1 / 17

LINAC4 – LBS & LBE Lines dump design

LINAC4 – LBS & LBE Lines dump design. F. Regis, 07-04-2011. Outline. LBS and LBE lines Design specifications Dump features LBS dump: RP preliminary analysis General design features Energy deposition Thermal analysis Structural analysis Conclusions and next steps

drake
Download Presentation

LINAC4 – LBS & LBE Lines dump design

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LINAC4 – LBS & LBE Lines dump design F. Regis, 07-04-2011

  2. Outline • LBS and LBE lines • Design specifications • Dump features • LBS dump: RP preliminary analysis • General design features • Energy deposition • Thermal analysis • Structural analysis • Conclusions and next steps • LBS dump: Scenario 1 vs. Scenario 2

  3. LBS & LBE lines LBS line: Present layout LBS line LBE line

  4. Design specifications LINAC4 Project Document No. L4-B-ES-0001 rev.1.0 LINAC4 standard pulses Most severe thermo-structural scenario for LBS dump: Accident Most severe thermo-structural scenario for LBE dump: Commissioning For fatigue stress evaluation: most severe duty cycle. Absorbing core diameter: LBE beam size at vertical measurement, re-scaled at 5-σ LBS line operational scenario LBE line operational scenario LBS line 1-σ beam size LBE line 1-σ beam size

  5. Dumps features LBS Dump • Installation in the tunnel ceiling (≈4.5 m height) • dmin=200 mm from SEM grid (SEM grid vacuum tank, line installations, extra-shielding,...) • Reduced particle fluence beyond the dump (soil activation issues and possible effects on TP9 Gallery) • Reduced particle backscattering to the SEM grid • Feasibility study presented in March 2010 (R. Chamizo, V. Boccone): starting point LBE Dump LINAC4 full intensity beam (40 mA average current, 2834 W average power) Most stringent thermo-structural constraints w.r.t. LBS dump Reduced particle backscattering towards instrumentation Let’s try a common design

  6. LBS dump: RP preliminary analysis Irradiation profile Fluka model • 2 months – 12 h/day @142 W • 1 month off • 2 years – 8h x 2/week @14 W Induced activity in the water circuit • More calculations needed to evaluate concrete thickness necessary to reach 2.5 µSv/h • SEM grid position still to be defined • Estimated activity based on steady water volume: conservative approach • Refined analysis ongoing Courtesy of J. Vollaire

  7. General Design Features Cu10100 OFE Copper Jacket R4550 Graphite Absorbing Core Beam parameters • LBE: commissioning scenario • 400 µs • Rep. Rate = 1.11 Hz • Iavg = 40 mA • Pavg = 2834 W • Beam size: vertical measurement scenario

  8. Energy deposition Fluka • Peak energy deposition: 0.833e9 J/m3 • Nominal deposited power: 2834 W • Total deposited power ≈ 2419 W • Peak coordinates: zpeak = 265 mm ANSYS • Peak energy deposition: 0.804e9 J/m3 (-3.5% w.r.tFluka) • Total deposited power ≈ 2554 W (+5.6% w.r.t. Fluka)

  9. Thermal analysis Steady state – 4 c.p. Vs. 8 c.p. ncp= no. of cooling pipes • Maximum water speed to prevent from erosion/corrosion problem = 1.5 m/s • Nominal Heat convection coefficient in cooling pipes = 7157 W/m2/K • Perfect thermal contact Graphite/Copper • ΔTin&out = 0.44 K (1/4th model) • Δpss ≈ 0.012 bar (1/4th model – straight section only)

  10. Thermal analysis Transient analysis – Heat convection efficiency

  11. Thermal analysis Absorbing Core – Regime Tmax Jacket – Regime Tmax Tmax=450°C Tmax=29°C Nominal convection Cooling pipe – Regime Tmax,wall Tmax=27°C

  12. Structural analysis • Quasi-Static Structural analysis (worst cooling scenario): • First pulse: analysis of stress field in Graphite • ith pulse on regime: global analysis of stress field • Failure criteria: • Stassi Criterion for Graphite • VonMises Criterion for cooling jacket • Dynamic stress - Graphite • Heating process slower than stress relaxation due to elastic wave propagation

  13. Structural analysis 1st pulse – Stassi criterion Tension 1st pulse – Stassi criterion Compression σmax=3.30MPa σmax=-28.72MPa Beam 500st pulse – Stassi criterion Tension 500st pulse – Stassi criterion Compression σmax=3.88MPa σmax=-31.3MPa

  14. Structural analysis End 1st pulse – Von Mises σmax=0MPa • Stress levels within failure limits for both Graphite and Copper • No relevant mechanical properties degradation of Cu10100 (Tmax = 36°C) 500st pulse – Von Mises Next steps σmax=13.5MPa Thermal conductance model between graphite core and copper jacket Definition of the assembly interference (shrink fitting) Fatigue analysis for the dump – worst case scenario

  15. Conclusions and Next Steps A common solution for the LBS and LBE dump seems possible: further analysis needed Worst case for thermo-structural analysis have been selected for the LBE dump Dump configuration has been set according to LBS operation specification (back-scattering) Thermal analysis for cooling system design: steady-state and transient state Structural analysis performed on worst cooling conditions WHAT IS NEXT? Thermal conductance model for graphite to copper interface Refined thermo-structural analysis: assembly interference, ... Detailed analysis of cooling water activation (RP) Possible reduction in dump size: open discussion with RP team

  16. LBS Dump: Scenario 1 vs. Scenario 2 L s1 d l2 s2 d/2 lSEM l1 s3 H  zMagnet zWall h

  17. LBS Dump: Scenario 1 vs.Scenario 2 • Scenario 1: bending magnet (α=54°) and slit. The LBS dump placed in the tunnel ceiling. • Scenario 2: bending magnet (α=35°) and no slit. The LBS dump placed in the tunnel shielding. • First guess dimensions: 1.5 m max. length, 50 cm max diameter. • Preliminary discussion with Civil Engineering (N. Lopez-Hernandez): • Scenario 1: more complicated installation. Detailed analysis of dump infrastructure needed. • Scenario 2: slot for dump will be drilled. No need for wall partial dismantling. • Time of operation: ≈3-5 days. • Drilling machine encumbrance: ≈1 m machine width + 1 m on each side. • Preliminary discussion with RP (J. Vollaire): • Scenario 1: detailed evaluation of soil activation (fluence to TP9 gallery to be checked) • Scenario 2: issues about particle fluence to PSB tunnel

More Related