1 / 13

Resident Engineer Training

Resident Engineer Training. Ken Jacoby Federal Highway Administration Office of Asset Management . AASHTO Subcommittee on Construction 2010 Annual Meeting Burlington VT. Background. TCCC Study (2003) 53% of states have no formal training for construction managers

emiko
Download Presentation

Resident Engineer Training

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Resident Engineer Training Ken Jacoby Federal Highway Administration Office of Asset Management AASHTO Subcommittee on Construction 2010 Annual Meeting Burlington VT

  2. Background • TCCC Study (2003) • 53% of states have no formal training for construction managers • Provided information that could help states in developing academies • Did not provide a curriculum of formal training • FHWA“Phase 1” Initiative (2009) • Follow-up to the TCCC Study • Provided a recommended curriculum of courses for an academy.

  3. Phase 1 – Curriculum • Total of 9 subject areas • Total of 38 courses within the 9 subject areas

  4. Subject Areas • Considerations during Project Development • Constructability reviews • Value Engineering • Construction involvement during design process (e.g. specification development) • Environmental commitments • Post construction meetings • “Hand-off” from project development to construction • Project review prior to construction • Life cycle cost (LCC) analysis and LCC management • Alternative technical bids • Technical • Grading • Drainage • Aggregate Inspection • Geotechnical Construction • New Structure Construction • PCC Pavement Field Inspection • Hot Mix Asphalt Field Inspection • Asphalt Recycling • Landscaping

  5. Subject Areas (continued) • Safety and Legal • Worker and work zone safety • Safety inspection standards, tools and techniques • Role of Construction Project Manager in work zone safety • OSHA compliance and injury prevention • State specific occupational safety and health program • Construction Law • Statutory lien rights for builders and contractors • Bonding requirements • Interrelation of project owners, contractors, and other stakeholders • Project documentation • Project Controls • Scope, Schedule & Budget • Earned Value Methods • Critical Path Method (CPM) Scheduling • Life Cycle Cost Analysis/Life Cycle Management (LCM) • Risk Management • Change Management

  6. Subject Areas (continued) • Methods of Payment • Bid items • Agreed price • Lump sum price • Force account • Claims • Partnering • Alternative Dispute Resolution • Types of claims: delay, changed conditions, etc. • Project Closeout • Need for consistent and regular project documentation • Contractor performance measurement/documentation • Final acceptance of a project • Contract Administration • Approaches to Contracting • Contractor Payments and Retainage • Contractor payment estimates and payment timelines • Incentives and disincentives • Retainage • Liquidated damages • Supplemental Agreement • Change orders • Justification statements for change orders • Design/redesign during construction phase • Specifications • Interpret specifications for change orders

  7. Subject Areas (continued) • Quality Management • Project Manager’s use of QA information • Elements of a “good” QC plan and QC data analysis • Construction and materials acceptance • Construction inspection and workmanship • Independent Assurance • Project Quality considerations: • Different acceptance criteria and methods based on procurement methods • Scope, location and size of the project(s) • Coordination of multiple projects • When project work is conducted (day time, night time) • Environmental • Compliance, Review & Mitigation • Stormwater Pollution Prevention • NPDES permits • Environmental Permits, Certificates and Licenses • Hazardous Materials • Erosion and Sediment Control • Water & Sanitary Sewer Facilities • Environmental stipulations regarding pollution (water, air & noise), archeological, paleontological findings • Best practices in environmental compliance, review and mitigation

  8. Subject Areas (continued) • Interpersonal and Leadership Skills • Communication • Leadership • Public Relations • Conflict Resolution • Ethical Conduct • Third Party Coordination • Common issues in third party coordination and the role of the PM • Permits and Agreements • Location, Mapping, Survey • Railroads • Subsurface Utility Engineering

  9. Available Courses Summary

  10. Gap Matrix

  11. Academy Considerations • Develop as a “curriculum” rather than a “course”. • Utilize training materials and training frameworks available from various states and NHI. • Manage scope as courses are developed. • Consider all available delivery methods

  12. Next Steps • Obtain external input and validation • Establish Technical Panel for curriculum and course development • Finalize course curriculum and training course outline • Refine scope, target audience, and outcomes for proposed course • Initiate training course development contract

  13. Thank You! For More Information Contact: Ken Jacoby Telephone: (202) 366-6503 Email: Ken.Jacoby@dot.gov

More Related