Tentative HIAPER Development Plan. Critical Infrastructure Dev. (10/1/04 – 4/30/05) Pilot Proficiency (5/1/05 – 5/15/05) Science Systems Flight Checks (5/15/05 – 6/15/05) Progressive Science upload (6/15/05 – 8/15/05) Progressive Science Research (8/15/05 – 12/15/05)
E N D
Tentative HIAPER Development Plan • Critical Infrastructure Dev. (10/1/04 – 4/30/05) • Pilot Proficiency (5/1/05 – 5/15/05) • Science Systems Flight Checks (5/15/05 – 6/15/05) • Progressive Science upload (6/15/05 – 8/15/05) • Progressive Science Research (8/15/05 – 12/15/05) • 1st Infrastructure Upgrade Package (1/1/06 – 3/1/06) • Available for Standard Research (3/1/06) • 2nd Infrastructure Upgrade Package (6/1/06 – 9/1/06) • 3rd Infrastructure Upgrade Package (6/1/07 – 7/10/07)
Projected HAIS Integration Schedule • Stratospheric Humidity - 9/1/2006 • Atmos. Radiation Pkg - 9/1/2006 • Small Ice Detector- 9/1/2006 • In-situ Ozone- 9/1/2006 • Whole Air Sampler- 9/1/2006 • Ozone Photometer- 9/1/2006 • Cascade Laser Spectrometer- 9/1/2006 • High Spectral Res. Lidar 1/1/2007 • GPS Profiler- 1/1/2007 • Cloud Radar- 9/1/2007 • Microwave Temperature Profiler- 9/1/2007 • Cloud Particle Imager- 9/1/2007 • Chemical Ion Mass Spec- 9/1/2007 • Aerosol Mass Spec- 9/1/2008 • Trace Organic Gas Analyzer- 9/1/2008
Tentative HIAPER Development PlanProjected Integration Schedule • Critical Infrastructure Period (10/1/04 – 6/15/05) • Basic science deliverables • Ground support equipment • Flight critical parts
Tentative HIAPER Development PlanProjected Integration Schedule • Progressive Science Period (6/15/05–12/15/05) • Community Exhaust • Dropsondes • Window blanks / remote sensing materials • Condensation Nuclei • Trailing Cone pressure calibration
Tentative HIAPER Development PlanProjected Integration Schedule • 1st Infrastructure Upgrade Package (1/1/06–3/1/06) • Optical View Ports / fused silica • Retractable View Port Covers • Radar Altimeter • Compressed gas cylinder mounts • Antennae
Tentative HIAPER Development PlanProjected Integration Schedule • 2nd Infrastructure Upgrade Package (6/1/06–9/1/06) • Radiometric Surface Temperatures • Digital Video • Wing Pylons / PMS Canister Mounts • Tail Deck Modifications & Wiring • Mission Scientist Station • Liquid Water & Icing Rate • Radiative Fluxes
Tentative HIAPER Development PlanProjected Integration Schedule • 3rd Infrastructure Upgrade Package (6/1/07 – 7/10/07) • All Weather Flux Pod* (11/15/06 – 12/15/06) • General Wing Pods / Large User Access