480 likes | 802 Views
Milt Stoltzfus Area Training Supervisor PFS Corporation. In-Plant Construction Examples for Factory Built Structures. Example of Point Loads. 28’ wide by 40’ long box. Microlam bearing at single 2x12 matewall header. Example of Floor Loads at Rim. Two-Story.
E N D
Milt Stoltzfus Area Training Supervisor PFS Corporation In-PlantConstruction Examples for Factory Built Structures
Example of Point Loads 28’ wide by 40’ long box Microlam bearing at single 2x12 matewall header
Example of Floor Loads at Rim Two-Story Failure of Connector plate on top of column support. Uncovered Electrical Junction Box
Example of a Rated Assembly R301.4 – Storage Load 20# Fire Separation Wall Piping not supported
R314.2.1 Minimum –3/4”, maximum 1-1/4” nosing
R314.2 8-1/4” maximum high
Chapter 3 Gable panel not fastened – loose in its opening
P3105.2 Vent air below centerline of trap arm
P3105.2 – Pipe Sizes must increase Illegal trap arm – center line of trap arm places vent opening lower than center
P3201.5 – S traps prohibitedP3201.6 – Trap to protect Fixture Drain No primer on glue joints No insulation in floor NM cable sheathing (no interior cable) used as 3” DWV hanger
R502.8.1 Hole drilled within 2” of edge of floor joist
P2603.2.1 – Pipe ProtectionNEC 300.4 (A) (1) Double rim of floor system at marriage line cut away for DWV run (to stay above floor joists)
R502.8.1 Holes drilled within 2” of edge of floor joist Note double joist repair
R502.8.1 & P3005.1 Notch shall not exceed 1/6 the depth Note vent elbow at the left
P3005.1 3” vent elbow as a drain fitting
P3114.4, P3201.5 & P3104.4 Air admittance valve below trap wier S trap Flat dry vent below the flood level of the fixture
R602.8 Firestopping incomplete at hole through floor decking & wall plate
P3201.5, P3101.2.1 & P3104.4 Tub trap = S trap No fire stopping (site installed) No Vent Dry horizontal vent below the flood level of the fixture
P3201.4 Building Trap – Not permitted
P3104.2 Vent inside roof cavity does not slope to drain Slope of vent – belly in the middle
Workmanship Oversized hole through the roof decking
Rated Assembly One 2” pipe is missing fire collar at through-penetration R602.6 – Excessive notches in wall framing members Table P2605.1 – No mid-story support for PVC pipe P2603.2.1 – Pipe protection not sufficient / correct at wall plates
P3201.5 No fire stopping at floor cut-out Tub Trap = S trap
P3105.2 Shower Trap – Vent connection below the trap weir
P3104.4 Horizontal dry vent below the flood level of the fixture
R502.6 & R502.2.1 Improper installation of metal joist hangers Deck rim nailed directly through the siding
R502.6 & R703.8 No hangers at the deck joist to deck rim No flashing at deck rim to house
R502.6 No ledger or hangers at joists to mate wall rim joist Large gaps between halves 2 members not capable of supporting the imposed load/span All 4 members needed, tied together
R502.6 Improper hanger installation / lack of effective bearing
R303.3 Bath exhaust fan not connected to exhaust duct
NEC 300.4 (A) (1) NM cable through a hole in a 2x4 stud where the hole is less than 1-1/4” from the edge – no protection (plate, sleeve)
NEC 320.23, 334.30 & 110.26 NM cables in/through attic access opening NM cables not secured within 12” of panel box Insufficient clearance at front (36” depth x 30” width)
Good Installation Clean box, line side – Length of conductor
NEC 314.17 (C)(Exception) & 300.14 Multiple cable entry at one knock out Ground connection/crimp inside the box How big will this box need to be? Answer – 32 cu. in.
NEC 110.12 - Workmanship Pinched wire
NEC 334.14 (B) NM cable not fully protected, subject to physical damage
NEC 310.15(B) (2) Bundled cables – Note good gable panel fit / installation
R404.1.6 & R408 Clearance to grade Crawlspace venting
House wrap installed 1st floor (plant) 2nd floor not done (on site)
I can’t open my window Flipped wide eaves = lower side wall mount
Table 602.3(1) Plywood fastening / 16” at intermediate = NO
Shingle Mfgr Installation Instructions Felt underlayment is under the drip edge