Steps for Permitting a Wastewater Spray Irrigation System in Delaware

Steps for Permitting a Wastewater Spray Irrigation System in Delaware. Ronald E. Graeber Program Manager Ground Water Discharges Section Division of Water Resources (302) 739-9948 Ronald.graeber@state.de.us. Letter of Intent. Department response. Identifies need for:

elyse
Download Presentation

Steps for Permitting a Wastewater Spray Irrigation System in Delaware

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Steps for Permitting a Wastewater Spray Irrigation System in Delaware Ronald E. Graeber Program Manager Ground Water Discharges Section Division of Water Resources (302) 739-9948 Ronald.graeber@state.de.us

  2. Letter of Intent • Department response. Identifies need for: • Site Selection and Evaluation Report • Site Inspection • Design Development Report • Permit Application and Public Notice • Plans and Specifications • Plan of Operation and Management • Trust Indenture or CPCN for privately owned facilities

  3. Site Selection and Evaluation Report • Submitted for Department review • Provides preliminary site details • Department conducts site inspection • Site concurrence or denial issued by Division • Table 201-2 of the Regulations

  4. Design Development Report • Submitted for Department review • Detailed Soils Report, Wastewater Treatment details, Vegetative Management Plan, LLC • Accepted by Department as the basis for facility design • Table 202-1 of the Regulations

  5. Plans and Specifications • Submitted by owner for Department review • Checked against accepted Design Development Report • Approved by Department for construction and incorporated into final LTS permit • Should be of “Biddable” quality • As-Built Drawings must be submitted following construction

  6. Application for permit • Permit application requested from owner • Permit application completed and submitted to Department • Application reviewed and checked against Design Development Report

  7. Public Notice • Public Notice drafted by Department • Public Notice advertised by Department; billing sent to owner • Public comment period • Public Notice requirements completed (hearing held if necessary) • Trust Indenture or CPCN executed for privately owned facilities • Applicant is responsible for paying for the Public Notice cost

  8. Land Treatment System (LTS) Permit drafted • Industrial pretreatment requirements included if necessary • Draft permit and monitoring requirements sent to owner for comment • Draft permit modified if necessary

  9. Land Treatment System (LTS) Permit issued • Permit signed • Sent to facility owner • Facility construction begins

  10. Plan of Operation and Management • Submitted by owner for Department review • Approved by Department • Incorporated into final LTS Operating Permit • The Final Operation and Management Plan must be approved by the Department prior to issuance of an Authorization to commence operation at design flow

  11. Certification of Construction Completion • Submitted to Department by design engineer • Department conducts facility inspection to verify compliance with approved plans and specifications

  12. Authorization to commence operation at design flow • Begin Ground Water Sampling • Initiate Effluent Sampling requirements • Submission of As-Built Drawings • All Permit Requirements and Limitations become effective

  13. Thank-you Q U E S T I O N S ? C O M M E N T S