1 / 10

THRESHOLD CRITERIA FOR DETERMINING FRACTURE REPAIR PROCEDURES

THRESHOLD CRITERIA FOR DETERMINING FRACTURE REPAIR PROCEDURES. SSC Project Recommendation for FY-2008. BACKGROUND. Steel Repair NVIC 7-68 explains how to properly insert hull plating, but lacks guidance as to when

elina
Download Presentation

THRESHOLD CRITERIA FOR DETERMINING FRACTURE REPAIR PROCEDURES

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. THRESHOLD CRITERIA FOR DETERMINING FRACTURE REPAIR PROCEDURES SSC Project Recommendation for FY-2008

  2. BACKGROUND • Steel Repair NVIC 7-68 explains how to properly insert hull plating, but lacks guidance as to when • Critical Length and brittle mode of fracture are difficult to relate to actual ship hull plating situations • Modern welding technology has improved quality of gouge & re-weld repairs, including a smaller heat-affected zone • Loss of West Coast repair drydock capacity has caused increased use of in-water dry habitat technique (i.e., welder in an evacuated box) for below-the-waterline fracture repairs

  3. CASE HISTORY 1 • Travelers attended an ACP-enrolled TAPS tanker on drydock in Singapore • MISLE history revealed 4 previous amidships in-line transverse bottom shell fatigue fractures, all repaired in-water (over several years) by gouge & re-weld • Longest = 62” and running into an erection butt • Fractures caused by a design detail problem that had been corrected

  4. CASE HISTORY 1 • In the past, these kind of repairs would have been considered temporary, but class now accepting them as permanent • Travelers recommended:- ABS improve weld procedure;- Notation to re-examine at the next drydocking; • Owner’s steel superintendent opted to crop out a 2.5m wide band from bilge to bilge because he felt he could not guarantee against re-fracturing

  5. CASE HISTORY 2 • Travelers asked to consult on a side shell fracture found in way of a deep tank on an ACP enrolled operating container ship in service • Question specifically was:- whether a gouge and re-weld job as proposed by the company was an acceptable repair- if so, would it be considered a temporary repair and for how long- if not, what would be the basis for considering the repair permanent

  6. CASE HISTORY 2 - Longitudinal fracture - 2-3 inches in length- 3/4 inch high tensile steel plate- Below the loaded waterline -Next scheduled drydocking in 1 year

  7. CASE HISTORY 2 - 2-3 inches from longitudinal weld seam

  8. CASE HISTORY 2 • Because deep tank emptied and fracture above the waterline after cargo discharge, local CG preferred permanent repair by insert IAW limited guidance in Steel Repair NVIC 7-68. • Travelers and ABS recommended:- NDT and safe-ending of fracture;- Gouge and re-weld;- Operate with deep tank empty;- Regular visual exam by crew and report any change;- Condition of Class to re-examine at the next drydocking; • Owners conducted repairs per the above. Repair inspected by CG and after voyage from West Coast to China and return • Final disposition of repair referred to Class

  9. NEED FOR PROPOSED STUDY • Field needs a reference that provides a review of the sum total of factors to be considered when deciding whether to gouge & re-weld or to insert hull plating including, where appropriate, threshold criteria • Factors would include location, orientation, relation to previous repairs, plate material & condition, inset damage, upset internal structure, vessel service, etc., etc. • Establishment of post-repair policy also needed (e.g., appropriate NDT, scheduled re-examination, etc.)

  10. NEED FOR PROPOSED STUDY • This guidance would mitigate the overall lessening of experience levels among CG marine inspectors and other maritime professionals due to:- the decline in the size of the U.S. flag fleet; - the advent of the ACP program; - the decrease in stateside deep draft hull repair availabilities; and - continued advances in welding/repair technologies

More Related