Instrument Performance Verification and Optimisation. David L. Smith Space Science and Technology Department, CCLRC, Rutherford Appleton Laboratory, Chilton, Didcot OXON, United Kingdom, OX11 OQX. Instrument Performance Verification and Optimisation.
E N D
Instrument Performance Verification and Optimisation David L. Smith Space Science and Technology Department, CCLRC, Rutherford Appleton Laboratory, Chilton, Didcot OXON, United Kingdom, OX11 OQX
Instrument Performance Verification and Optimisation • Overview of instrument and commissioning phase • Functional performance • Thermal, Cooler, Scan Mechanism • Calibration Subsystems • Blackbodies, VISCAL unit, Gain-Offset Loop • Signal Channel Performance • Dynamic Range, Radiometric Noise, Pixel Map Alignment, Low Gain Mode, EMC • Conclusions on instrument performance
AATSR - OVERVIEW • Key Aims • Measurement of global sea-surface temperatures to <0.3K • Global vegetation monitoring • Cloud Properties • Continuation of SST datasets provided by ATSR-1 and ATSR-2 • Thermal IR channels at 12µm, 11µm and 3.7µm • Visible/Near Infrared Channels at 1.6µm, 0.87µm, 0.66µm and 0.56µm
Cold Blackbody VISCAL Hot Blackbody AATSR
AATSR Cooler Subsystem • IR detectors are maintained at 80±1K • Cooler subsystem can lift 600mW with a mounting interface temperature of 25°C • Maximum power demand is 53W during cool-down • 4 years design life
Infra-Red Calibration System Blackbodies viewed every scan.
AATSR Commissioning • Initial Switch-On • Activate instrument systems in a controlled sequence • Checkout • Verify function of subsystems • Characterise performance • Optimise subsystems • Mechanisms (Cooler, blackbody heaters, scan mechanism) • Pixel Map • Control Loops • Configure for nominal operations
Constraints • ICU switch-on not before L+7 to allow for LEOP and PEB switch-on • Initial cooldown not before L+14 to allow FPA outgassing • First outgassing must start 14 days after start of first cooldown • Visible channel optimisation to be completed before start of cool-down. • Condensation on IR-FPA expected to affect calibration (based on ATSR-2 experience) • Allow 5 days turn-around time for analysis of science data.
Key Dates • 1st March - Launch • 9th March – AATSR ICU ON • 12th March – AATSR to HEATER mode • 15th March - First AATSR science data (Visible Only) • 26th March - 1st Cooldown of IR-FPA and acquisition of first IR science data • 3rd-9th April – Outgassing • 19th May - End of main commissioning phase tests • 24th May – First Validation cruise started • 15-22nd July – Repeat of Cooler Checkout Tests • 16th Sept – End of AATSR commissioning phase