Welcome IMAC Members !. Report to IMAC Hesheng Chen. Progress of BEPCII Accelerator Status of BESIII Summary. BEPC running ended July 4 2005. SR running finished at 20 June 20, 2005 SR running: 3009 hour. 362 experiments, 1087 users 1751 hours for test beam & slow e+ source
E N D
Report to IMACHesheng Chen • Progress of BEPCII Accelerator • Status of BESIII • Summary
BEPC running ended July 4 2005 • SR running finished at 20 June 20, 2005 • SR running: 3009 hour. • 362 experiments, 1087 users • 1751 hours for test beam & slow e+ source • Machine studies: • high beam current, • e+ injection, • transverse feedback, • BPM, • response matrix, • …
Milestones in the shutdown • Pre-alignment of half units started 17 May 2005 • Remove old ring : July 4 – Aug. 5, 2005√ • Survey network in tunnel for magnet alignment Aug. 6 – Sept. 5, 2005 √ • Decoration tunnel: Aug. 25 – Sept. 22, 2005√ • Transformer &Electricity upgrade, new water pipes, cabling: Sept. 23, 2005 – Mar. 2, 2006 √. • Installation of two rings: started 2 March, 30 units installed until today.
Delays in delivery and installation of some key devices • SCQ: • delivery delayed about 6 month • Installation: more delay • SCQ Valve boxes : • delivery delayed about 4 month • more delay installation • Power Leads & valve boxes of BESIII SC magnet. • Antechamber depressed:
Progress of Linac • Tuning Phase I: • e+ available at the end of Linac March 19, 2005 • e+ reached 63mA @ 1.3GeV June 1, 2005 • e- reaches 1.89 Gev & e+ 1.55 GeV June 17,2005 • Repetition rate 12.5Hz →25Hz → 50Hz • Shutdown July 4, 2005 – Feb. 28, 2006 • Phase control system installed • Microwave system improved • Vacuum system improved • Stability of Linac and beam • Tuning Phase II: March 1 – July 30, 2006
Progress of Storage Ring • Mass production of most components finished • 2 superconducting RF cavities, • 2 RF power sources (250kW), • 2 superconducting quards, • 49 dipoles, 89 quadrupoles, • special magnets in IR, • 300 power suppliers of magnets, • 4 sets of injection magnet system, • 80 antechambers. • Instrumentations of beam diagnostics and control in good progress. • In progress: • the vacuum chambers of straight sections, • photon absorber • movable mask …
Progress of Storage Ring • Critical path: • superconducting IR magnet, • pre-alignment • cryogenic system/SC devices integrating. • Most of the hardware are in the stage of installation, testing and commissioning. • Installation of pre-aligned magnet unit (B,Q,S with one girder) into the tunnel started March 2. 30 units installed
Installation of half unit (15-17.5 tone) by air beds
IMAC May 2005 Challenges • Cryogenics system: critical path • Linde compressors and cryogenics arrived • Gas tanks, He gas pipes, N pipes: done • critical path : valve box, system tuning • SC devices: critical path • SC Magnets production @BNL: small delay • SC cavities: arrived IHEP last week. • BESIII SC magnet: winding to be finished in 10 days. Assembling / testing? reach the specifications ? • Uncertainty in system tuning • Field mapping
IMAC report (May, 205) • There are apparent discrepancies between the schedule used by the project office and the one used by the group leaders. • The completion of the cryogenic system can not be accurately predicted due to the delivery of connection box from HIST and completion of transfer lines. So far, there is about 3 months delay. • The delivery of vacuum chamber and the Ti-N coating also encountered possible delay of about 3 months and with no effective plan of recovery. • Commissioning of all three SC components, SCQ, SRF, SSM also will be delayed by more than 3 months caused by the delay of completion of the cryogenic system. More `experienced` manpower is needed to complete the design and installation of the cryogenic transfer lines and smooth start up of the cryogenic system. • The time allowed for combined field measurement with SCQ and SSM in place appears too tight.
Difficulties • The teams of cryogenics system and SC devices are limited andshortage of experiences. However, Many helps from experts of DESY and KEK, the teams are shaping. • Poor performance of HIT Inst. of SCC: delay, bad cooperation and poor management • BESIII SC magnet: Wang NMR Co. in some troubles • We could handle other problems, such as mechanics, control, electronics…
Spare Scheme of IR • Delay & uncertainties of IR devices commissioning : • SCQ + Valve boxes: later arrival and delay in installation • BESIII SC magnet • Possible further delay in installation, commissioning and filed mapping • A spare scheme of the IR lattice configuration without SCQ is designed and under preparation . • Two normal conducting bending magnets (70B) will replace the two SCQ IR magnets. • With this scheme, the outer ring (SR), the electron ring and positron ring can be commissioned. • The spare scheme is to save the time of about 3 months for the SCQ field measurement with detector solenoid and the field mapping of the detector solenoid itself.
Quality Control • Quality control system established: • Quality control manuals • Quality control forms • Quality controller • Review designs and prototypes • Monitor quality and progress in factories • Most of cases are successful, while some cases have problems in quality and schedule for various reasons. • In case of problem, quality is the first. • Over design happens some times.
Schedule • — 9 Oct. 2006: • Installation of two rings • Tuning and commissioning of devices and systems, including SCQ commissioning and field mapping • Alignment • Oct. 06 - July. 07: • Tuning of machine + SR running • Field mapping of SCQ + BESIII SC magnet • BESIII assembling and tuning • Aug. 07: BESIII detector moved into beam line • Sept. 07 : Starting machine-detector tuning. • Data taking by Autumn 2007
The BESIII Detector SC magnet Magnet yoke TOF Be beam pipe MDC CsI calorimeter
MDC electronics • 160 channel prototype system comics ray test and test beam • 512 channel system: final version • Oct. 2005 intl. review • Mass production under way
Calorimeter electronics • FE under production • 3 beam test and and 384 channel prototype: reach the performance. Noise: 1000 e/crystal 。 • Intl. review • On schedule
Installation of RPC into endcap -- 32 --
Mass production ---- Module test Test result of an endcap module ——after install Test result of a barrel module
BESIII Magnet Progress 绕线 包绝热膜 组装 安装 运输
Valve box of BESIII SC magnet Power leads thermal leakage
BESIII: work to be done • Challenge: BESIII SC magnet • Power Leads • Test of Valve box • Cool down of Magnet • Performance & Stability • Field mapping • Under construction • Structure of ECAL endcap • Assembling of subdetectors • Assembling BESIII • Tuning • Cosmic ray test
TCF50s passed assessment 冷箱 150L/h 500W@4.5K 主压缩机 14bar,78g/s 低温系统控制室
Cryogenics pipes made in IHEP 各种低温外管道 各种低温内管道 各种G10支撑件 8通道低温管线
Summary • LINAC tuning goes smoothly with good progress. • Manufacture of most of components of Storage rings and detector goes well. Some delays and technical difficulties in SC components. • So far, no fundamental problem found in the machine and the detector. • We are in a difficult period with many problems in quality and schedule. Great challenges in next 18 month. • About 4 month delay in schedule so far. • Thank you for helps from IMAC and many Labs