Tracker and Preshower detector cooling plant F545/TS/CMS Status report. December the 7th 2006 P. Tropea. General layout . Brine circuit: Tyfoxit -50 1 heat exchanger with the chiller circuit 2 pumps (redundancy) 7 heat exchanger in the detector units .
E N D
Tracker and Preshower detector cooling plantF545/TS/CMSStatus report December the 7th 2006 P. Tropea CMS Tracker cooling - status report
General layout Brine circuit: Tyfoxit -50 • 1 heat exchanger with the chiller circuit • 2 pumps (redundancy) • 7 heat exchanger in the detector units • 3 cooling loops in cascade (chiller, brine, fluorocarbon) • 3 regulation systems for the distribution Temperature (H20 flow rate, brine flow rate, C6F14 heating up) CMS Tracker cooling - status report
What is there • Chiller and brine circuits installed in USC55 in April 06 • Thermal Screen and Preshower cooling units installed in UXC55 in August 06 • Silicon strip and Pixels units installed in UXC55 in November 06 • Electrical and control rack in USC55 in October 06 • Piping and cabling between caverns ready CMS Tracker cooling - status report
What has to be done… • Pneumatic pipe installation (CMS) – Jan 07 • C6F14 cooling system connections – Dec 06 • Chiller tests – Jan 07 • C6F14 cooling plant tests – Feb/Mar 07 • Piping btw cooling and Tracker (Tender)– Apr 07 • Commissioning with Tk on – Jun 07 • C6F14 recuperation system – Apr 07 CMS Tracker cooling - status report