This report provides information on the organization issues, tasks and aims, milestones, re-organization of personnel, and interfaces to other project divisions within the LINAC & Operations division at FAIR@GSI. It includes details on the staff members, project groups, and departments within the division.
E N D
REPORTS BY NEW PROJECT DIVISION HEADS: “LINAC& Operations” • organisation issues • tasks and aims • milestones • re-orgnisation of personell • interfaces to other project divisions
Organigramm /L&O (recently) 113 FTE 10/2012
Established: 8/2012 For 120 – 140 staff members: head of division, 1 secretary, 2 assistants (financial issues, personell management, time schedule, reporting, general administration, project control issues) tot. need: 4 FTE (since 10/2012: 2.75 FTE) and 1 deputy tasks and aims I Projektbereich L&O (LO) Project Group FAIR-p-linac (LOPL) • Established: 10/2012 • need: 5.5 FTE, Status: 1 scientist, 3 engineers, • Groupleader resonsible for FAIR p-linac@gsi as well as for group staff • general project management, system design, Building follow up (GAP), supervision of inkind contributions: rf cavities (RFQ, CH, rebuncher), 325 MHz klystrons
The FAIR Proton Injector CH-DTL RFQ Klystron
Established: 10/2012, former part of the department „LINAC&Ion Sources“ New head of division, + 7 FTE, leaving of 4 FTE (LO, LOPL and FAIR@gsi) tot. need: 7 FTE FAIR UNILAC-upgrade, UNILAC: operation, upgrade „Fit for FAIR“ commissioning, shutdown, HITRAP, CRYRING-injector operation, r&d-, prototyping for the HE-LINAC (replacement of Alvarez DTL), rf-cavity development tasks and aims II LINAC department (LOLI) 2010 beam direction 2011
Further preparation activities for the injector linacs FAIR-p-linac rf-teststand (325 MHz-CH-prototype, commissioning 2012) HGF-AcceleratorResearch&Development (prototyping HE&cw-LINAC key components) Prototyping of a sc 325 MHZ-CH@GUF (HE-LINAC-Booster) Room Temp. IH-DTL Supercond. CH-DTL Room Temp. CH-DTL sc-prototype Cold model
tasks and aims III Accelerator Operation (LOAO) • Established since many years • need: 0 FTE, Status: 18 FTE, leaving of 2 FTE (1 senior scientist LO, 1 operator SB) • to be done: dedicated staff planing for the long shutdown periods (2013-2016) • Requirement by project division „Primary Beams“: 10 FTE (operators) for magnet testing (2015/2016) • machine beam time operation 2013, 2014 • organization and managment of shutdown-measures • preparation for FAIR-commissioning: operators training • recruitment of operation staff (fit for injector- and FAIR-commissioning: >2016
tasks and aims III Ion Sources (LOIS) • Established: 10/2012, former part of the department „LINAC&Ion Sources“ • New head of division, + 18 FTE, leaving of 1 FTE (rf-engineerLOPL) • work package: proton source for the FAIR p-LINAC • FAIR UNILAC-upgrade: new uranium high current ion source terminal compact LEBT, • ion source operation (Penning, MeVVa, MUCIS, ECR) • R&D or FAIR: High Current operation for FAIR (2.5 Hz operation) • 28 GHz-ECR project • infrastructure group: mech. workshop, ... (temporarily available)
tasks and aims IV LINAC RF (LORF) • Established: 10/2012, former part of the department „Radio Frequency“ • New head of division, + 12 FTE, leaving of 1 FTE (experienced rf- engineerLOPL) • no rf-engineers available • work package: rf system for the FAIR p-LINAC • 2 MW rf-amplifier prototype for the HE-LINAC-project, preparation of series production • „Reconstruction“ of the complete UNILAC-rf-gallery) • rf-system/IH-prototyping for the HE-LINAC project • operation and support of the running rf-systems • maintenance shutdown, ... • R&D of UNILAC rf-system • Digital low level rf system for the HE-LINAC-2 MW amplifiers • Support of HITRAP, CRYRING rf-cavities
tasks and aims V Electric Power Systems (LOEP) • Established since many years • max. need: 8 FTE (2016), Status: 17 FTE • retirement of key personell
tasks and aims VI Beam Instrumentation (LOBI) • Established since many years • max. need: 4 FTE (2016), Status: 30 FTE • requirements adressed to other divisions to be considered
personell/beam instrumentation priorisation for basic beam instrumentation for SIS100&CR 2 FTEs from Egineering&LO original recruitment of project associates 8 FTE from Common System
L&O established since 10/2012 worpackage leader (LOBI, LOEP) for Primary Beams, Stored Beams and Rare Isotope Beams personell support from Project Coordination, Common Sytems, Engineering defined Transformation process of the former accelerator division not completed until now Careful and early stage planing of beam operation, commisioning phases is strongly recommended (LOAO, LOLI, LOIS, LORF) Summary