Non Domestic RHI: Biogas. 17 th June 2014. Overview. Biogas specific RHI Key eligibility criteria Determining capacity Commissioning and CHP conversion What comprises an installation Heat provided to biogas production Payment calculation – worked example Sustainability.
E N D
Non Domestic RHI: Biogas 17th June 2014
Overview Biogas specific RHI • Key eligibility criteria • Determining capacity • Commissioning and CHP conversion • What comprises an installation • Heat provided to biogas production • Payment calculation – worked example • Sustainability General RHI • Key eligibility criteria • Eligible Heat Uses • Metering and payments • Ongoing obligations • Preliminary accreditation • Additional capacity • Degression
Key Eligibility Criteria • Installed/first commissioned on or after: • Biogas capacity <200kWth- 15 July 2009 • Biogas capacity ≥200kWth- 4 December 2013 • Equipment new at time of installation • Grant funding from a public body towards the eligible installation must be • Repaid to the grant making body, or • Value of grant funding is deducted from payments • Medium of heat transfer must be liquid or steam - no direct air heating
Eligible Heat Uses • In a building • Space heating • Water heating • Carrying out a process • Other than in a building • Commercial cleaning • Commercial drying
Defining a building “any permanent or long-lasting buildingor structure of whatever kind and whether fixed or moveable which, except for doors and windows, is wholly enclosedon all sides with a roof or ceiling and walls” Typically includes: • Silos • Distillation columns • Anaerobic digesters Typically excludes: • Tents • Polytunnels • Open sided barns or sheds 5
Metering • Liquid or steam • Meter standards – MID Conformity, Class 2 Accuracy • Appropriately calibrated and installed • Heat loss assessments • Proxy measurements • (natural) gas and electricity • assumed 100% conversion to heat
Payment = • Meters must positioned in order to determine the relevant quantities: • B - the kWhth of heat generated by that plant which is used for eligible purposes • C - the heat in kWhth directed from the installation or delivered from any other source to the biogas production plant which produced the biogas combusted in the relevant quarterly period (other than heat contained in feedstock to produce biogas by anaerobic digestion).
Periodic data and payments • Periodic data: • Heat output data • Supporting meter readings • Fuel data (depending on installation type) • Payments: • Based on quarterly data • E.g. ‘date of accreditation’ on 1st July 2014, • first payment for period 1st July – 1st Oct; • Second for 1st Oct– 1st Jan... • Installation capacity ≥1MWth - submit meter readings monthly • Installation capacity <1MWth - submit meter readings quarterly
Ongoing Obligations • Feedstock records • Anaerobic digestion: solid biomass, solid waste, liquid waste • Gasification or pyrolysis: solid biomass, waste • Metering • Continuously operating, properly maintained, re-calibrated every 10 years • Supporting invoices, receipts, certificates. • Must not generate heat for the predominant purpose of increasing payments. • Should supply a heat use that would otherwise be met by other means • Installations will be audited
Preliminary accreditation • Available for all biogas installations not yet commissioned • ‘In principle’ agreement giving assurance that, once built, full accreditation will be granted provided: • The installation was built in line with the details originally submitted • No Regulatory changes have been made such that if the preliminary application had been made after the regulatory changes, it would have been refused. • Need to demonstrate genuine intent: • Planning permission, • Evidence showing planning permission is not required • Does not guarantee tariff
Additional capacity • Available to plant: • First commissioned after the date on which the original RHI installation was commissioned • Uses the same source of energy and technology • Forms part of the same heating system Additional capacity first commissioned within 12 months of original installation being commissioned Additional capacity first commissioned more than 12 months after the original installation was commissioned n.b. Illustrative purposes only, future tariffs may not be as shown
Degression • Degression is a long term budget control mechanism where reductions can be applied to an individual tariff, or tariffs if certain financial triggers are met at each quarterly review period relating to: • Overall spend on the scheme • Individual technology spend on the scheme • Tariff reductions only impact new applicants or those participants installing additional capacity. Changes will be made to the calculation methodology.
Biogas specific criteria • Tariff banding applies: • Small installations (<200kW) will receive 7.5p/kWh. • Medium installations (200-599kW) will receive a tariff of 5.9p/kWh. • Large installations (600kW and above) will receive a tariff of 2.2p/kWh. • Installations 200kW and above must be installed and first commissioned from 4th December 2013 to take advantage of this support • The provisions and tariffs will apply to heat only installations as well as biogas CHP installations. CHPQA accreditation is not necessary. • Installations over 200kWth will be able to apply for preliminary accreditation in the same way as existing biogas installations.
Capacity • Defined in Regulations as : “total installed peak heat output capacity of the plant” • For CHP this relates to the total heat output of the equipment in the form of usable hot liquid or steam • E.g. Installation comprised of a CHP engine with 150kW water jacket and 150kW exhaust flue heat exchanger would be considered 300kW. • Where a water jacket is used for cooling of the engine, we would generally consider this to be included as part of capacity, unless we are satisfied that any heat associated with this water jacket could not be used on the heating system.
Commissioning • Installations must be installed and first commissioned on or after: • 15th July 2009 (for <200kW) • 4th December 2013 (for 200kW and above) • CHP installations : • Where a plant converts from electricity only to CHP, we will take the conversion date to be the commissioning date. • 15th July 2009 (for <200kW) • DECC have stated the policy intention is that first commissioning as a CHP system >200kW must also be on or after 4th December 2013. The Regulations make reference to 2009 but please note this is a drafting error and will be corrected at the earliest opportunity. • Plant cannot be considered ‘first commissioned as a CHP system’ if heat is already being recovered and used, e.g. to heat a digester. • Combustion units: • A CHP installation can add a new ‘combustion unit’ to an existing system and receive support on heat produced by the combustion unit. This is allowed even if the rest of the installation is ineligible. • Must be commissioned as part of a CHP system on or after 4th December 2013
Combustion units Electricity Fossil fuel plant CHP Turbine Fossil fuel plant New biogas plant Heat Eligible plant
Heat provided to biogas production plant • Can be considered an eligible heat use • Any heat demand prior to combustion that may result in an increase in potential heat output of a given installation will be considered as ‘heat provided to the biogas production plant’. • Generally, this would include: • Thermal hydrolysis • Desulphurisation • and exclude • Pasteurisation • Will be assessed case-by-case • In discussion with DECC regarding ‘apportioning’ of this heat.
A -tariff • B - the kWhth of heat generated by that plant which is used for eligible purposes • C - the heat in kWhth directed from the installation or delivered from any other source to the biogas production plant which produced the biogas combusted in the relevant quarterly period (other than heat contained in feedstock to produce biogas by anaerobic digestion).
Heat generated by eligible installation x Heat used for eligible purpose Heat generated by all plant B =
Sustainability • Sustainability requirements are now due to take effect from Autumn 2014 and will apply to all participants (old and new) generating heat from biomass or biogas • From Autumn 2014 participants will need to demonstrate that their fuel meets a greenhouse gas (GHG) lifecycle emissions savings (of 60% compared with the EU fossil heat average) • Land criteria requirements are expected to be introduced by April 2015 • The Biomass Suppliers List is intended to be open for applications from biomass suppliers in Spring 2014 • Participants will be able to demonstrate compliance in one of three ways: • - Self-reporting • - Sourcing from a supplier registered on the Biomass Suppliers List (BSL) (or equivalent) • - Register with the BSL (or equivalent) as a self-supplier (source woody biomass from their own estates)