Positron Target Prototype - Status

Positron Target Prototype - Status. Leo Jenner. Overview. The set-up Latest Simulation Project plan Progress. ILC. The plan is still the same…. Sweep in parameter space of B-Field, Rotation Speed and Immersion (1 T, 2000 rpm, 50 mm) Observation of kicks as spokes traverse field

elvis
Download Presentation

Positron Target Prototype - Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Positron Target Prototype - Status Leo Jenner LC-ABD / LCUK, Bristol

  2. Overview • The set-up • Latest Simulation • Project plan • Progress LC-ABD / LCUK, Bristol

  3. ILC LC-ABD / LCUK, Bristol

  4. LC-ABD / LCUK, Bristol

  5. LC-ABD / LCUK, Bristol

  6. The plan is still the same… Sweep in parameter space of B-Field, Rotation Speed and Immersion (1 T, 2000 rpm, 50 mm) Observation of kicks as spokes traverse field Measurement of eddy currents by torque and direct heating ( Lei Zang: PhD student, Liv ) Additional support from Duncan Scott ( ASTeC ) Study of rotor-dynamics (LLNL: accelerometers) Simulations from Jim Rochford (RAL) in parallel with LLNL Tues Mar 24 LC-ABD / LCUK, Bristol 6

  7. Immersion 2000 rpm 1500 rpm 1000 rpm 500 rpm Speed 1.0 0.8 0.6 0.4 0.2 0 B-field Tues Mar 24 LC-ABD / LCUK, Bristol 7

  8. Carmen spoke model • Model results; full revolution • Here we see the torque peaks correspond to each point a spoke crosses the –ve X axis i.e. when a spoke passes through the coil centres 90o 162o 18o rotation 234o 18o 162o 234o 306o 90o 306o • Retarding torque predicted by CARMEN for 100rpm for a full revolution Alignment at t=0

  9. LC-ABD / LCUK, Bristol

  10. LC-ABD / LCUK, Bristol

  11. Conclusion • I’m confident the experimental programme will be completed in the next 2 months • PAC paper, NIM paper will follow • Thank you and goodbye!