160 likes | 347 Views
Rosetta Lander System and Programmatics Berndt Feuerbacher, DLR Cologne. Payload Review 8-June-2000. Overview. Project team reorganized in January 2000 Joint Task Force established between Lander Team and ESA Schedule reworked for EQM and FM Team strength increased
E N D
Rosetta LanderSystem and ProgrammaticsBerndt Feuerbacher, DLR Cologne Payload Review 8-June-2000
Overview • Project team reorganized in January 2000 • Joint Task Force established between Lander Team and ESA • Schedule reworked for EQM and FM • Team strength increased • Project resources increased • Close contact established within Lander team • FDIR analysis in progress
Key System Contributions Rosetta Lander Team Instrument PIs • MPAe Lindau • MPE Garching • MPC Mainz • IAS Orsay • DLR Cologne • DLR Berlin • Open University Milton Keynes • KFKI Budapest • University Münster • LPG Grenoble • DLR Cologne • DLR Braunschweig • MPAe Lindau • MPE Garching • CNES Paris, Toulouse • ASI Roma • KFKI Budapest • STIL Dublin • FMI Helsinki • RAL Chilton • IWF Graz
Joint Task Force • Established Jan 2000 on behalf of Executive Managenment Committee • Mandate: • consolidate mission, system and operations issues • consolidate schedule • assessment 3 months, implementation 3 months • Members from Lander Team and ESA • Results • mission assessment completed, implementation in progress • schedule delay reduced • many technical, financial and schedule issues resolved • close cooperation Lander Team - ESA established
Project Resources • New management structure established Jan 2000 • Staffing increased, all vacancies filled • Resources increased through efforts of • DLR • CNES • ESA • Flywheel and ESS Software contracted to industry • Two integration teams formed (DLR, MPAe) for parallel work on EQM, FM
Subsystem Status • Structure & Thermal • STM qualified, EQM delivered, FM on track • Power • PCU: EQM integrated and tested, FM integration starts with EQM-2, exchange for FM Dec 2000, schedule critical, progress is shadowed • Solar generator: FM cells delivered, integration in progress • battery capacity upgrade agreed • CDMS • EQM integrated and tested, FM on track • Software: progress satisfactory, staff reinforcement established • Descent system • ADS: EQM on track, FM delayed due to components delivery, no impact on overall FM schedule • Flywheel:contract signed, FM in production
Subsystem Status II • Anchor - on track • Landing Gear • FM and DM schedule agreed • detailed design in certain areas incomplete • qualification parallel to FM integration • Orbiter-Lander interface • TxRx: EQM integrated and tested, FM on track • ESS: FM software contracted to industry, hardware progress slow , development shadowed • MSS: on track • STM separation tests successfully completed • Sample retrieval and distribution • Drill EQM integrated, FM on track
Operations • Lander delivery at 3 AU • Science operations consists of • initial science sequence • long term operations • timeline for initial science (65h) supported by battery • energy margin critical • increase of battery enhances robustness • extended operations timeline supported by solar generator + secondary battery
AIV Status • EQM delivery and integration complete except for • CIVA-CE, CIVA/M, CASSE, DIM, PP (LG-Foot) • Outstanding activities: • CDMS S/W update • Integration and Integrated Unit Tests of above mentioned units • Integrated Unit Tests for SD2, ADS • Final MLI and harness work • Tests to be performed prior to EQM delivery to ESA: • Integrated System Tests, partially with EMC testing on integrated unit level (June / July 00) • End-to-end Test with ESS + MSS (June / July 00) • Lander Level EMC Qualification Tests (August 00)
Conclusions • Project consolidation process proceeds satisfactory • Lander status as Orbiter subsystem implemented • Joint Task Force works efficient and successful • Coordination within Lander team improved • Shadow engineering implemented for critical subsystems / payloads • Schedule incompatibility minimized, based on testing opportunities after delivery • Project remains fragile, but all partners combine efforts to ensure success