CAMINO CRÍTICO

CAMINO CRÍTICO. CAMINO CRÍTICO. ES LA CADENA DE TAREAS SUCESIVAS QUE UNE LOS NODOS INICIALY FINAL DEL PROYECTO, CUYA SUMA DE TIEMPOS DE DURACIÓN ES MÁXIMA CUALQUIER ATRASO EN ALGUNA DE LAS TAREAS DEL CAMINO CRÍTICO PRODUCIRÁ UN ATRASO EQUIVALENTE EN LA DURACIÓN TOTAL DEL PROYECTO.

dolph
Download Presentation

CAMINO CRÍTICO

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CAMINO CRÍTICO

  2. CAMINO CRÍTICO • ES LA CADENA DE TAREAS SUCESIVAS QUE UNE LOS NODOS INICIALY FINAL DEL PROYECTO, CUYA SUMA DE TIEMPOS DE DURACIÓN ES MÁXIMA • CUALQUIER ATRASO EN ALGUNA DE LAS TAREAS DEL CAMINO CRÍTICO PRODUCIRÁ UN ATRASO EQUIVALENTE EN LA DURACIÓN TOTAL DEL PROYECTO

  3. SUCESOS CRÍTICOS: SECUENCIA ININTERRUMPIDA • ACTIVIDADES CRÍTICAS: SECUENCIA ININTERRUMPIDA • CAMINO CRÍTICO PUEDE NO SER ÚNICO • DISTINTOS CAMINOS CRÍTICOS PUEDEN TENER TRAMOS EN COMÚN O SER TOTALMENTE DISTINTOS

  4. MARGEN DE UN SUCESO MSi = FTi - Fti 15 MSi = 21 – 15 = 6 i 21

  5. SUCESOS CRÍTICOS SON LOS QUE TIENEN MENOR MARGEN 21 MSi = 0 i 21

  6. ACTIVIDAD CRÍTICA • FORMA PARTE DEL CAMINO CRÍTICO • SI SE DEMORA, SE ATRASA EL PROYECTO • SE ENCUENTRA SIEMPRE ENTRE DOS SUCESOS CRÍTICOS • UNA ACTIVIDAD ENTRE 2 SUCESOS CRÍTICOS PUEDE NO SER CRÍTICA

  7. 24 14 24 3 4 5 27 20 12 20 20 27

  8. MARGEN TOTAL DE UNA ACTIVIDAD i-j MTij = FTj – (Fti + dij) 8 20 5 i j 23 12 MTij = 23 - 8 - 5 = 10

  9. MARGEN TOTAL DE UNA ACTIVIDAD i-j • ES EL MARGEN QUE SE DISPONE PARA PROGRAMAR LA TAREA SIN COMPROMETER LA DURACIÓN DEL PROYECTO 23 15 8 20 5 i j 23 12 8 MTij = 23 - 8 - 5 = 10

  10. MARGEN LIBRE DE UNA ACTIVIDAD i-j MLij = Ftj – (Fti + dij) 8 20 5 i j 23 12 MLij = 23 - 8 - 5 = 7

  11. MARGEN LIBRE DE UNA ACTIVIDAD i-j • ES EL MARGEN QUE SE DISPONE PARA PROGRAMAR LA TAREA SIN COMPROMETER AL PROYECTO HACIA ADELANTE 12 8 20 5 i j 23 12 8 MLij = 20 - 8 - 5 = 7

  12. MARGEN INDEPENDIENTE DE UNA ACTIVIDAD i-j MIij = Ftj – (FTi + dij) 8 20 5 i j 23 12 MIij = 20 - 12 - 5 = 3

  13. MARGEN INDEPENDIENTE DE UNA ACTIVIDAD i-j • ES EL MARGEN QUE SE DISPONE PARA PROGRAMAR LA TAREA SIN COMPROMETER AL PROYECTO HACIA DELANTE NI HACIA ATRÁS 8 8 20 5 i j 23 12 MIij = 20 - 12 - 5 = 3

  14. Fti FTi Ftj FTj PFC UFF

  15. Fti FTi Ftj FTj MT PFC UFF

  16. Fti FTi Ftj FTj ML PFC UFF

  17. Fti FTi Ftj FTj MI PFC UFF

  18. ACTIVIDAD CRÍTICA Ftj  FTj Fti  FTi PFC UFF

  19. MÉTODO NODO-ACTIVIDAD • LAS ACTIVIDADES SE REPRESENTAN POR BLOQUES (NODOS) • LAS FLECHAS INDICAN SOLAMENTE RELACIÓN DE DEPENDENCIA ENTRE TAREAS • NO REQUIERE ACTIVIDADES FICTICIAS (SALVO INICIAL Y FINAL) • ES MÁS FACIL DE ENTENDER POR QUIENES NO CONOCEN CC

  20. Q M R N P Q M R N P

  21. PROYECTO: CONSTRUCCIÓN DE UNA CASA