progress • TE-EPC intervention in progress • Cryogenic consolidation in progress (65% done) • Commissioning of the tomograph this week • Protection of 600A currentleadsdone • ODH • Access system maintenance in progress All activities on schedule No show stopper Technical Stop Coordination

  10. Updatedschedule Technical Stop Coordination

  11. Patrols (forecast @ Jan. 12) • Jan. 12th : Arc 81 • Jan. 13een: Arc 12 • Jan. 15een: Arc 23 • Jan. 19een: Arc 34 + Point 1 + Point 2 • Jan. 20th: Arc 45 • Jan. 22nd: Arc 56 + Point 3 + Point 4 + Point 5 • Jan. 26th: Arc 67 • Jan. 27th: Arc 78 + Point 8 • Jan. 28th: Point 6 • Feb. 1st: Point 7 Technical Stop Coordination