Airframe Measurements. P09233 – Managerial Design Review. Team Structure. Team Lead: Michael Skube – Mechanical Engineer Co-Team Lead: J ames H unt – Mechanical Engineer Electrical Lead: Joseph Peters – Electrical Engineer Kevin Li – Electrical Engineer
E N D
Airframe Measurements P09233 – Managerial Design Review
Team Structure • Team Lead: Michael Skube – Mechanical Engineer • Co-Team Lead: James Hunt – Mechanical Engineer • Electrical Lead: Joseph Peters – Electrical Engineer • Kevin Li – Electrical Engineer • William Atkinson – Mechanical Engineer • Heidi Morgan – Electrical Engineer • John Isely– Mechanical Engineer
Measurements Box Design GPS IMU Altimeter Microcontroller Ultrasonic
Projected Project Costs • Building a second Measurements Box: • Total Project Cost: $1900(includes IMU cost ~$500) • Total Project Cost: $1400 (assumes donated IMU) • Measurements Box BOM: • $1100(includes IMU cost ~$500) • $600(assumes donated IMU) • The Current Project Cost: $910
Current Risks • Ability to Program the MCU • Ability to Interface with the IMU • Ability to Test the IMU – MAV Test Stand • GPS Calibration • Airframe A Flight Testing
Action Items • Program MCU • IMU Testing • Further Sensor Testing • Pitot Static Tube Mounting Design • Part Drawings • Assembly Instructions • Component Documentation
Schedule - SDII Part Design Test Pitot Static Tube Program MCU Phase I System Testing Test Altimeter Document BOX Build
Schedule - SDII Drawings Documentation Refine Programming Phase II System Testing Final Documentation Documentation