460 likes | 500 Views
Insights into Google's PUE Results. Spring 2009. Published Google PUE Results. Insights into Google's PUE Results. Today, more details on... Innovations and best practices that enabled the results Measurement method & accuracy Benefits of measuring PUE
E N D
Insights into Google's PUE Results Spring 2009
Insights into Google's PUE Results • Today, more details on... • Innovations and best practices that enabled the results • Measurement method & accuracy • Benefits of measuring PUE • And, a PUE update + a Google server on display
Impact of power & cooling innovations and best practices PUE Components: Typical vs. Google Google Data Center ‘E’ PUE = 1.16 Typical PUE = 2.0 *Reference: Silicon Valley Leadership Group, Data Center Energy Forecast, Final Report July, 2008 Google E Data Center energy-weighted average PUE results from Q2-Q1’09 (to 3/15/09)
Impact of power & cooling innovations and best practices PUE Components: Typical vs. Google Google Data Center ‘E’ PUE = 1.16 Typical PUE = 2.0 85% reduction in cooling energy *Reference: Silicon Valley Leadership Group, Data Center Energy Forecast, Final Report July, 2008 Google E Data Center energy-weighted average PUE results from Q2-Q1’09 (to 3/15/09)
Impact of power & cooling innovations and best practices PUE Components: Typical vs. Google Google Data Center ‘E’ PUE = 1.16 Typical PUE = 2.0 82% reduction in power distribution/backup losses *Reference: Silicon Valley Leadership Group, Data Center Energy Forecast, Final Report July, 2008 Google E Data Center energy-weighted average PUE results from Q2-Q1’09 (to 3/15/09)
PUE Components: Typical vs. Google Result How? Details • Close-coupled cooling • Raise the temperatures • Economizers Cooling energy reduced by 85% This afternoon Power distribution & backup losses reduced by 82% 99.9% efficient UPS Next
Facility UPS Grid AC UPS IT AC Battery Pack Rectifier Inverter
Facility UPS Grid AC IT AC
Facility UPS Grid AC IT AC
Typical Server PSU Motherboard Disk
Google Server PSU Motherboard * DCP++ Disk
Google Server PSU Motherboard Disk * Featured in the Climate Savers Computing (initiative)
Google Server PSU Motherboard Disk
Google Server PSU Motherboard Battery Disk
Google UPS State Diagram Shutdown Timeout or low battery AC on AC back Recharge Discharge AC loss AC loss Battery full Float
Google UPS State Diagram Shutdown Timeout or low battery AC on AC back Recharge Discharge AC loss AC loss Battery full Float
Float: VBATT ≈ 13V RBATT ≈ 100mΩ VSUPPLY ≈ VLOAD ≈ VBATT > 13V AC live, load running, battery float charging VSUPPLY≈ 13V RLOAD ≈ 0.5Ω RCHARGER ≈ 20Ω Discharge Battery leakage (self-discharge) current <0.6mA, leakage power <8mW, efficiency >99.99%
Design Summary and Achievements Examine the entire cluster for a solution, not just the UPS Eliminate central UPS, distribute to each machine Eliminate AC-DC-AC double conversion Small battery, just enough to bridge until generators start up, or clean machine shutdown Incremental deployment of UPS capacity - no waste! Single-voltage PSU is the enabler, also made servers more power-efficient (not included in PUE computation) Real-world measured efficiency of >99.99%
PUE Definition & Trends Green Grid Data Center Efficiency Metric Total Facility Power PUE = IT Equipment Power EPA 2006-2011 PUE Projections Technology Investment Scenario PUE Typical 2006 Data Center 2.0 Current Trends 1.9 2011-Era Data Center Improved Operations 1.7 Best Practices 1.3 State-of-the-Art 1.2 References: The Green Grid, 2007, “The Green Grid Data Center Power Efficiency Metrics: PUE and DCiE,” Technical Committee White Paper, Environmental Protection Agency, ENERGY STAR Program, 2007, “Report to Congress on Server and Data Energy Efficiency”.
PUE Definition & Trends Green Grid Data Center Efficiency Metric Total Facility Power PUE = IT Equipment Power EPA 2006-2011 PUE Projections Technology Investment Scenario PUE Typical 2006 Data Center 2.0 Current Trends 1.9 2011-Era Data Center Improved Operations 1.7 Best Practices 1.3 Remember this number! State-of-the-Art 1.2 References: The Green Grid, 2007, “The Green Grid Data Center Power Efficiency Metrics: PUE and DCiE,” Technical Committee White Paper, Environmental Protection Agency, ENERGY STAR Program, 2007, “Report to Congress on Server and Data Energy Efficiency”.
Green Grid Measurement Accuracy Classifications Level 1 (Basic) Level 2 (Intermediate) Level 3 (Advanced) IT Equipment Power Measurement From... UPS PDU Servers Total Facility Power Measurement From... Data Center Input Power Data Center Input Less Shared HVAC Data Center Input Less Shared HVAC plus Building, Lighting, Security Minimal Measurement Interval Monthly/Weekly Daily Continuous Reference: The Green Grid, 2008, “The Green Grid Metrics: Data Center Infrastructure Efficiency (DCiE) Detailed Analysis,” Technical Committee White Paper
Green Grid Measurement Accuracy ClassificationsGoogle Data Centers: 2+ Level 1 (Basic) Level 2 (Intermediate) Level 3 (Advanced) IT Equipment Power Measurement From... UPS PDU Servers Enabled on newer servers Total Facility Power Measurement From... Data Center Input Power Data Center Input Less Shared HVAC Data Center Input Less Shared HVAC plus Building, Lighting, Security Minimal Measurement Interval Monthly/Weekly Daily Continuous 4 of 6 reported data centers 2 of 6 reported data centers Reference: The Green Grid, 2008, “The Green Grid Metrics: Data Center Infrastructure Efficiency (DCiE) Detailed Analysis,” Technical Committee White Paper
Google Data Center Power Distribution Schematic Medium Voltage High Voltage Utility Distribution Low Voltage Overhead (Cooling plant...) L3 IT Equipment Power Losses & Overhead Power UPS Network MV Switchgear Substation L2 Overhead (CRACs...) UPS Servers UPS Network 99.99% Efficient UPS
PUE Uncertainty <2%Achieved with Accurate Unit Substation Meters Σ Unit Substations + Small Terms Total Facility Power PUE = ~ Σ IT Unit Substations - Small Terms IT Equipment Power Total Data Center power extrapolated to here Overhead (Cooling plant...) L3 IT Equipment Power Losses & Overhead Power UPS Network MV Switchgear Substation L2 Overhead (CRACs...) UPS Servers UPS Network IT power extrapolated to here
Primary Power Measurement PointHigh-Accuracy Metering at the Unit Substations Measurement Uncertainty (CT + PT + Meter) = <±2% Overhead (Cooling plant...) L3 UPS Network MV Switchgear Substation L2 Overhead (CRACs...) UPS Servers UPS Network IT power extrapolated to here
Example: Data Center 'E': PUE = 1.16 ± 1.0%Unit Substation Measurement Uncertainty Unit Substation Measurement 10% of total error Total Data Center power extrapolated to here Overhead (Cooling plant...) L3 IT Equipment Power Losses & Overhead Power UPS Network MV Switchgear Substation L2 Overhead (CRACs...) UPS Servers UPS Network IT power extrapolated to here
Example: Data Center 'E': PUE = 1.16 ± 1.0%Substation-to-Meter Uncertainty Total Data Center power extrapolated to here Overhead (Cooling plant...) M L3 IT Equipment Power Losses & Overhead Power Overhead Unit Substation UPS Network M MV Switchgear Substation L2 Overhead (CRACs...) UPS Servers Substation-to-Meter Losses 2% total power 13% of error UPS Network IT power extrapolated to here
Example: Data Center 'E': PUE = 1.16 ± 1.0%Low Voltage-Side Uncertainty Network 0.2% total power 0.2% of error Total Data Center power extrapolated to here Overhead (Cooling plant...) M L3 IT Equipment Power Losses & Overhead Power Overhead Unit Substation M Network UPS MV Switchgear Substation L2 Overhead (CRACs...) CRACs & Parasitics 3% total power 73% of error UPS Servers M Network UPS Meter-to-IT Losses 1% total power 5% of error IT power extrapolated to here
Example: Data Center 'E': PUE = 1.16 ± 1.0%Summary Uncertainty Component % Unit Substation Energy % Contribution to Total Uncertainty 100% 10% Unit Substation Measurement Substation-to-Meter Estimate 1.9% 13% Network Estimate 0.2% 0.2% CRACs & Parasitics Estimate 3.2% 73% Meter-to-IT Estimate 0.6% 5% • Very accurate measurement of Unit Substation power dominates uncertainty calculation • Estimated components are less accurate, but small in magnitude
January 2009 PUE Results Commissioning & seasonal effects Data published quarterly for all Google data centers with 5+ MW IT load for at least 6 months
Latest PUE Results Continued optimization & beneficial seasonal effects Data published quarterly for all Google data centers with 5+ MW IT load for at least 6 months
PUE ResultsUpdate: Q1'09 to 3/15 Scenario Q1’09 to 3/15 Q4’08 Q3’08 Quarterly energy-weighted average PUE 1.15 1.16 1.23* Trailing twelve-month energy-weighted avg. PUE 1.19 1.20* 1.21 Individual facility minimum quarterly PUE 1.12 1.13* 1.17 Individual facility minimum TTM PUE** 1.15 1.15 1.15 Individual facility maximum quarterly PUE 1.20 1.21 1.30* Individual facility maximum TTM PUE** 1.23 1.24 1.25 *Audit revealed a 1-2% error in previously published results. **Only facilities with at least twelve months of operation are eligible for individual facility TTM PUE reporting
Better than the 2011 EPA State-of-the-Art data center PUE of 1.20 PUE ResultsUpdate: Q1'09 to 3/15 Scenario Q1’09 to 3/15 Q4’08 Q3’08 Quarterly energy-weighted average PUE 1.15 1.16 1.23* Trailing twelve-month energy-weighted avg. PUE 1.19 1.20* 1.21 Individual facility minimum quarterly PUE 1.12 1.13* 1.17 Individual facility minimum TTM PUE** 1.15 1.15 1.15 Individual facility maximum quarterly PUE 1.20 1.21 1.30* Individual facility maximum TTM PUE** 1.23 1.24 1.25 *Audit revealed a 1-2% error in previously published results. **Only facilities with at least twelve months of operation are eligible for individual facility TTM PUE reporting
PUE ComponentsWe Measure by the Minute Daily PUE Overhead – Google ‘E’ Q2’08 Q1’09 Q3’08 Q4’08 Deeper insight into commissioning & seasonal effects
Hourly Average PUE ReportingMinute-by-Minute Measurements Google Data Center ‘E’ Week 1 January 2009 Google Data Center ‘E’ January 2009 Unusual weather impacts chiller runtime
Insights from MeasurementsPUE vs. IT Load Identify commissioning & operational issues, design & deployment plan decisions IT Growth Weather, commissioning & plant scaling
Conclusions • 80+% reduction in power & cooling overhead vs. typical facility • Google UPS solution delivers >99.99% efficiency • Consider options in the market that approach this efficiency • Line-interactive & multi-mode UPS, flywheels, DC distribution • Cooling best practices • Close-coupled cooling, raise the temperatures, & economizers • Continued improvement in latest Google PUE result • TTM Average PUE Trend: • 1.21 (Q3'08) to 1.20 (Q4'08) to 1.19 (to 3/15/'09) • Know your PUE • What's next?
Best practice: minimize chiller operating hours • Best embodiment: chiller-less data centers • Reduce capital costs • Reduce the PUE spikes • Target TTM average PUE ~ 1.1 • Chiller-less Belgium data center operational The Limit: Chiller-Less Data Center
Thank you! Q&A