1 / 37

ILC Mechanical & Electrical Review

ILC Mechanical & Electrical Review. Conventional MECHANICAL System Design Summary Emil Huedem , FNAL Lee Hammond, FNAL Parsons Mechanical Team (Tim Sheehan, Jerome Burke, Michael Painter) March 21, 2012. INTRODUCTION Process cooling water , ventilations, and sump system

didina
Download Presentation

ILC Mechanical & Electrical Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ILC Mechanical & Electrical Review Conventional MECHANICAL System Design Summary Emil Huedem, FNAL Lee Hammond, FNAL Parsons Mechanical Team (Tim Sheehan, Jerome Burke, Michael Painter) March 21, 2012

  2. INTRODUCTION • Process cooling water, ventilations, and sump system • Cryogenic system is not included but only it’s final heat rejection (cooling towers) • Sizing (&costing) for full power first (adjustment to lower power-baseline will be done later) • Criteria/Load tables used was before July 2011. Many changes since • Parsons did the concept & costing for both KCS-ML and DRFS-ML. Only KCS is considered in this review • Costed each system-bottoms up, per shaft, per system (in RDR scaled from shaft 7) • Some items just have cost ($/m fire suppression, $ target ventilation, $laser room HVAC, $compressed air from RDR)

  3. WBS • Follows the RDR WBS system • Specific wbs only 1.7.3 AIR TREATMENT (HVAC) 1.7.4 PIPED UTILITIES 1.7.5 PROCESS COOLING WATER

  4. Load Table progress –Basis for current Concept design RECENT CHANGES ARE NOT INCLUDED HERE

  5. CRITERIA / TECHNICAL LOADS In Central Region ML loads comes from RF system & racks For KCS, more than 60% of ML loads are in the surface Some key criteria/input Various area system heat load tables (except e-) Various delta T per users Machine design to run all year or anytime in a year DR & BDS has tight space (air) stability Lcw/process water supply stability not critical 150 gpm per mile inflow for groundwater RECENT CHANGES ARE NOT INCLUDED HERE

  6. PROCESS WATER PLANT LOCATIONS & LOADS-KCS(Technical components only shown) PM-7cr PM+ 7cr PM-12 PM-9 PM-7 PM+7 PM+9 PM+11 PM-11 PM-10 PM-8 PM+8 PM+10 PM+12 5876 Central Region 570 1976 570 2092 2092 1823 2092 2092 2092 2092 1046 2092 2092 1046 D R A F T 7/19/2011 E. Huedem RECENT CHANGES ARE NOT INCLUDED HERE

  7. ML-KCS Process water System SURFACE (per RF) ~62.5 KW to LCW 3 KW to CRAC ~10.2 KW to air (ventilation) 7 7 11 11 12 10 9 9 8 12 10 8 RECENT CHANGES ARE NOT INCLUDED HERE

  8. ML-KCS Process water System SURFACE RF MAIN CW SYSTEM TUNNEL CAVERN

  9. ML-KCS Process water System (simplified) 83/98F (28/37C) (15 F DT) 85/100F (29/38 C) (15 F DT) FCU 85/95F (29/ 35 C) (10 F DT) LCW 85/107F (29/41.7 C) (22 F DT) 104F (40 C) Space

  10. INTERFACE (KCS) (ONLY THE SUPPLY PIPE ARE SHOWN FOR CLARITY) ONE 1” VALVE TAP FOR RACKS PER RF (5 KW PER RF) @ 10 F dt 3.4 GPM [ from RLarsen Mar252010 GDE presentation & RLarsen MAY162011 email confirmation] LCW BOOSTER PUMP (1 PER 2 RF) 24 GPM, 1 BHP, 1-1/2”PIPE 1-1/4” (4.5 GPM) TO FANCOILS 1qty/RF 12” LCW MAIN SUPPLY PIPE 1 RF ( 3 CRYOMODULES) 1-1/4” PIPE HEADERS AFTER BOOSTER PUMPS INCLUDED (assumed qty VALVE TAPS) ~ 38.75 m SEP 23 2011

  11. Central Region Process water System COOLING TOWERS CHILLERS To MAU MAIN CHW SYSTEM PROCE WTR PUMPS CAVERN LCW SKID TUNNEL

  12. Central Region Process water System (simplified) 85/100F (29/38 C) (15 F DT) 60/82F (15 / 28 C) (22 F DT) PW 65/85F (18/13 C) (20 F DT) FCU 65/75F (18/24 C) (10 F DT) 85F Space LCW 70/92F (21/33 C) (22 F DT)

  13. D R A F T SEP 2 2010 Central Region LCW SKID LOCATIONS & FEED Length shown are approximate for process water distribution purposes only & doesn’t reflect the actual beamlength PLTR 500 KW LCW placeholder PM-7 40KW Heat Loadto Air 234m 480m 434m 487m 270m 512m 353m 270m 353m 431m 35m END OF MAIN LINAC Fast Abort PreUndulator Undulator PTran 2 5 GeV Booster Section 400 MeV Pre-Acc Positron Capture Auxiliary Source Target PTran1 1,010 m 683 m 74 m 17 m 512 m 313 m 70 m 35 m 84.9 KW LCW 193 KW LCW 14.7 KW LCW 657 KW LCW (excl dumps) 29 KW LCW (excl dumps) 104 KW LCW 310 KW LCW (excl dumps) 2,023 KW LCW (excl dumps) 90.2 KW Heat Load to air Beam Tunnel 0 KW Heat Load to air Beam Tunnel 1.8 KW Heat Load to air Beam Tunnel 0.9 KW Heat Load to air Beam Tunnel 101.5 KW Heat Load to air Beam Tunnel 8.6 KW Heat Load to air Beam Tunnel 0 KW Heat Load to air Beam Tunnel 7.4 KW Heat Load to air Beam Tunnel 0 KW Heat Load to air Service Tunnel 0 KW Heat Load to air Beam Tunnel 4.6 KW Heat Load to air Service Tunnel 2.3 KW Heat Load to air Service Tunnel 25.5 KW Heat Load to air Service Tunnel 86.8 KW Heat Load to air Service Tunnel 21.4 KW Heat Load to air Service Tunnel 204.1 KW Heat Load to air Service Tunnel 34.5 KW Rack Heat Load At Service tunnel 92 KW Rack Heat Load At Service tunnel

  14. INTERFACE (Central Region)(ONLY THE SUPPLY PIPE ARE SHOWN FOR CLARITY) 14” PROC WATER (PW) MAIN SUPPLY PIPE HX FANCOILS LCW SKID SERVICE TUNNEL 2” LCW PIPE (to Power Supplies) 2” LCW PIPE VARIOUS VALVE TAPSassumed 2” PW 4” LCW (298 gpm) 1-1/2” PW 1-1/2” PW FANCOILS BEAM TUNNEL 3” LCW PIPE (to Magnets) 3” LCW PIPE VARIES SEP 23 2011

  15. Damping Ring Process water System (PMB shaft)

  16. Damping Ring Process water System (PMC shaft)

  17. Damping Ring Process water System (Simplified) PMC-0 Tower 83/98F (15oF DT) 28/37o C Chiller 60/90F (30oF DT) 15.6/32o C Wiggler LCW 65/105F (40oF DT) RF LCW 63/106F (43oF DT) 18/41 oC 17/41o C Wiggler Wiggler 84oF Space 29 oC ~23 oC 73F return 52/62F to FCU 11/17 oC 65/94F magnet&PS (65/105 magnets) 18/34 oC 18/41o C HX 52/73oF (21oF DT) 11/23o C Chiller 50/71oF (21oF DT) 10/22 oC PMB-0

  18. INTERFACE (Damping Ring)(ONLY THE SUPPLY PIPE ARE SHOWN FOR CLARITY) 6” (52F) LCW FANCOILS 4” (65F) LCW Will assume minimum number of valves taps Feed from PMB-0 to beam tunnel (approx 1.3 Km) 6” (52F) LCW from PMB-0 FANCOILS Will assume minimum number of valves taps 8” LCW TO WIGGLERS from PMC-0 Feed from PMC-0 to wiggler area (approx 204m x 2)

  19. IR & Main Dump Process water System (simplified)

  20. AIR TREATMENT SCHEME 20Kcfm 40Kcfm 60”x54” supply & return duct in shaft 40Kcfm 80Kcfm 80Kcfm 80Kcfm Typical Ventilation Equipment on each shaft Supply air to use the space below floor (non-ducted) Ducted supply air to each “Refuge Area Alcove” • ~1mph airspeed (~2 ac/hr)

  21. PLUMBING SCHEME • 150 gpm per mile inflow

  22. OVERHEAD (full power loads) 0.08 w/w at peak

  23. ADJUSTMENT TO FINAL NUMBERS PARSONS’s MECH COST EXCEL PARSONS’s ELEC COST EXCEL • Separate cost by Area systems • Add missing wbs • Adjust IR water plant cost • Adjust Ventilation cost • Add laser rooms • Add Fire suppression • etc CIVILCOST EXCEL • Scale per new load/criteria • Adjust cost to low power ADJUSTED MECH COST EXCEL ADJUSTED ELEC COST EXCEL OVERALL CFS COST EXCEL (AMERICAs) LINK or INPUT ? Add EDMS references Add other mandatory input Risk Basis (high & low %) GERRY DUGAN’s EXCEL FILE ( CEM)

  24. 28F dt • Stacking of loads in surface RF considered but not used • Not much first cost savings, (10” to 8” pipe mains) vs effect of high space temperature

  25. Chiller vs w/out chiller on DR

  26. POST RDR • About 50+ list from V.E. in Nov 2007, List from value engineering sessions in Nov 2007. Some appear to have real good cost reduction potentials. • Project focus on “first-cost” reduction • Talks located in http://ilcagenda.linearcollider.org/conferenceDisplay.py?confId=2328 • Description of each list, but no detailed evaluation • Specific items selected by project to be evaluated in 2008 • Elimination of centralized chilled in ML • Higher RF water delta T • Warmer tunnel temperature during operation and local cooling during maintenance • Other pipe materials • discussions during this effort effort • Centralized LCW vsprocesswtr/skid • Tunnel booster pump footprint=2/rf • (stacking of loads) Surface RF High delta T 28 Fdtvs 15F = not much cost savng • Surface RF ventilate or part of rack • DR chilled water or not

  27. BACKUP SLIDESsome LOAD TABLES SEP 29 2011 Conv Mechanical Updates E.Huedem / L. Hammond Backup Slides

  28. MAIN LINAC KCS Mar 23 2011 Load to LCW per Ray Backup Slides

  29. POSITRON SOURCE (1 of 3) Backup Slides

  30. POSITRON SOURCE (2 of 3) Backup Slides

  31. POSITRON SOURCE (3 of 3) Updates recently Added ~200KW New totals = 6460 Backup Slides

  32. BDS Backup Slides

  33. Backup Slides

  34. 40 265 20 78 40

More Related