The Rebirth of the Davis Hall Network Room. December 2009. Before (1) - How it used to be…. Before (2). Before (3). Before (4). Before (5). Before (6). After (2). After (1) – Gotta start somewhere.
E N D
The Rebirth of the Davis HallNetwork Room December 2009
Before (1) - How it used to be… Before (2)
Before (3) Before (4)
Before (5) Before (6)
After (2) After (1) – Gotta start somewhere
After (3) – The rack is installed but had to precariously move the phone blocks to the side temporarily…….very time consuming After (4) – oy vey…..
After (5) – all the switches, POE injector, UPS’s and video transceivers have been installed (but no patch cables yet) and phone blocks still hanging on the side After (6) – ethernet + fiber-optic patch cables are connected and phone blocks moved from the side
After (7) – phone blocks are installed above the rack After (8) – fiber-optic patch panel and iLon box + cables properly installed and routed
After (9) – All done! After (10)
After (11) After (12)
After (13) After (14)
UPDATE (July 2013):Replaced two of the oldest switches with a single new switch After (15)