150 likes | 268 Views
KANE COUNTY DIVISION OF TRANSPORTATION STEARNS ROAD WETLAND MITIGATION SITE. SECTION NO. 06-00214-03-BR. PRE-BID MEETING. PROJECT LOCATION. NEW ALIGNMENT WEST OF IL ROUTE 25 AND EAST OF THE FOX RIVER SOUTH OF CNIC TRACKS AND NORTH OF MIDWEST GROUNDCOVERS ST. CHARLES TOWNSHIP, KANE COUNTY
E N D
KANE COUNTY DIVISION OF TRANSPORTATION STEARNS ROAD WETLAND MITIGATION SITE SECTION NO. 06-00214-03-BR PRE-BID MEETING
PROJECT LOCATION • NEW ALIGNMENT WEST OF IL ROUTE 25 AND EAST OF THE FOX RIVER • SOUTH OF CNIC TRACKS AND NORTH OF MIDWEST GROUNDCOVERS • ST. CHARLES TOWNSHIP, KANE COUNTY • THIS PROJECT IS LOCATED IN A SENSITIVE ENVIRONMENTAL AREA
PROJECT LOCATION PROJECT LOCATION
PROJECT DESCRIPTION • 11.7 ACRES OF WETLAND MITIGATION • 12.8 ACRES OF COMPENSATORY FLOODPLAIN STORAGE • 1,500 FT OF STREAMBANK RESTORATION • 3,417 FT (0.65 MI) OF NEW ALIGNMENT • ROADWAY EMBANKMENT • THE PROJECT INCLUDES SPECIAL WASTE REMOVAL
PROJECT DESCRIPTION • THIS IS A WETLAND MITIGATION PROJECT FIRST AND FOREMOST. • THIS PROJECT ALSO INCLUDES: • ROADWAY EMBANKMENT • COMPENSATORY FLOODPLAIN STORAGE • TEMPORARY AND PERMANENT STABILIZATION • SPECIFC TREE PROTECTION AREAS
CONSTRUCTION ENGINEERING KANE COUNTY DIVISION OF TRANSPORTATION • COUNTY ENGINEER CARL SCHOEDEL • PROJECT MANAGER MARK BAGHERPOUR • CONSTRUCTION MGR DAVE BOESCH CONSULTANT - CHRISTOPHER BURKE ENGINEERING • ENGINEER OF RECORD MIKE KERR, CBBEL • CONSTRUCTION DAN CROSSON, CBBEL • ENVIRONMENTAL PAT KELSEY, CBBEWL
PHASING • PHASE 1 – ALL WORK, EXCEPT FOR LANDSCAPING AND TEMPORARY SESC SHALL BE COMPLETED BY OCT 15, 2007 • PHASE 2 – ALL SEEDING SHALL BE COMPLETED BY DECEMBER 1, 2007 • PHASE 3 – ALL PLANTINGS SHALL BE COMPLETED BY JUNE 1, 2008 • PHASE 4 --ALL CONTRACT WORK INCLUDING PUNCH LIST, SHALL BE COMPLETED BY OCTOBER 15, 2008
FAILURE TO COMPLETELIQUIDATED DAMAGES • PHASE 1 -- $1,100.00/DAY • PHASE 2 -- $ 550.00/DAY • PHASE 3 -- $ 725.00/DAY • PHASE 4 -- $1,300.00/DAY
404 PERMIT COMPLIANCE • USACE SECTION 404 INCLUDING SECTION 401 WATER QUALITY CERTIFICATION • KANE-DUPAGE SOIL & WATER CONSERVATION DISTRICT OVERSIGHT • KANE COUNTY STORMWATER ORDINANCE SESC -- NPDES PHASE II
404 PERMIT COMPLIANCE • CONTRACTOR SHALL MEET ALL REQUIREMENTS OF 404 PERMIT INCLUDING SOIL EROSION AND SEDIMENT CONTROL AND PROTECTION OF HIGH QUALITY AQAUTIC RESOURCES • NO DIRECT DISCHARGES TO THE EAST BRANCH OR NORTH ARM OF BREWSTER CREEK • NO DIRECT DISCHARGES TO THE FOX RIVER
KEY SPECIAL PROVISIONS • DEBRIS REMOVAL • BREWSTER CREEK CONCRETE REMOVAL • SELECTIVE CLEARING • LIMITED ACCESS TO SOME AREAS • SEEDING, CLASS 4 AND 5 MODIFIED • 8 SEED TYPES FOR CLASS 4 • 8 SEED TYPES FOR CLASS 5 • 4 INTERSEEDING SEED TYPES • LOCAL GENOTYPE – 150 MI RADIUS
KEY SPECIAL PROVISIONS • PERENNIAL PLANTS • WETLAND EMERGENT TYPE • WETLAND TYPE • PERENNIAL PLANTS • IDOT WILL TAG TREES & SHRUBS • IDOT & RE WILL INSPECT ALL PLANTS ON ARRIVAL TO THE JOBSITE.
KEY SPECIAL PROVISIONS • COORDINATION BETWEEN CONTRACTORS • MANAGEMENT OF SOIL EROSION AND SEDIMENT CONTROL
OTHER CONSIDERATIONS • ELECTRIC SERVICE TO MIDWEST GROUNCOVERS SHALL BE UNINTERUPPTED • CONTRACTOR AND RESIDENT ENGINEER TO WORK WITH MIDWEST GROUNDCOVERS ON TREE REMOVAL NEAR PROPERTY LINE • USACE TO MAKE REGULAR SITE VISITS ALONG WITH KDSWCD