An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Integrated Water Resources Project Update Presented to: Orange County Board of County Commissioners April 10, 2007

  2. Contents • Background • Project Overview • Upcoming Projects

  3. Contents • Background • Project Overview • Upcoming Projects

  4. BackgroundWater is a Valuable Resource • Central Florida’s water resources are limited • Growth stresses these resources • Need to use water responsibly

  5. BackgroundOngoing Changes • Received SJRWMD groundwater permit • Completing SFWMD groundwater permit • CFCA Action Plan and rulemaking • Groundwater to 2013 • Immediate development of alternative water supplies

  6. BackgroundIntegrated Water Resources Surface Water Supply Reclaimed Water Stormwater Groundwater Supply Aquifer Recharge Conservation

  7. BackgroundIWRP Benefits • Good for the environment • Good for rate payers • Good for the region • Some alternatives may disappear if not made today

  8. BackgroundContract • PB Team selected June 2002 • Contract Y2-903 executed October 2002 • 4-year contract (with two 3-year extensions) • Long-term planning and implementation program • 58 task authorizations issued • $8.9M authorized

  9. BackgroundIWRP • Very capable and diverse team • 4 national and 11 M/WBE firms • Achieving M/WBE goal of 24% participation • High-quality products within schedule and budget • PB Team assistance has significantly increased grant funding • Over $3 million

  10. Contents • Background • Project Overview • Upcoming Projects

  11. Integrated Water ResourcesGroundwater Supply Surface Water Supply Reclaimed Water Stormwater Groundwater Supply Aquifer Recharge Conservation

  12. Groundwater SupplySFWMD Permitting • STOPR Group • Transient groundwater modeling • Aquifer monitoring • Water quality testing • Lake and wetland monitoring

  13. Integrated Water ResourcesReclaimed Water Surface Water Supply Reclaimed Water Stormwater Groundwater Supply Aquifer Recharge Conservation

  14. Reclaimed Water • 100% reuse since 1985 • 51 mgd in 2006 • Irrigation • Industrial • Aquifer recharge • Wetlands • Invested over $150 million

  15. Integrated Water ResourcesSurface Water Supply Surface Water Supply Reclaimed Water Stormwater Groundwater Supply Aquifer Recharge Conservation

  16. Surface Water Supply • SJR/TCR Feasibility Study Underway • Water quality assessments • Plant and storage siting • Southeast Water Supply Augmentation Project • ERP and ROW permits obtained • Completing WUP • Pilot testing for compatability

  17. Integrated Water ResourcesStormwater Surface Water Supply Reclaimed Water Stormwater Groundwater Supply Aquifer Recharge Conservation

  18. Stormwater • Industrial use since July 2005 • Approximately 2 mgd • Evaluating use of stormwater site for irrigation • Partnering with Public Works • Feasibility study for use of OCCC runoff

  19. Integrated Water ResourcesAquifer Recharge Surface Water Supply Reclaimed Water Stormwater Groundwater Supply Aquifer Recharge Conservation

  20. Aquifer Recharge • Lake Marden Project • Startup in 2006 • 3.0 mgd • OWGR RIB Site • Startup in 2006 • 0.3 mgd capacity

  21. Integrated Water ResourcesConservation Surface Water Supply Reclaimed Water Stormwater Groundwater Supply Aquifer Recharge Conservation

  22. Conservation • Reduction in water demands • Education • Fixture replacement • Ordinances • Watering restrictions • Rate structure • Water audit

  23. Orange County Cocoa Reedy Creek Toho Water Supply Authority Regional Partnerships • CROT Group - April 2005 • SJR/TCR MOA – November 2005 • STOPR Group – December 2006 • Cooperative water supply solutions

  24. Contents • Background • Project Overview • Upcoming Projects

  25. Upcoming Projects • Integrated Resources Plan • Expanded monitoring network • Additional permit compliance • Reclaimed water and aquifer recharge • Reclaimed water augmentation • Alternative water supplies

  26. Upcoming ProjectsImplementation • Eastern wellfield expansion • Western wellfield expansion • Southern wellfield expansion • Southwest wellfields under construction • ASR Test Well • Southeast Water Supply Augmentation • South-East Connector Pipeline

  27. Integrated Water Resources ProjectA Vision for the Future Surface Water Supply Reclaimed Water Stormwater Groundwater Supply Aquifer Recharge Conservation

  28. Integrated Water Resources Project Update Presented to: Orange County Board of County Commissioners April 10, 2007