1 / 4

Tracker and Preshower detector cooling plant F545/TS/CMS Status report

Tracker and Preshower detector cooling plant F545/TS/CMS Status report. December the 7th 2006 P. Tropea. General layout . Brine circuit: Tyfoxit -50 1 heat exchanger with the chiller circuit 2 pumps (redundancy) 7 heat exchanger in the detector units .

diella
Download Presentation

Tracker and Preshower detector cooling plant F545/TS/CMS Status report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tracker and Preshower detector cooling plantF545/TS/CMSStatus report December the 7th 2006 P. Tropea CMS Tracker cooling - status report

  2. General layout Brine circuit: Tyfoxit -50 • 1 heat exchanger with the chiller circuit • 2 pumps (redundancy) • 7 heat exchanger in the detector units • 3 cooling loops in cascade (chiller, brine, fluorocarbon) • 3 regulation systems for the distribution Temperature (H20 flow rate, brine flow rate, C6F14 heating up) CMS Tracker cooling - status report

  3. What is there • Chiller and brine circuits installed in USC55 in April 06 • Thermal Screen and Preshower cooling units installed in UXC55 in August 06 • Silicon strip and Pixels units installed in UXC55 in November 06 • Electrical and control rack in USC55 in October 06 • Piping and cabling between caverns ready CMS Tracker cooling - status report

  4. What has to be done… • Pneumatic pipe installation (CMS) – Jan 07 • C6F14 cooling system connections – Dec 06 • Chiller tests – Jan 07 • C6F14 cooling plant tests – Feb/Mar 07 • Piping btw cooling and Tracker (Tender)– Apr 07 • Commissioning with Tk on – Jun 07 • C6F14 recuperation system – Apr 07 CMS Tracker cooling - status report