1 / 64

Facilitation of Transport Cooperation among CAREC Countries

Facilitation of Transport Cooperation among CAREC Countries. Final Report January 2007. Objective. Undertake/update pre-feasibility studies To determine whether there is a potential project Three corridors Bishkek –Tourgart Pass – Kashi linking Kyrgyzstan and China

dusan
Download Presentation

Facilitation of Transport Cooperation among CAREC Countries

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Facilitationof Transport Cooperation among CAREC Countries Final ReportJanuary 2007

  2. Objective • Undertake/update pre-feasibility studies • To determine whether there is a potential project • Three corridors • Bishkek –Tourgart Pass – Kashi • linking Kyrgyzstan and China • Angren–Gulistan in Uzbekistan, and • Dushanbe – Tursunzade road in Tajikistan • (Initially Oybek–Pungan road) • Identify rural roads for inclusion • Emphasis on economic growth from trade rather than direct impact on poverty

  3. Tasks • Review of previous studies • Survey of current road condition • Engineering cost estimates • Economic analysis • Traffic counts /demand forecasts • Benefit estimation • Social / poverty impact analysis • Environmental impact analysis

  4. Work program • Project commenced May 2006 • Based in Bishkek, Kyrgyzstan • Inception Report June • Field visits July – August • Surveys undertaken by local consultants in each country • Draft Final Report September • Uzbek component extended to include additional option on new alignment • Final Report January 2007

  5. Bishkek-Torugart-Kashi

  6. Option Considered • “Upgrading option” was based on previous studies • Basically upgrading of the existing route • Upgrading would involve: • Reconstruction over some sections • Improve geometry in some locations • Sealing of the section south of At Bashi • Sub-options in some areas • Deviation between km 103 and km 117 • Kuvaky Pass • Landslide areas • Other options not ruled out • Eg retention as a gravel road

  7. Unstable slopes and poor geometry Landslide Railway Existing main road Alternateroute

  8. Steep gradients and tight curves over the Kuvaky Pass

  9. Surface in poor condition South of Naryn

  10. Gravel road in very poor condition near Torugart

  11. Cost estimates • Based on figures supplied by MOTC and Kyrgyzdortransproject • Central estimate • Do not allow for full reconstruction • Geotechnical and topographical surveys will be needed for feasibility/detailed design

  12. Cost Estimate$ million

  13. Traffic Flows • The benefits are heavily dependent on traffic • Traffic counts and origin / destination surveys undertaken by Kyrgyzdortransproject

  14. Adjusted traffic countvehicles per day

  15. Origin Destination

  16. Economic rate of return

  17. Social impact • Existing right of way • Social impact likely to be small • Reaction to proposal almost entirely positive • Further work is needed on • Public consultation • Gender analysis • Assessment of poverty impact • HIV /Aids • Involvement of locals in construction work

  18. Environmental impact • Existing right of way • Impact will be small • The road passes close to Chatyr-Kul Lake, a Ramsar site • It is recommended that the project be classified “A” • There are also trans-boundary issues • The pre-feasibility study should be subjected to a State Environmental Review.

  19. Border issuesTrucks wait for the post to open

  20. Trucks queuing at the Chinese outpost

  21. Border Issues • Reputation for unpredictability • closed on weekends and holidays • only open limited hours • Number of vehicles controlled by permits • bilateral agreement on number of crossings • Not officially open to ‘third parties’ • Kyrgyz drivers complain they are prevented from accessing China • in theory access rights are reciprocal • Border fees could be used to maintain the road

  22. Conclusions Bishkek-Kashi • There appears to be a viable project • The project should proceed to the feasibility study stage • Other options should be investigated at that time • The Bishkek-Issyk Kul road has the highest return • this could be seen as a separate project • Naryn – Torugart is most important for regional trade. • Current procedures constrain cross border travel • Increasing opening hours would reduce delays • The permit system should be abolished • Transit fees could be used for road maintenance • There do not appear to be significant social issues • Because of the fragile environment around Chatyr-Kul Lake, it is recommended that the Project be category “A” • this would require an EIA.

  23. Uzbekistan Angren - Gulistan

  24. Angren – GulistanEastern section

  25. Angren GulistanCentral section

  26. Angren GulistanWestern section

  27. Options Considered • Two options considered • Upgrading existing route with minor re-alignment and bypasses • New alignment • Improvement of current road not considered practical • Upgrading would involve: • Bypasses of main towns and settlements • Duplication of current road • Could be constructed in phases • New alignment • New alignment south of current route • Avoids inhabited areas • Links to M39 further south • Other options not ruled out

  28. The route is unsigned and involves 90o turns

  29. Four lanes un-divided carriageway near Angren

  30. Junction of 4P-2 and M-373 near Ahangaren M373 To Angren

  31. Cost estimates • Based on figures supplied by I/K/S • Central estimate • More geotechnical and topographical surveys will be needed for feasibility/ detailed design

  32. Cost EstimateRe-align and improve current route $ million

  33. Cost EstimateNew Alignment $ million

  34. Traffic Flows • Benefits are heavily traffic- dependent • Traffic counts and origin / destination surveys were undertaken at: • Beskostina (between Angren and Almalyk) • Buka • Segizbaev (near Sirdarya bridge) • Easing of border restrictions could result in much greater regional traffic

  35. Adjusted traffic countvehicles per day Traffic via Buka is very small compared with that at Beskostina

  36. Origin Destination(2 way flows by route – vehicles /day) Half the traffic is going between Angren and Gulistan (blue shaded), But only a small proportion is on the direct route (lower quadrant)

  37. Comparisondaily traffic by route Only 15% of total traffic is using the direct route, but 73% of large vehicles use the direct route

  38. Potential traffic • Half the traffic between Angren and Almalyk is travelling to Gulistan or beyond • Most cars currently travel via Tashkent because it is faster (the roads are better) • Most heavy vehicles use the direct route because it is significantly shorter • It is likely that most potential traffic would switch to an improved direct route • International traffic would use the route if border restrictions were eased

  39. Economic rate of return There is clearly a project worth funding Alternative 2 may be viable with more international traffic

  40. Social impact • The social impacts is expected to be minimal • Reaction to the proposal was mostly positive • Some concern about extra traffic on the existing route • The new alignment would have less resettlement but greater land loss • Further work is needed on resettlement and other impacts at the feasibility stage

  41. Environmental impact • Both options will have land acquisition impacts • Both use land currently in agricultural uses • The project would be classified “A” • All impacts likely to be mitigatable • The pre-feasibility study should be subjected to a State Environmental Review.

  42. Border Issues • Currently regional and international traffic is minimal • Some Turkish and Iranian trucks were observed • The route has potential as an important international route • The recommendations are based on current traffic, but anticipate regional trade • A phased approach is possible with Alternative 1 • Border fees could be used to maintain the road

  43. Conclusions for Uzbekistan • There is a viable project that ADB or other agencies could support • Alternative 2 requires more research to justify the additional cost • Current border procedures constrain regional travel • Regional trade would boost traffic numbers • The design should anticipate future regional traffic • There do not appear to be significant social issues • Growth of traffic on the existing roads would be undesirable • Resettlement would be less with alternative 2, but there would be more land acquisition • The Project would be environmental category “A” under either option • this will require an EIA.

  44. TajikistanDushanbe Tursunzade

  45. Alternatives Considered • Two alternatives were considered • Upgrading the existing route • Upgrade plus new alignment to bypass main towns • The existing route • Improve geometry • Reconstruction over some sections (20 -40%) • Passing lanes within current right of way. • The new alignment • New road bypassing Gissar junction and Sachrinav • Elsewhere using existing route • Four lanes • Other options not ruled out

  46. Gissar turnoff

  47. Much of the right of way is wide and passing lanes could be provided

  48. Open farmland – probable route of Alternative -2

  49. Export grapes go by local roads to the railhead

More Related