1 / 13

CREZ Transmission Optimization (CTO) Study Overview

CREZ Transmission Optimization (CTO) Study Overview . Dan Woodfin Director, System Planning. Designated Zones and Scenario Wind Levels. Scope of Study. Scope of 2006 CREZ Study. Scope of 2008 CTO Study. 4850 MW. ~10,000 MW. ~12,000 MW. ~25,000 MW.

elinor
Download Presentation

CREZ Transmission Optimization (CTO) Study Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CREZ Transmission Optimization (CTO) StudyOverview Dan Woodfin Director, System Planning RPG-CREZTF

  2. Designated Zones and Scenario Wind Levels RPG-CREZTF

  3. Scope of Study Scope of 2006 CREZ Study Scope of 2008 CTO Study 4850 MW ~10,000 MW ~12,000 MW ~25,000 MW Number and complexity of different transmission options increases exponentially RPG-CREZTF

  4. Study Approach • Develop a number of significantly different core concepts and test their performance • Variations on the concepts with best performance will be developed and tested • The best performing plan will be selected for the scenario Significantly-Different Plans, e.g. Scenario 2 Range of Potential Solutions RPG-CREZTF

  5. Study Approach • May use the same core concepts as bases for significantly different plans in different scenarios Scenario 2 Scenario 1 Scenario 3 • But a different core concept may provide the basis for the preferred plan for a different scenario RPG-CREZTF

  6. Concepts High-level Concepts under study include: • Incremental 345 kV transmission system for wind in west Texas • Integrated 345 kV transmission system for wind in west Texas • Reduced number of right-of-ways using higher voltage circuits (500 kV or 765 kV) • Shorter wind connections with low impedance backbone or loop • Low impedance loop circuits (around load centers and/or around wind generation zones) • HVDC circuit(s) to move power to load centers or between load centers, integrated with 345kV upgrades RPG-CREZTF

  7. Recommended Plan Optimized for each Scenario 12 GW 18 GW 25 GW 24 GW 1 2 3 4 RPG-CREZTF

  8. Staging and Expansion • Will develop a preferred plan that is optimized for each of the four scenarios • Will provide expansion path of what elements in each of these plans should be built first if that Scenario is selected (except for Scenario 1) • Use lower scenarios as basis • Will develop an expansion path from the preferred plan for the lower scenarios, so as to allow for consideration of future expandability of those plans • Using next higher scenario as basis RPG-CREZTF

  9. Staging and Expandability 12 GW 18 GW 25 GW 24 GW 1 1+ 2 2+ 2 - 3 3 - 3 - - 4 4 - 4 - - RPG-CREZTF

  10. Certainty 12 GW 18 GW 25 GW 24 GW • Collection systems, transmission from west to east, and integration into eastern portion of grid are well defined • Recommended projects fit into plan for expansion to next level • All relevant studies have been completed • Transmission owners have agreed to feasibility of connections into existing facilities • Some minor changes may be necessary as result of routing analysis 1 1+ 2 2+ 2 - 3 3 - 3 - - 4 4 - 4 - - RPG-CREZTF

  11. Some Additional Study 12 GW 18 GW 25 GW 24 GW • Collection systems and transmission from west to east are well defined • A viable, near-optimal plan for integration into eastern portion of grid has been identified • Further work and a few changes in endpoints may be necessary before finalizing integration into the eastern portion of the grid • Additional requirements to address feasibility of upgrades in east • Need to include consideration of other requirements in east 1 1+ 2 2+ 2 - 3 3 - 3 - - 4 4 - 4 - - RPG-CREZTF

  12. Flexibility 12 GW 18 GW 25 GW 24 GW • Collection systems in the west are well defined • A viable plan for transmission from west to east and integration into eastern portion of grid has been identified, based on powerflow and stability • Additional work will be needed; capacity and positioning of west to east paths may change, as well as system upgrades in the eastern portion of the grid, based on consideration of additional system requirements 1 1+ 2 2+ 2 - 3 3 - 3 - - 4 4 - 4 - - RPG-CREZTF

  13. Questions?

More Related