MICE Funding Agency Committee PM report

MICE Funding Agency Committee PM report. Overview Organisation and project management Schedule reconstruction The Step IV subsystems. Andy Nichols, STFC, FAC, 15-7-11. Overview. Muon beamline reliable, decay solenoid, magnets and detectors working routinely

denna
Download Presentation

MICE Funding Agency Committee PM report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICE Funding Agency CommitteePM report • Overview • Organisation and project management • Schedule reconstruction • The Step IV subsystems Andy Nichols, STFC, FAC, 15-7-11

  2. Overview • Muonbeamline reliable, decay solenoid, magnets and detectors working routinely • Target development is going very well, Re-engineered configuration now accepted by ISIS as baseline – a crucial step • FC #1 manufacture is progressing well, first coil wound, delivery Q3/4, 2011 • Spectrometer solenoids – re-working underway, new confidence in delivery dates (June 2012) • 2MVA substation upgrade – completed ahead of schedule and working • PPS - now in use • First EMR planes installed in June, running successfully right now • Coupling magnets, first coil wound, test is critical to future plans and decision points, test in US likely, CC delivery plan must be addressed urgently

  3. Organisation and Project Management • Some changes to the project management: • UK project re-modelled: • UK Project Manager - Alan Grant, DL • System Engineer RAL – Tim Hayler • Project Associate – Andy Lintern • MICE Project: • Project Manager – Andy Nichols • Integration Engineer – Jason Tarrant • Schedule co-ordinator – Gail Hanson • MICE Magnet co-ordination team • Engineering – Roy Preece – resident at LBNL since April 1st • Magnetic – Mike Courthold – based at RAL • Very unfortunately the Hall Manager, Willie Spensley departed in May. AN is default, supported by Vishal Francis. This is an unsatisfactory arrangement.....! • Vital that STFC fills the vacancy – this is a major safety liability

  4. Reconstructing the schedule • Now accepted that we go straight to Step IV • More subsystem detail has been added to top level schedule – see later • Aim is to achieve some running with Step V before long ISIS shutdown in August 2014 • This is not a firm commitment; it’s critically dependent on the Coupling Coil delivery programme • But if running is not possible with Step V, the project will consider moving to Step VIas soon as possible after the shutdown to advance the schedule

  5. MICE Top-Level Project Schedule • Step IV • Step V • Revision date: 17th June, 2011 • Note: items in red text are key schedule drivers • Items in orange text are high risk items • Items in Green text are complete

  6. STEP IV Step IV ready...Q3, 2012

  7. STEP V Step V ready... Q2, 2014

  8. Step IV subsystemsSpectrometer solenoids Courtesy, Steve Virostek • Workshop held in LBNL during May • Collected all known information on the spectrometer solenoids • Focussed on: • Quench protection/detection • Heat load calculations • Assembly/MLI application • Manpower • Shipping • Representation from s/sol review committee, LBNL team and MIT staff • Most issues are closed now, delivery plan very well constructed and credible • Repair has effectively begun

  9. Step IV subsystemsSpectrometer solenoid • What are we doing? • Better understanding of 4.2K heatload: • Pumping capability and monitoring improved • Better instrumentation • Vent lines baffled • MLI on cold mass improved • Radiation shield made of higher conductivity (1100) series alum • Better connections of rad. shield to first stage of CCRs • 5+1 cooler configuration accepted as baseline • Engineering drawings and 3D CAD models rigorously updated - now we know where we are starting from

  10. Step IV subsystemsSpectrometer Solenoid Definitive 5+1 CCR layout

  11. Revised manpower plan Manpower The following individuals are part of the Spectrometer Solenoid team: This is great news – a major step forward Steve Gourlay – LBNL AFRD Division Director - LBNL technical contact for Spectrometer Solenoid and Coupling Coil magnets - oversight of the LBNL Spectrometer Solenoid team - contact for the DOE Office of High Energy Physics Steve Virostek - Sr. Mechanical Engineer - overall project management • some oversight of magnet assembly and training - documentation Tapio Niinikoski - Sr. Cryogenic Engineer - CERN retiree, hired 1/2 time by LBNL • magnet design analysis and modification - some oversight of magnet assembly and training • magnet training oversight Dennis Calais - Cryogenic Technician • on site at Wang NMR during assembly • Mainly working on instrumentation and cryocoolers Roy Preece - Mechanical Engineer (RAL) - oversight of magnet assembly - magnet training oversight - integration and documentation Nanyang Li - Mechanical Engineer - oversight of magnet assembly - magnet training oversight - documentation Soren Prestemon - Cryogenic Engineer - magnet design analysis - design modification recommendations - occasional oversight of magnet assy Heng Pan - Cryogenic Postdoc - quench analysis - radiation shield eddy current and force analysis

  12. Step IV subsystemsAFC module Courtesy, Tom Bradshaw • FC #1 is in final stages at Tesla Engineering • Coil is wound, experts agree that it went very well • Cryocooler performance is being physically verified now - important • Some design issues with outer vac vessel and cold mass supports need sorting out • Tesla are re-organising their staffing on the project, good news • Plan to ship to RAL around September/October 2011 • Initial testing, powering and mapping will be in building R9 • Absorber module #1 was delivered form KEK last month, effectively ready for use – now in safe storage

  13. Step IV subsystemsAFC module

  14. Step IV subsystemsLiquid hydrogen delivery system Courtesy, Matt Hills • Four parallel activities going very well: • R&D vessel, pipe and valve work in MICE hall • Venting, vacuum and extraction system outside • Control engineering • Safety planning and admin • R&D vessel now installed and liquefying helium successfully • Process now entirely operated by the control system – great effort from DL group • Exterior work well underway – large fans have been tested, most civil engineering work is done • Safety & Admin: • SuccessfulLHe test needed for input to Hydrogen safety case • Pre-operation safety review being organised now, aiming for later this year • Formal monthly exchange with ISIS Safety

  15. Step IV subsystemsLiquid hydrogen delivery system