Duke Energy Carolinas Quarterly Stakeholder Meeting. 2 nd Quarter 2011. Independent Entity Services Thursday, May 19, 2011 3:00 to 4:00 p.m. EDT. Agenda. Action Items from December 2, 2010 and March 17, 2011 Transition to AFC Methodology NAESB Update - Wholesale Electric Quadrant
E N D
Duke Energy CarolinasQuarterly Stakeholder Meeting • 2nd Quarter 2011 Independent Entity Services Thursday, May 19, 2011 3:00 to 4:00 p.m. EDT
Agenda • Action Items from December 2, 2010 and March 17, 2011 • Transition to AFC Methodology • NAESB Update - Wholesale Electric Quadrant • Open Access Transmission Tariff Filings • 676-E & 729 OASIS Project • Wrap-up
Action Items December 2, 2010 • Duke was asked to host a meeting between December 2nd and April 1st to address the Flowbased Methodology. • Meeting was held on March 17th • Presentation posted on the OASIS Homepage Documents > Stakeholder Meetings > Stakeholder Presentation held on 03/17/2011 March 17, 2011 • Update to the implementation of Orders 676E/729 regarding NAESB & NERC • Presentation added to today's Agenda
Action Items Customer/Stakeholder Questions submitted by e-mail • Expand on 10 year Forecast of PTP transmission rates under the new formula rate. • Will be addressed during the Tariff Filings discussion today • More discussion of the NAESB plan for capturing full path on an OASIS request. • Service Across Multiple Transmission Systems (SAMTS) will be addressed during today’s NAESB update • Please discuss, if any, plans Duke has to increase transfer capability with SOCO and/or TVA. • North Carolina Transmission Planning Collaborative http://www.nctpc.net/nctpc
Transition to AFC Methodology • Transitioned on March 30th, 2011 • - Originally scheduled for March 29th, 2011 • Delayed transition due to vendor issues being resolved • - Effective date of the NERC Standards on AFC - April 1st, 2011 • Independent Entity perspective – transition went well • - What were your experiences like?
Transition to AFC Methodology • For more detailed information on AFC Methodology • View the following documents posted on OASIS: • Attachment C • http://www.oatioasis.com/DUK/DUKdocs/DukeCarolinaOATT.pdf • ATCID • http://www.oatioasis.com/DUK/DUKdocs/Current_Available_Transfer_Capability_Implementation_Document_-_ATCID.pdf • TRMID • http://www.oatioasis.com/DUK/DUKdocs/Current_TRM_Implementation_Document_-_TRMID.pdf • CBMID • http://www.oatioasis.com/DUK/DUKdocs/CBM_Defining_Statement.pdf • Postback Methodology • http://www.oatioasis.com/DUK/DUKdocs/Current_Postback_Methodology.pdf • Questions on the calculation of ATC • Email:DukeNCIEATC@midwestiso.org • Call: 651-632-8708
NAESB Update Wholesale Electric Quadrant ServiceAcross Multiple Transmission Systems (SAMTS) (OASIS Subcommittee) • Some key aspects • Permits combination of requests and reservations over a time period to be coordinated • Only monthly and longer requests may be included (no restriction on reservations) • Requests must be submitted pre-confirmed • If one request is not accepted in full, customer may reduce or withdraw any and all requests in the group • If all requests are accepted at requested capacity, all requests must be confirmed • Time zone mismatch is permitted
NAESB Update Wholesale Electric Quadrant Service Across Multiple Transmission Systems (SAMTS) – cont. (OASIS Subcommittee) • Recommendation sent to EC for approval • Formal comment period ends June 10, 2011 -- link • Technical conference on 5/20/2011 • WEQ Executive Committee to review & vote on 6/30/2011
NAESB Update Wholesale Electric Quadrant • Network Service on OASIS (NITS) (OASIS Subcommittee) • Significant changes • New templates – Network reservations will need to move to the new system • New Network Customers will need to fill out an on-line application on OASIS • Existing Network Customers will not have to make a new application on OASIS • Target for EC completion in 3rd quarter 2011 • NITS work delayed while completing Service Across Multiple Transmission Systems (SAMTS) • OASIS subcommittee plans to send out draft version for informal comments early June • Next steps are dependent upon magnitude of comments received
NAESB Update Wholesale Electric Quadrant Parallel Flow Visualization for Eastern Interconnect (Business Practices Subcommittee) • The WEQ Executive Committee approved the recommendation for the interim solution on 10/26/2010 (approved recommendation) • The BPS is working on a permanent solution – Options include: • Hybrid Option • Tag all Non-Firm transactions within a BA • Require upload of firmness of transmission service for each running generator every 15 minutes (Generator Prioritization) • Flowgate Allocation based on 2-day ahead, 1-day ahead and hour-ahead projected use • BPS is considering a two-tiered firm curtailment process (first-to-cut / last-to-cut) • Investigating whether this is a policy change (NAESB by-laws prevent subcommittee to recommend policy changes unless directed to do so by the Board) • May require coordination agreements for one BA’s loop flows to be granted first-to-cut priority in another BA
NAESB Update Wholesale Electric Quadrant Electric Industry Registry (EIR) • Transfers TSIN Registry from NERC to NAESB • OATI will administer for NAESB • Functional Specs are completed • Should be in production 1st qtr 2012 (with training and parallel operations 4th quarter 2011) • Data will need to be registered again – not moving TSIN data to EIR • Annual registration fee will be required
Open Access Transmission Tariff Filings In 2011 Duke Energy Carolinas filed an amended OATT to request FERC approval of a new formula rate for Transmission Service • The requested effective date was for June 1, 2011 • There was an intervention in favor of the filing • Radial transmission lines will be excluded from the transmission rate based on a going forward basis • The transmission system peak calculation has changed and will change again on June 1, 2011 • June, 1 2011 new rates will go into effect e-Tariff Public Viewer • http://etariff.ferc.gov/TariffList.aspx
FERC Order 676-E & 729 OASIS Project • FERC 676-E & 729 Ordered on November 24, 2009 • Both orders support the NAESB standards and NERC Requirements and required an implementation date of April 1, 2011 • Re-bid of Partial Service WEQ 001-4.7 through 4.12 • Rebid Price – Complete Rebid MW – Complete • Priorities for Competing Requests WEQ 001-4.14 through 4.16 • NAESB Table 4-3 revised - Complete • Preconfirmed Priority • Duke Business Practice 3.F. Revised to coincide with Table 4-3 • OASIS Home Page General Posting Standards WEQ-001-13 / MOD-001, 004 & 008 • Links, Order and Naming Convention - Complete • ATC Information Link - ATCID, CBMID, TRMID Documents posted – Complete • `
FERC Order 676-E & 729 OASIS Project • ATC Narratives and Questions WEQ 001-14, 15 & 16 • Zero ATC Narratives & Change Narrative – Complete • On OASIS >Go to > Select Narrative Attribute & Filters as desiredfilters • ATC or AFC Methodology Questions • ATC Contact Person posted on OASIS homepage – Complete • Actual & Forecasted Load WEQ 001-17 • Forecasted & Actual Daily Sys-wide (includes Native Load) and Daily Native Peak Load – Complete • On OASIS > Go to > Select > Select Filters as desired • PostbacksWEQ 001-18 • Requires a Postback Methodology document be posted on OASIS under the ATC Information Link – Complete • `
FERC Order 676-E & 729 OASIS Project • Grandfathered Agreements WEQ 001-19 • GFA MW value is required to be queried on OASIS systemdatatemplate – Template Complete • Must be identified in the TP’s ATCID – Complete • Duke does not have grandfathered agreements • Rollover Rights WEQ 001-20 • Duke Business Practice 3.J has been modified to reference the 5yr/1yr requirement • webTrans Rollover functionality – Complete • webOASIS Rollover functionality – Complete • Rollover on Redirects WEQ 001-9.7 • FERC did not incorporate 001-9.7 with reference to Renewal Rights on Redirects • Once adopted by FERC webOASIS and webTrans will be upgraded to meet the requirement
FERC Order 676-E & 729 OASIS Project • Conditional Curtailment Option WEQ 001-21 • CCO applies to requests for Long-term Firm Point-to-Point Transmission Service • Upon request of the Transmission Customer Duke will accommodate CCO • CCO service is treated as firm in calculation of ATC in the full amount reserved • During defined periods CCO service is moved to Transmission Product code = 6-CF • Management and accounting templates and processes – Complete • Use of CBM WEQ 001-22 / MOD-004 • Requires Posting, Tracking, Ability to query, View and Audit the use of CBM on OASIS • Must be Identified in the TP’s CBMID – Complete • Duke Energy Carolinas does not currently allocate Capacity Benefit Margins (CBM) on its ATC Paths
FERC Order 729 • NERC Requirements pertaining to ATC transparency • Available Transmission System Capability - MOD-001-1a • http://www.nerc.com/files/MOD-001-1a.pdf • Capacity Benefit Margin - MOD-004-1 • http://www.nerc.com/files/MOD-004-1.pdf • Transmission Reliability Margin Calculation Methodology - MOD-008-1 • http://www.nerc.com/files/MOD-008-1.pdf • Area Interchange Methodology - MOD-028-1 • http://www.nerc.com/files/MOD-028-1.pdf • Rated System Path Methodology - MOD-029-1 • http://www.nerc.com/files/MOD-029-1a.pdf • Flowgate Methodology - MOD-30-1 • http://www.nerc.com/files/MOD-030-2.pdf
Wrap-up Proposed Next Quarterly Stakeholder Meeting • Thursday, September 15, 2011 – 2 p.m. to 3 p.m. ET Customer Suggested Topics? • This is the forum for discussing emergent topics (Upcoming changes, stakeholder input) Questions and Comments