By Colin Phan, Ken Lee Marquez, Gyu Beom Choi Total server implementation
Agenda • Introductions • Project Information • Challenges • Successes • Lessons Learned • Budget • The Final product • Acknowledgements • Conclusion • Questions
Introductions • Ken Lee Marquez – Computer Systems Major • - Programmer • Colin Phan – Computer Systems Major • Server Administrator, Security • Gyu Beom Choi – Computer Systems Major • Programmer, Security
Project Information • Develop a functional Intranet • Private Network • Company Website
Challenges • Working with real-time hardware • Time Management • Website Layout and Contents • Syncing data with SQL database • Security • Programming • Configuration errors (apache, Microsoft exchange)
Solutions • Implemented services on a VM • Followed Gantt Chart • Scheduled extra work days • Conducted research for web programming, security • Trial and error • Resort to back ups
Lessons Learned • Time Management • Communication • Making Back ups regularly
Budget • $12,000 • Total cost of project = $6596 • Variance = $12,000-$6596 = $5404
Final Product • Server: • DNS, DHCP • Active Directory • Apache HTTP Server - Website: login/register/upload/download/order form • Microsoft Exchange Server configured with outlook - mySQL Database sync
Acknowledgements • Colin Chamberlain • Jason Fisher • SAIT