K. Long, 7 September 2009. Target:. — T1 continues to run smoothly details in MOM’s report. Initial schedule for T2 re-instatement:. T2 refit: Schedule prepared by JT discussed by Target group and is being revised Still expect T2 mid October Expect schedule by end of this week
E N D
K. Long, 7 September 2009 Target: — T1 continues to run smoothly details in MOM’s report
Initial schedule for T2 re-instatement: • T2 refit: • Schedule prepared by JT discussed by Target group and is being revised • Still expect T2 mid October • Expect schedule by end of this week • Parts in manufacture, preparations for pieces and processes sourced from ‘outside’ in hand • T3 and bearing test programme: • Schedule prepared by JT discussed by Target group and is being revised • Expect schedule by end of the week • J.Tarrant, who has done an excellent job, is moving to ATLAS: • Phased transition, AN and KL working out how to replace him