1 / 24

Responsibility Assignment Matrix (RAM) — Purpose

Responsibility Assignment Matrix (RAM) — Purpose. Ensure that all tasks are assigned to people Show levels of involvement of people to work. Linkage Between WBS and OBS. OBS. X. X. WBS. X. X. Responsibility Assignment Matrix. RASIC Method. SENIOR MANAGEMENT. TEAM MEMBER.

eelliott
Download Presentation

Responsibility Assignment Matrix (RAM) — Purpose

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Responsibility Assignment Matrix (RAM) — Purpose • Ensure that all tasks are assigned to people • Show levels of involvement of people to work

  2. Linkage Between WBS and OBS OBS X X WBS X X

  3. Responsibility Assignment Matrix RASIC Method SENIORMANAGEMENT TEAMMEMBER SUPPORTSTAFF PROJECTMANAGER CUSTOMER MARKETING STUDY R I I A I I A S S S S S S S R/S S R I I I I A S S S I S IDENTIFY POTENTIAL MARKET IDENTIFY SURVEY POPULATION DEVELOP SURVEY TEST SURVEY ON SAMPLE FINALIZE SURVEY CONDUCT SURVEY COLLECT SURVEY ANALYZE DATA REPORT RESULTS AND SUGGESTION C C R R R R R R LEGEND R - RESPONSIBLEA - APPROVES - SUPPORT (DOES THE WORK)I - INFORMC - CONSULT

  4. Guidelines • Team member names should be shown across the horizontal axis in the final matrix. • There should be only one R and one S for each activity if possible. • Every activity should have an R and an S. R/S for an activity is acceptable. • The project manager will have the majority of Rs. • The customer and senior management have the majority of As and Is.

  5. Project Schedule — Purpose • Determine if requested completion date is possible. • Identify start and completion dates of all work. • Determine the controlling sequence of activities. • Provide data for resource allocation. • Track progress by providing a baseline.

  6. Scheduling Step 1: Estimate Activity Durations

  7. Estimating Techniques • Deterministic • Best Guess • Delphi (Consensus) • Probabilistic • Program Evaluation Review Techniques (PERT)

  8. Scheduling Step 2: Determine Activity Sequence By Creating a Network Diagram

  9. g a b c d e f h i j i b d e h a c j f g WBS/Network Diagram Linkage

  10. Network Diagram Methods C A B J D F E G Arrow Diagram Method H I J C A B D E F G Precedence Diagram Method H I

  11. Create a Network Diagram • A is the first activity • B, C and D are dependent on A • E and F are dependent on B • G is dependent on C • H is dependent on C and D • I is dependent on F and G • J is dependent on E, I, and H • J is the last activity

  12. Precedence Diagram Method E B F I A C J G D H Logic Connection Activity

  13. Scheduling Step 3: Calculate the Schedule Using Critical Path Method (CPM) Procedures

  14. What’s is the Critical Path? • Riskiest path in a project • Path with the most important activities • Path with least slack • Path with least resistance • Path with longest duration • Path to Emerald City

  15. What’s is the Critical Path? • Path with least slack • Path with longest duration

  16. Determine the Critical Path • A = 2 weeks • B = 1 week • C = 3 weeks • D = 1 week • E = 4 weeks • F = 3 Weeks • G = 2 weeks • H = 1 week • I = 2 weeks • J = 1 week

  17. Project X — Critical PathSolution E Activity Name Float Duration 2 4 3 7 5 9 ES EF LS LF B F 1 1 1 3 2 3 3 4 3 6 4 7 I G J A C 0 0 0 0 0 2 2 3 2 1 5 7 5 7 7 9 7 9 9 10 9 10 0 2 0 2 2 5 2 5 H D 3 5 1 1 2 3 7 8 5 6 8 9

  18. Scheduling Step 4: Show the Schedule by Drawing Gantt and/or Milestone Charts

  19. Enhanced Gantt Chart Jan Feb Mar April May June Task A Task B Task C Task D Task E Task F - Non-Critical - Slack/Float - Critical

  20. Gantt Charts • Simple to construct • Easy to interpret • Good for management reporting

  21. Project X — Gantt Chart Solution Time 1 2 3 4 5 6 7 8 9 10 Activity Duration 2 A B C D E F G H I J 1 3 1 4 3 2 1 2 1 - Non-Critical - Slack/Float - Critical

  22. Develop a Project Schedule • Prepare a project schedule for the room you are going to paint.

More Related