Greenlee County

Greenlee County. June 2008 County Engineers – Mormon Lake Philip Ronnerud, Engineer. Greenlee County. Created 3/10/1909 2000 Population 8,547 2006 Estimate 8,394 1,838 sq mi 6% private land. Greenlee County free flowing streams. Roads. 1 st Chip seal FY 08 June 2008

dolf
Download Presentation

Greenlee County

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Greenlee County June 2008 County Engineers – Mormon Lake Philip Ronnerud, Engineer

  2. Greenlee County • Created 3/10/1909 • 2000 Population 8,547 • 2006 Estimate 8,394 • 1,838 sq mi • 6% private land

  3. Greenlee County free flowing streams

  4. Roads • 1st Chip seal FY 08 June 2008 • 350 miles of roads • 35 miles paved • 315 miles unpaved • Need easement inventory • 26 Bridges

  5. Major Projects New Maintenance Facility • Centrally located at airport (Three Way) • Developing facility program • 15 acre site with outside storage • Offices and Shops

  6. ADOTGila River Bridge US 191 – Guthrie - $28 million AMEC – Designer / FNF Contractor

  7. Rehabilitation of 4 wood bridges 2 concrete arch bridges Local Bridges

  8. Airport • Extend West Taxiway bid at $1 million • Apron rehabilitation – 100% • Signage – 100% • Airport Master Plan Update • Drainage Master Plan • Drainage improvements • DBE/GPS • Security Fence • EA Runway/Taxiway • Obstruction removal

  9. Planning • 550 homes - Freeport-McMoRan • 125 homes planned in Clifton • 140 homes planned in unincorporated area of County • Tripled permitting in 2007 and DES says population is decreasing • Small Area Transportation Plan Amendment 1

  10. Landfills • MSWLF and C&D • Enlarge MSWLF permitted cell, and • Design 25 acre MSWLF expansion • 2 transfer stations • Relocated waste tire site • Enlarge C&D Landfill cell

  11. Floodplains • Stateline Road Bank stabilization • Revised Ordinance • DFIRM’s effective September 28, 2007 • Levy like structures • Provisionally Accredited Levee (Clifton 1st PAL in nation) • Clifton flood warning system • Enacted Flood District Tax – FY 2007 • AWPF Grant to restore 1 mile of the Gila River

  12. Questions? Thanks for your attention. Philip Ronnerud (928) 865 4762 pronnerud@co.greenlee.co.az