CERN workshop upgrade Aida Rui De Oliveira

CERN workshop upgrade Aida Rui De Oliveira. CERN workshop upgrade for MPGD. First step: buy and install 9 machines. The 9 machines are at CERN 6 are installed and commissionned : (large laminator, large oven, photoresist stripping for GEMs, electro-chemical etching line for

Download Presentation

CERN workshop upgrade Aida Rui De Oliveira

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CERN workshop upgrade Aida Rui De Oliveira Rui De Oliveira

  2. CERN workshop upgrade for MPGD • First step: buy and install 9 machines. • The 9 machines are at CERN • 6 are installed and commissionned: (large laminator, large oven, • photoresist stripping for GEMs, electro-chemical etching line for • GEMs, large UV lamp, Polyimide etching line). • 3 are still not installed (photoresist development, Copper etching, • photoresist stripping). • They will be installed directly into the new building 107 • This decision does not affect the running R&Ds • Second step: • -redefine all the process parameter related to the new equipments • -Build some prototypes of the # detectors • We have built large detectors for CMS , Kloe , Jlab, ATLAS… Rui De Oliveira

  3. TE/MPE/EM Workshop upgrade • An agreement was reached with CERN management in 2010 to purchase the subset of machines necessary to carry out R&D on large size GEM • (2m x 0.5 m) & Micromegas (2m x 1m) and the associated large size • read-out boards in the current CERN TE/MPE/ME facility. • GEM market call for order received ready • survey tender • 1 continuous polyimide etcher x x x x 06/2012 • 1 Cu electroetchline x x x x 06/2012 • Micromegas • 1 large laminator x x x x 06/2011 • 1 large Cu etcher x x x x postponed • 1 large UV exposure unit x x x x 06/2011 • 1 large resist developer xxx x postponed • 1 large resist stripper xx x x postponed • 1 large oven x x x x 06/2011 • 1 large dryer x x x x 06/2011 Rui De Oliveira 3

  4. UV exposure unit limited to 2m x 0.6m  2.2m x 1.4m • Resist developer limited to 0.6m width  1.2m • Resist stripper “ • Copper etcher “ • Dryer “ • GEM resist stripping limited to 1m  2m • GEM electro etch “ • GEM polyimide etch limited to 1m  2m • Ovens limited to 1.5m x 0.6m  2.2m x 1.4m • Laminator limited to 0.6m width  1.2m Rui De Oliveira

  5. Ovens limited to 1.5m x 0.6m  2.2m x 1.4m • In building 102 . Rui De Oliveira

  6. UV exposure unit limited to 2m x 0.6x  2.2m x 1.4m • In building 254 Rui De Oliveira

  7. GEM polyimide etch limited to 1m x 0.5m  2m x 0.5m • In building 254 Rui De Oliveira

  8. Laminator limited to 0.6m width  1.4m width • In building 102 . Rui De Oliveira

  9. Resist stripping limited to 1m x 0.5  2m x 1m • In building 102 . Rui De Oliveira

  10. CMS GE1/1 GEM detector • 1m x 50cm • 5 detector produced • ATLAS MuonsMicromegas detector • 1m x 1m active area (1 detector produced) • 2m x1m Rui De Oliveira

  11. CERN funded the machines. AIDA funded 2 years of a technician(240 kCHF). • Julien Burnens, 6 months • Michal Zientek, 12 months • Looking for somebody for the 6 remainingmonths. Rui De Oliveira