GreenSlot : Scheduling Energy Consumption in Green Datacenters

GreenSlot : Scheduling Energy Consumption in Green Datacenters. Íñigo Goiri , Kien Le, Md. E. Haque , Ryan Beauchea , Thu D. Nguyen, Jordi Guitart , Jordi Torres, and Ricardo Bianchini. Motivation. Datacenters consume large amounts of energy Energy cost is not the only problem

emele
Download Presentation

GreenSlot : Scheduling Energy Consumption in Green Datacenters

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GreenSlot: Scheduling Energy Consumption in Green Datacenters ÍñigoGoiri, Kien Le, Md. E. Haque, Ryan Beauchea, Thu D. Nguyen, JordiGuitart, Jordi Torres, and Ricardo Bianchini

  2. Motivation • Datacenters consume large amounts of energy • Energy cost is not the only problem • Brown sources: coal, natural gas… • Lots of small and medium datacenters • Connect datacenters to green sources • Solar panels, wind turbines… • Green datacenter

  3. Green datacenter • Energy sources • Solar/wind: variable availability over time • Electrical grid: backup • Other (problematic) approaches • Batteries: losses, cost, environmental • Bank energy on the grid: losses, cost, unavailability Wind Power Solar Power Time

  4. Scheduling scientific workloads • Batch jobs • User specifies: #nodes, estimated runtime, deadline • Challenge • Match workloads with green energy availability Power Load Time

  5. GreenSlot • Predict green energy availability • Weather forecast • Schedule jobs • Maximize green energy use • If green not available, consume cheap brown • May delay jobs but must meet deadlines • Turn off idle servers to save energy

  6. Dealing with energy costs • Schedule jobs: evaluate energy cost • Green energy is “free” (amortization): $0.00/kWh • Cheap (off peak, 11pm to 9am): $0.08/kWh • Expensive (on peak, 9am to 11pm): $0.13/kWh • Optimization goal • Minimize energy cost while meeting deadlines

  7. Conventional vsGreenSlot J3 J2 Power Nodes J1 J3 J3 J2 Power Nodes J1 J3 J1 J2 Now Time

  8. GreenSlot: scheduling round • Divide “scheduling window” into slots (15 minutes) • Predict green energy availability • Consider jobs by earliest start deadline • Calculate cost starting at every slot • Schedule job at the cheapest slot • Dispatch actions • Calculate and start required servers • Start jobs to be executed now • Deactivate unneeded servers (ACPI S3 state) Power Time

  9. GreenSlot: scheduling round • Divide “scheduling window” into slots (15 minutes) • Predict green energy availability • Consider jobs by earliest start deadline • Calculate cost starting at every slot • Schedule job at the cheapest slot • Dispatch actions • Calculate and start required servers • Start jobs to be executed now • Deactivate unneeded servers (ACPI S3 state) 10 5 0 0 0 5 10 15 X X Power Time

  10. GreenSlot behavior Schedule: J1, J2 J2 J2 Power Nodes J1 J1 J1 J2 Now Brown electricity price Time Job deadline Scheduling window

  11. GreenSlot behavior Schedule: J3, J4 J2 J2 J4 J4 Power Nodes J3 J3 J1 J1 J3 J4 Now Brown electricity price Time Job deadline Scheduling window

  12. GreenSlot behavior Schedule: J4 Weather prediction was wrong J2 J2 J4 J4 Power Nodes J3 J3 J1 J1 J4 Now Brown electricity price Time Job deadline Scheduling window

  13. GreenSlot behavior Schedule: J5 J2 J2 J4 J4 Power Nodes J3 J3 J5 J5 J1 J1 J5 Now Brown electricity price Time Job deadline Scheduling window

  14. Evaluation methodology • Cluster with 16 nodes • Modified version of SLURM • GreenSlot implemented on top • Energy profile • NJ electricity pricing (on/off peak) • Solar farm energy availability (10 panels) • Four weeks (most, best, average, and worst) • Schedulers • Conventional: EASY backfilling • GreenSlot: Green energy, Brown electricity price

  15. Evaluation methodology • Workload • Real workload from BSC • Workflows for sequencing yeast genome • 5 days (Monday to Friday) • Deadlines: 9am, 1pm, and 4pm Monday Tuesday Wednesday Thursday Friday

  16. Energy prediction vs actual

  17. GreenSlot for BSC workload Conventional 26 kWh 75 kWh $8.00 24% cost savings 38 kWh 63 kWh $6.06 -24% GreenSlot

  18. GreenSlot for BSC workload

  19. Other results • Impact of weather miss-predictions • Less than 1% cost savings • Workloads variations: Staggered and Multi-node • Consistent green energy increases and cost savings • Workload intensity (datacenter utilization) • Works well with low/medium utilization • High switches to conventional • Inaccurate user run time estimations • Maximum cost increase of 2%

  20. Staggered workload Conventional 32 kWh 69 kWh $8.58 30% cost savings 38 kWh 63 kWh $6.00 -30% GreenSlot

  21. Conclusions • Parallel job scheduler for green datacenters • Predicts green energy availability • Increases the use of green energy • Reduces energy related costs • Solar array amortized in 11 years (18 years originally) • We are building a solar-powered μDatacenter

  22. GreenSlot: Scheduling Energy Consumption in Green Datacenters ÍñigoGoiri, Kien Le, Md. E. Haque, Ryan Beauchea, Thu D. Nguyen, JordiGuitart, Jordi Torres, and Ricardo Bianchini