May 13 th , 2014 Portage County, Ohio

May 13 th , 2014 Portage County, Ohio Tallmadge Road Corridor and Interchange Improvement Project. Safety study presentation. Project Location & Description Tallmadge Road Corridor Parliament Drive to Sunnybrook Road Distance – 1.1 Miles Approximate ADT –

Download Presentation

May 13 th , 2014 Portage County, Ohio

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. May 13th, 2014 Portage County, Ohio Tallmadge Road Corridor and Interchange Improvement Project

  2. Safety study presentation • Project Location & Description • Tallmadge Road Corridor • Parliament Drive to Sunnybrook Road • Distance – 1.1 Miles • Approximate ADT – • Opening Year 2019 – 15,940 • Certified Traffic Obtained & Used for Analysis (Certified at 0% Per Year Growth)

  3. Safety study presentation POR – Tallmadge Road Corridor Study Area

  4. SAFETY STUDY PRESENTATION • Regional Priority • The Congestion Management Process Study published by AMATS in July 2012 lists Congestion Reduction Strategies for various intersections. Listed below is the strategy for the study corridor: • I-76 / Tallmadge Road / Mogadore Road Interchange – Reconfigure Interchange. • This is the highest crash corridor in Portage County (80 Crashes). Next Closest area is the State Route 59 corridor near the State Route 261 intersection (68 crashes).

  5. SAFETY STUDY PRESENTATION • Crash Analysis Summary • 80 Crashes Reported in Study Area from 2010 – 2012 • 43 Rear-end • 10 Angle • 8 Left Turn • 7 Sideswipe - Passing • 5 Fixed Object • 4 Other Non-Collision • 3 Sideswipe – Meeting *Note the High Number of Rear-End Crashes

  6. SAFETY STUDY PRESENTATION • Crash Analysis • Much Higher than Average Rear-End Crashes • Inefficient Cluster Signal Operation at I-76 WB Exit Ramp / Mogadore Road / Tallmadge Road Intersection • Non-Traditional Interchange Geometrics at I-76 / Tallmadge Road Interchange • Conclusion – Congestion Related Crashes Resulting from Inefficient Operations in Study Area

  7. SAFETY STUDY PRESENTATION • Crash Analysis I-76 WB Exit Ramp / Mogadore Road / Tallmadge Road Intersection

  8. SAFETY STUDY PRESENTATION • Looking east on Mogadore road (west)

  9. SAFETY STUDY PRESENTATION • Crash Analysis

  10. SAFETY STUDY PRESENTATION • Looking South on Mogadore Road (West) at the I-76 EB Exit Ramp

  11. SAFETY STUDY PRESENTATION • Crash Analysis

  12. SAFETY STUDY PRESENTATION • Looking west on Tallmadge road at i-76 eb ramps interchange

  13. SAFETY STUDY PRESENTATION • PROPOSED DEVELOPMENT

  14. SAFETY STUDY PRESENTATION • PROPOSED DEVELOPMENT Developable Land: 6 Acres Site Trips: 500 Daily Trips

  15. SAFETY STUDY PRESENTATION • PROPOSED DEVELOPMENT Developable Land: 127 Acres Site Trips: 15,810Daily Trips

  16. SAFETY STUDY PRESENTATION • PROPOSED DEVELOPMENT Developable Land: 48 Acres Site Trips: 2,820 Daily Trips

  17. SAFETY STUDY PRESENTATION • PROPOSED DEVELOPMENT Developable Land: 72 Acres Site Trips: 3,960 Daily Trips

  18. SAFETY STUDY PRESENTATION • PROPOSED DEVELOPMENT Total Developable Acres: 253 Acres Total Site Trips: 23,090 Trips

  19. SAFETY STUDY PRESENTATION Proposed Countermeasures • Eliminate both Mogadore Road junctions with the I-76 Exit Ramps to Remove the Mogadore Road / Ramp Overlap Sections • Relocate / Reconstruction Mogadore Road (West) to tie into Existing East End Welding • Cul-de-Sac Mogadore Road (East) and Reroute all Traffic to Sunnybrook Drive • Reconstruct the Traffic Signal at the Reconfiguration Intersection of Tallmadge Road / I-76 WB Ramps. • Construct a Traffic Signal at the Newly Created Intersection of Tallmadge Road / Mogadore Road • Convert the I-76 / Tallmadge Road Interchange from a Tradition Diamond Interchange Into a Diverging Diamond Interchange • Interconnect the Traffic Signals Along the Tallmadge Road Corridor to Form a Coordinated Signal System

  20. SAFETY STUDY PRESENTATION Proposed improvement

  21. SAFETY STUDY PRESENTATION • Vacant property on SE Corner of Tallmadge Road / I-76 EB intersection

  22. SAFETY STUDY PRESENTATION Synchro Models • Improved Interchange (Traditional) • DDI Interchange

  23. SAFETY STUDY PRESENTATION Other Diverging Diamond Interchanges • I-270 / Roberts Road Interchange in Columbus, Ohio • Opened in Fall of 2013 • Seven Total Crashes Between October 26th and December 31st, 2013 • S.R. 4 / U.S. 68 Interchange in Lexington, Kentucky • Opened in Fall of 2011 • Two Years Before Opening vs. Two Years After Comparison: • 47.8% Reduction in Total Crashes at Interchange • 60.9% Reduction in Injury Crashes at Interchange

  24. SAFETY STUDY PRESENTATION Lexington kentuckyddi

  25. SAFETY STUDY PRESENTATION Lexington kentuckyddi

  26. SAFETY STUDY PRESENTATION Letters of Support

  27. SAFETY STUDY PRESENTATION Project Cost Estimate and Rate of Return • Total Cost Estimate of All Improvements, Right-of-Way, Construction and Construction Inspection: $7,364,575 • Benefit to Cost Ratio on Project: 0.75 • Total Safety Funding Request: $4,350,000 • Benefit to Cost Ratio on HSP Funding Request: 1.01

  28. SAFETY STUDY PRESENTATION Funding Type Dollar Amount % of Total Safety Funding Request: $4,350,00059.1% Future AMATS / CEAO Request: $2,024,994 27.5% Local Funding: $989,581*13.4% Total Project Funding: $7,364,575 Current project funding plan * Local Funding will be Comprised of Funds from Portage County, the City of Tallmadge, Brimfield Township and OPWC Issue I Funds

  29. SAFETY STUDY PRESENTATION Proposed improvement countermeasures

  30. Safety study presentation Corridor safety study questions • Michael a. hobbs, p.e., ptoegpd director of traffic engineering • Mark R. Grossman, P.E.GPD Chief Highway Engineer • Ryan m. Gillespie, P.E., PTOEgpd Traffic ENGINEER • Curtis J. Deibel, E.I.gpd traffic ANALYST • Anthony Zumbo, P.E., P.S. PORTAGE COUNTY project manager