1 / 36

APS Implementation Improves Logistics Processes and KPIs

Summary of the last lecture on the implementation of APS, which resulted in significant improvements in planning, logistics, and KPIs. Includes lessons learned and detailed computer assembly supply chain process.

eleanora
Download Presentation

APS Implementation Improves Logistics Processes and KPIs

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PART IV ARCHITECTURE OF SELECTED APS

  2. SUMMARY of Last Lecture • The APS implementation resulted in major improvements of the planning and logistics processes and helped to improve major KPIs. Table 23.3 lists the improvement of logistical KPIs from 1999 to 2002 and the target value. The improvement of the customer service level and the delivery reliability resulted in additional revenue. Better forecast accuracy helped to reduce the inventory levels and by that reduced the direct material costs by approx. 0.3–2%. Through better planning support the inbound logistics costs and the process costs in purchasing and planning departments could be decreased. In addition to these business improvements the following “Lessons Learned” can be summarized from the project work: • • The batch interfaces between i2 and SAP R/3 were easier to implement and to manage than expected. For example the adaption of the interface programs from SAP R/3 3.0 f to 4.6 c was accomplished within 6 weeks without support by external consultants. • • The online integration between i2 Demand Fulfillment and SAP R/3 SD turned out to be rather difficult to implement and stabilize. Especially the consideration of the SD order types and the specific customizing of SD was a source of many issues.

  3. DETAILED COMPUTER ASSEMBLY SUPPLY CHAIN

  4. COMPUTER ASSEMBLY PROCESS The computer assembly process is divided into two main parts • • The assembly operations • • The testing and packing operations. The first step is the assembly of the system board. Boards are assembled in batches of 100–1,000 pieces. The board assembly lead-time for one batch is roughly half a day. There are approximately 20 different system boards for PCs and another 20 for servers. The system boards for notebooks are procured. The second step is the configuration of the board. In this step, the processor assembly—consisting of the processor and the cooling—and the memory are put onto the board.

  5. Cont’d…. • The third step is the kitting and the loading of the disk drive with the selected software. The kitting operation collects all selected components—disk drives, controller cards for network, video and sound etc.—into a box that is called the kit. The kit, the housing and the power supply—which are not part of the kit—are used in the fourth step, the actual assembly of the computer. If the customer has special requests—e.g. specific controller cards that have to be assembled into the computer—a separate customization step follows the computer assembly operation. After that, the computer is tested and packed. In the final packing operation the keyboard and accessories as mouse, manuals, software, cables etc. are added. The complete lead-time is 24–48 h. The most time consuming operations are the software loading and the test operations. There are two production types: small batches (usually below 200 PCs) are assembled in a job shop, large batches (above 200 PCs) are assembled in a flow shop. Please note that kitting takes place only for the job shop production type. In the flow shop, the material for the complete batch is provided along the production line.

  6. Unit Planning • Table 23.2 shows the levels of the geographic and the product hierarchies used in the demand planning process. The numbers given in parentheses specify the number of instances on that level. All Geo is the root of the geographic hierarchy. The area level represents geographically defined areas in the world, e.g. Europe, Middle East and Africa (EMEA); America; Asia Pacific. The regional level represents sales regions within an area, e.g. Germany, France and the UK are regions within the EMEA area. All_Prod is the root of the product hierarchy. The product segment level divides the product hierarchy into sub-hierarchies for PCs, servers, notebooks and the planned components (see next subsection). On the product group level each sub hierarchy is split into multiple product groups, e.g. the PC sub-hierarchy is split into consumer PCs and professional PCs, and the server sub-hierarchy into small servers and large servers. • The next level is the product family that groups products which are in the same performance class (low-end consumer PCs vs. high-end consumer PCs). The model line groups PCs and servers by the type of the housing. The sub model line groups PCs and servers within one model line by the type of the system board. The SKU level is normally not planned for units (refer to the next section about component planning for explanation why the SKU level is in the product hierarchy).

  7. PLANNING PROCESSES SUPPORTED BY I2 DEMAND PLANNER • Actual data: Three types of actual data are maintained: Shipments (quantities related to shipment date), orders (quantities related to customer requested date) and confirmed open orders (quantities related to confirmed date). • Budget plan: The budget plan is updated yearly and is valid for the current fiscal year. • Sales forecast: The sales forecast is created monthly and covers 6 months. The database contains four separate rows for the sales forecast, representing the current planning round and the last three planning rounds. • Plant forecast: The plant forecast is created weekly by the planners in the production sites. The database contains four separate rows for the plant forecast, representing the current planning round and the last three planning rounds. • Collaborative forecast: The collaborative forecast is determined monthly by a collaborative process in which sales, product management, procurement and the production sites participate.

  8. Component Planning • The business environment of this computer manufacturer was selected to be build-to-order and configure-to-order for the main part of the business. As the consequence of this decoupling point decision the main purpose of the monthly and weekly forecasting processes is the creation of an accurate forecast on component level (Fig. 23.5). The focus of the component planning process is therefore to generate a supplier forecast for all dependent components derived from the unit forecasts. Out of the approximately 2,000 components, 600 components are considered during component planning (A-parts). The planned components belong to the material groups processors, memory, disk drives, controllers, housing and power supply.

  9. 1. The collaborative forecast has to be split into (1) forecast related to fixed configurations and (2) forecast related to open configurations (that are still to be configured). 2. For forecasting fixed configurations, the bill of materials of the fixed configuration is being exploded. 3. For forecasting open configurations, the following steps are followed: (a) So-called mappings are defined that map some planned instances on finished goods level (e.g. a model line) onto planned components (e.g. disk drives, processors etc.). A mapping is established between a planned item A on finished goods level and all components C that can be configured into products of type A. (b) The distribution of the forecast on some planned item A on finished goods level over all components related to A by some mapping is defined by attach rates (i.e. distribution factors). The actual planning process is to determine these attach-rate factors. 4. The total component forecast of a component is derived by adding the forecast from Step 2 and Step 3. This component planning procedure is supported by i2 PRO (Product Relationship

  10. Operational Planning Operational Planning consists of the Weekly SCM Workflow and a consecutive MRP run in SAP not described in detail here. Weekly SCM Workflow The Weekly SCM Workflow consists of forecast netting, master planning and allocation planning and serves two purposes: 1. It calculates the total supply and capacity needed to fulfill the demand within the planning horizon and forms the basis for negotiations with suppliers and purchasing decisions. 2. It constrains the demand based on the feasible supply and serves as a medium to communicate deviations of forecast and availability. The demand planning process generates the forecasts for all products and components. This forecast is updated weekly and is netted against the actual orders received (forecast netting process, see Fig. 23.3). In the short-term the forecast for certain products or customers could already be realized in the form of actual orders.

  11. Cont’d.. The Weekly SCM Work flow is executed twice per week. In a first run the updated forecast plan from the demand planning process is taken and a fulfilment plan is generated publishing reports with defined problems in the supply chain. After the first run the exception handling starts and modifications are made to supply and demand data to solve the problems. During the Weekly SCM Workflow, the planners take the following actions: • Decisions about sourcing options (sourcing from multiple suppliers, sourcing from multiple plants, use of alternate parts) • Generation of supply requirements based on the netted forecast, including safety stock management decisions • Generation of a constrained demand plan on forecasted item level based on the netted forecast and the actual customer orders on hand • Generation of production requirements for make-to-stock forecast • Decisions about forecast shifts from one product to another due to supply constraints.

  12. Order Promising • The orders enter the system through the order entry process and are promised by the order promising process. To promise a new customer order the order starts searching for allocated ATP in the dimensions time, seller and product . Several consumption rules define how a new order can find ATP. The promising policies assigned to the orders define if the order is promised e.g. as a whole or in several partial deliveries. Again, one must distinguish between fixed configurations and open configurations: • Let us assume an order is received from a customer in France for x units of fixed configuration f with a request date for week w. The order promising process checks the quantity for the fixed configuration f that is allocated to France in week

  13. w; let us call this a. If the ordered quantity x is less than the allocated quantity a the order receives a due date in week w. If this is not the case, i.e. x > a, then additional ATP is searched in the preceding weeks—even if ATP is available in week w at other nodes of the customer hierarchy, e.g. Germany and the UK. This consumption rule ensures that quantities that have been planned by some region are reserved for orders coming from customers of that region. • Orders for open configurations are quoted based on the ATP for components. The order promising process searches the best ATP for each of the components required for the order. The latest ATP plus the configuration’s lead-time is assigned as due date to the complete order.

  14. Lecture 29 Oil Industry CHAP 24 • Mario Roitsch and HerbertMeyr

  15. LAYOUT • Introduction • Supply Chain Description and Typology Requirements for Planning • Requirements for Planning • Description of the Ideal Planning System • Modeling and Implementation of APS • Modules in Detail • Introduction of Supply and Demand Manager Hierarchical aggregation in Supply & Demand Planning, e.g., Commercial’s business unit • Hierarchical disaggregation in Product Supply Scheduling

  16. Introduction The oil market is a worldwide market. Due to an increasing demand of the fast growing countries like China and India, the oil market has been changing to a strong emerging market. Due to these effects the prices of raw material and finished goods have extremely increased and are strongly volatile. Faced with very complex production techniques and high investment costs for enlarging production capacities a European company needs a very high level of flexibility as well as integration in planning and scheduling in its supply chain to survive in the world market.

  17. Supply Chain Description and Typology Requirements for Planning On the base of these supply chain characteristics the main challenges for a planning, optimization and scheduling system are as following. Due to the long lead times for the refinery’s crude oil supply, the decision of crude oil purchase, e.g., which kind of crude oil sort in which quantity, at what purchase price and at what time—which is the most important financial decision—is the major focus. Therefore high forecast accuracy for a future customer demand per single product is fundamental.

  18. Requirements for Planning • On the base of these supply chain characteristics the main challenges for a planning, optimization and scheduling system are as following. Due to the long lead times for the refinery’s crude oil supply, the decision of crude oil purchase, e.g., which kind of crude oil sort in which quantity, at what purchase price and at what time—which is the most important financial decision—is the major focus. Therefore high forecast accuracy for a future customer demand per single product is fundamental. • After this decision about the crude oil supply the degrees of freedom for changes are limited, e.g., the ordered crude oil transported by ship cannot be switched or sold easily, at most with financial losses.

  19. Description of the Ideal Planning System • For all decisions mentioned in Sect. an integrated planning system, which generates solutions in an optimal way on various questions concerning the whole supply chain at different points in time, is required. Figure describes the entire planning system architecture. In this section, every single planning module of the developed planning system will be described. The corresponding software modules are then added in Sect. Every planning cycle starts with the Supply & Demand Planning (S&DP). The base for these forecasting processes are estimations from the market analysis department. This department is delivering expectations on market demands per country, on demanded product qualities and especially on expected price levels (quotations) for crude oil and finished products. Based on this information, planned sales numbers for the individual sales markets will be collected from every sales channel, e.g., estimated sales quantities and sales prices per region for diesel.

  20. Cont’d….

  21. Cont’d…. Parallel to this the evaluation of quantities, available on external supply sources, and their corresponding prices (purchase costs) for different crude oil sorts, semi finished products and finished products takes place, e.g., the available quantities and the purchase costs of the finished product diesel at an external refinery. To leave freedom for optimization the potential sales quantities as well as the available purchase quantities are planned as minimal and maximal bounds on sales/purchase. Additionally, availabilities of finished products on external sources (as input for a “make-or-buy” decision) and their purchasing costs have to be estimated.

  22. MODELING AND IMPLEMENTATION OF APS • For the implementation of the planning concept of Sect. 24.3 within a real-world planning system a variety of commercial software modules is needed (see Fig. 24.3). • Their detailed description is the focus of this section. To put the S&DP into practice the SAP module SAP APO DP (see Chap. 18) has been selected. Hereby it is unconventional for an APO DP usage that not only the demand but also sales prices are estimated and aggregated over three stages of the customer hierarchy. Additionally, availabilities, purchase prices and logistics cost rates of the crude oil supply have to be estimated.

  23. Modules in Detail • The implementation of the S&DP, PSS planning and ATP logic in SAP APO took place in two large APS projects, which will in the following be presented in detail. Thereby, the time period of carry out extended over 4 years. • Introduction of the Supply & Demand Manager • The first project, the “Introduction of the Supply & Demand Manager (S&DM)”, • was motivated by the following objectives:

  24. Introduction of Supply and Demand Manager • Introduction of a standardized and integrated planning system in all countries for the S&DP, including the features: – Automated collection of all relevant MP data, uniform for all countries and sales channels – Creation of a harmonized data base for all planning data • Simultaneous forecasting of quantities and prices/costs (concerning customer demand, external purchasing and crude oil supply) • Enabling process transparency & -monitoring (alerting) • Increase of forecast accuracy by introduction of an APS-based Demand Planning module • Higher transparency of the MP results by implementing a web-based front end reporting. Thus an APS module was looked for, simultaneously supporting both the existing MP solution and the above mentioned aims. After an extensive blueprinting and a following proof of concept SAP APO was chosen as the software module for putting the S&DP processes into practice.

  25. Cont’d….

  26. Cont’d… In order to sufficiently represent the existing business model, six forecast dimensions as well as nine related attributes had to be introduced and stored. In the following examples (see Fig. 24.4) we will concentrate on the three dimensions • • Sales channel, comprising product (groups) like gasoline, diesel, heating and aviation fuel, which are assigned to business units like “Retail” (responsible for filling stations) or “Commercial” (responsible for heating, aviation, etc.) • • Geography, comprising customer (groups), regions, countries and clusters (e.g., a set of countries) • • Time (e.g., days, months). The planning process of the S&DM usually starts with forecasting the future (basic) prices of crude oil (Brent), the finished products’ quotations or reference quotations for local markets as well as the exchange rates for the relevant countries. For markets, which are not directly following the global prices, a local finished product price scenario and local purchase prices (prices which the company could buy for from external refineries) have to be estimated.

  27. Hierarchical aggregation in Supply & Demand Planning, e.g., Commercial’s business unit

  28. Implementation of Product Supply Scheduling • The second project, the “Implementation of the Product Supply Scheduling”, had the following objectives: • Introduction of a standardized and integrated Allocation Planning and Quota Management system in all countries to close the gap between MP and the operational fulfillment of the customer demand, including the features – Hierarchical disaggregation of the MP results as part of the Allocation Planning – Possibility to provide sales & supply patterns for all quotas – On-line interface for monthly quota check between SAP APO and SAP R/3 SD • Calculation and estimation on the progress of quota consumption during the month for all responsibility levels (refinery production, depot supply & management, sales, purchase) and aggregation levels • On-line volume (quota) availability check by creating a customer sales order • Handling of quota changes via cockpit • Monitoring, alerting and web-based presentation of unexpected deviations in quota consumption • Setting up a performance management to measure the planning quality, the scheduling efficiency (sales pattern accuracy) and Quota Management efficiency for all responsibility levels.

  29. Hierarchical disaggregation in Product Supply Scheduling

  30. Cont’d…. • The MP optimization results, which are stored in the SAP APO BW, are the starting point for the Allocation Planning (AP). They are uploaded into a separate planning sphere for both AP and the later Quota Management. Since the MP results are only available in an aggregate form, e.g., over all customers of a business unit, it is up to AP to disaggregate them again according to the different dimensions of the forecasting hierarchy (see Fig. 24.6). This is a crucial task if the scarce capacities of MP led to (aggregate) shortages of the original (detailed) forecasts (see Sect. 9.4.4). AP supports this allocation by providing rules for the automatic disaggregation along inter sections of the sales channel/geography dimensions and along the time dimension.

  31. Cont’d…. • To create this separate sphere the structure of the optimization result has to be extended for the missing attribute combinations, e.g., from business units/clusters to products/customers. Next the allocation of the available quantity per product/ customer along the sales channel/geography dimensions takes place as following: at first the minimally demanded quantity (i.e., the detailed minimum sales quantity estimated in S&DP, the so-called “contract quantity”) will be replenished on the lowest level of the hierarchy. Thereafter the residuary quantity, which is the quantity the optimization model has determined between the aggregate minimum and maximum boundaries of MP, will be allocated to the customer with the highest sales price. The quantity on that customer is replenished until its maximum is reached (i.e., the detailed maximum sales quantity forecast in S&DP). After that the customer with the second highest price gets the quantity up to its maximum and this sequence goes further until all MP quantities are allocated.

  32. Summary For all projects a detailed business case with a net present value calculation on the entire supply chain was employed in advance. The resulting, here represented, benefits evidently indicate a two-digit million Euro amount. For the monitoring of these benefits a continuous recalculation took place and has confirmed the assumed benefits. Simultaneously, a performance management system was established along the new APS-supported processes. Summarizing, all these benefits lead to a stable and durable enhancement of the margin contribution along the complete downstream supply chain and a competitive advantage of the company in the relevant market. At the same time especially the high grade of flexibility and integration of the available planning, optimization, scheduling and management systems. Smaller raw material costs through an enhanced crude oil selection to fulfill the market demand,

  33. Cont’d…. • Reduction of production costs through a decrease of variable production costs • Reduction on working capital costs in inventories of crude oil and finished products • Enforced utilization of margin upgrade potentials through increased transparency • Persistent realization of the MP (optimization) results through quota formation and quota management, as well as its coordination over different responsibility levels • Transparency and as a result acceptance of decisions. Future main emphases will be identified and pursued further in the field of demand forecasting, short-term optimization, scheduling and management of the supply chain under the criteria of revenue management.

More Related