1 / 10

Air Quality Aspects for Construction Projects

Air Quality Aspects for Construction Projects. Subcontractor On Boarding Series 05/2012. Air Emissions from SLAC Operations. ESH Manual Chapter 30: Air Quality Exhibits for specific program elements Templates for recordkeeping included SLAC has an “umbrella” air permit

devin-orr
Download Presentation

Air Quality Aspects for Construction Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Air Quality Aspects for Construction Projects Subcontractor On Boarding Series 05/2012

  2. Air Emissions from SLAC Operations • ESH Manual Chapter 30: Air Quality • Exhibits for specific program elements • Templates for recordkeeping included • SLAC has an “umbrella” air permit • Covers all onsite emissions from various sources • Combustion • Chemical Treatment • Evaporation / Curing • Refrigeration / Insulation

  3. Typical Emissions Sources • Combustion • Generators/ Heavy Equipment • Chemical Treatment • Solvent cleaners, degreasers • Evaporation / Curing • Paints, coating, epoxies, adhesives, etc. • Refrigeration / Insulation • Freon, Off gassing

  4. SLAC Air Quality Programs • Permitting of New Sources • Non-SLAC Portable Equipment • Demolition / Renovation • No-Idling Policy • Hazmat Purchasing • Recordkeeping & Submittals

  5. Non-SLAC Portable Equipment • Regulated under statewide program • Voluntary program • Focus on diesel engines >50 HP • Registered for 3 years • Operate equipment anywhere in CA • Provide copy of PERP registration to SLAC • Portable Equipment Registration Program (PERP)

  6. Demolition / Renovation • Notify the Bay Area Air Quality Management District (BAAQMD), if required • Notification fee paid by ESH • Include project start and end dates • Notice signed by person performing work • Mandatory waiting period • 10 working days

  7. Renovation: Removal of As-containing material (ACM) from a structural member Sheet rock, floor tiles Notify BAAQMD of all renovations exceeding thresholds with friable asbestos Demolition / Renovation Demolition: Removal of a load-bearing structural member • Buildings, usually • Notify BAAQMD of all demolitions -- with or without asbestos!

  8. No-Idling Policy Statewide law for commercial vehicles SLAC Policy: Turn engines off • Whenever vehicle is stopped for >60 seconds • Applies to all vehicles while onsite • Personal , commercial and industrial • Exemption for special circumstances • Emergency vehicles

  9. Hazmat Purchasing • Haas system provides ‘single portal’ • Paints, coatings, solvents, epoxies, adhesives Be aware of better alternatives • Environmentally Preferable Purchasing (EPP) • Volatile Organic Compounds (VOC) content • “Low VOC” – typically, <300 grams/liter • Ozone-Depleting Substances (ODSs) • Greenhouse gases (GHGs) • Allowances for mission-critical operations

  10. Recordkeeping and Submittals • Prior to start of work • Pre-Work Hazmat List, w/MSDSs • During project: monthly logs • Hazmat use • Fuel consumption • Operating hours for portable equipment • Upon completion of work • Chemical Use Report • Templates available on ESH website

More Related