1 / 6

Implementation of NPRR153 Carrie Bivens Supervisor, Day-Ahead Market WMS May 8, 2013

Implementation of NPRR153 Carrie Bivens Supervisor, Day-Ahead Market WMS May 8, 2013. Summary. NPRR153 was a nodal parking deck item The purpose is to allow Generation Resources to offer their offline Non-Spin in fixed quantity blocks

dustin-moon
Download Presentation

Implementation of NPRR153 Carrie Bivens Supervisor, Day-Ahead Market WMS May 8, 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Implementation of NPRR153 Carrie Bivens Supervisor, Day-Ahead Market WMS May 8, 2013

  2. Summary • NPRR153 was a nodal parking deck item • The purpose is to allow Generation Resources to offer their offline Non-Spin in fixed quantity blocks • Currently only Load Resources can submit block offers for Ancillary Services • It is a straightforward and minor system change to the MMS validation rules, with an impact analysis between $12 and $16k. • During project planning, ERCOT recognized and studied that this NPRR could cause some potentially undesirable pricing outcomes and now seeks stakeholder guidance WMS May 8, 2013

  3. Clearing Price Impact • Fixed quantity blocks present a challenge to a marginal pricing scheme. • This issue was discussed extensively as it relates to DAM energy bids/offers during the MMS requirements approval phase of nodal. • Fixed quantity block offers do not set the clearing price and are essentially price-takers once selected in the commitment phase of DAM • For DAM energy, it is a regular occurrence to be struck below offer price, but the price differences are usually minimal • Upon implementation of NPRR153, fixed quantity Non-Spin offers could also clear below the offer price (and alternatively, fail to clear even when MCPC > offer price). • A/S market is less liquid than energy market so the magnitude of the price drop is likely to be larger (next lower variable offer sets price) • A/S products are linked together, so pricing impacts carry to other services • As an offline non-spin award, it will not be eligible for DAM make-whole payment WMS May 8, 2013

  4. Clearing Price Impact • In an extreme case study performed by ERCOT, the MCPC could be $0 no matter the offer costs • This outcome was simulated using a recent production case by converting all variable non-spin offers to block non-spin offers • MCPCNon-Spin = Shadow Price of the Non-Spin requirement constraint • If there are no committed variable offers to adjust with a small change in the Non-Spin requirement, then an incremental increase to the Non-Spin requirement would result in no change to the objective function Offer Price ($/MW) Non-spin req’t Offer MW WMS May 8, 2013

  5. Clearing Price Impact • This is an existing potential issue for Load Resources but is not observed because: • Currently LRs do not regularly offer Non-Spin, they only participate in the RRS market which has a 50% procurement limit • Offers from Generation Resources routinely set the clearing price WMS May 8, 2013

  6. Discussion of Options • Options: • Continue work on NPRR153 with existing block offer implementation • Choose to not implement NPRR153 • An alternative implementation with a change in price-setting methodology (and revise Impact Analysis for NPRR153): • Add a pricing run where the block of the marginal offer is removed for clearing purposes and it is allowed to set the price (economic dispatch is re-solved with the commitment pattern frozen and the offer as variable MW) • Creates inconsistency between dispatch, price and offer/bid values • Could lead to increased requests for make-whole consideration from both supply and demand side, once we begin publishing inconsistent results • Co-optimization is impacted • Generators would no longer be guaranteed an optimal dispatch among energy and A/S, once committed • This pricing run would be necessary for all hours due to the situation of fixed quantity block offers that are also multi-hour blocked. • More discussion and analysis would be needed if this option is desired 4. Other concepts or ideas? WMS May 8, 2013

More Related