1 / 42

BUDGET REVIEW AND RECOMMENDATIONS REPORT Presented by : Ms N Magubane Director General

BUDGET REVIEW AND RECOMMENDATIONS REPORT Presented by : Ms N Magubane Director General 20 October 2010. DoE Management Team. Mrs. Thandeka Zungu: COO Mr. Dakalo Netshivhazwaulu: Acting CFO Mr. Ompi Aphane: Acting DDG of Electricity, Nuclear & Clean Energy

emily
Download Presentation

BUDGET REVIEW AND RECOMMENDATIONS REPORT Presented by : Ms N Magubane Director General

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BUDGET REVIEW AND RECOMMENDATIONS REPORT Presented by : Ms N Magubane Director General 20 October 2010 -Confidential-

  2. DoE Management Team • Mrs. Thandeka Zungu: COO • Mr. Dakalo Netshivhazwaulu: Acting CFO • Mr. Ompi Aphane: Acting DDG of Electricity, Nuclear & Clean Energy • Ms Tshilidzi Ramuedzisi: Chief Director Energy Planning • Mr Muzi Mkhize: Chief Director Hydro Carbons • Ms Yolisa Mapekula: Office of the Director General -Confidential-

  3. Presentation outline • Overall Departmental budget review • Personnel budget outlook. • Austerity measures adopted to contain expenditures. • Unfunded key activities. • Overview of Programme(s) performance. • Conclusion. -Confidential-

  4. Introduction • Last week we presented and certain issues were raised by the Committee. • The presentation has taken into account these issues: • Further breakdown of expenditure per Programme • Consolidated and detailed Programme Performance • More details on previous slides 11-17: • INEP • SWH • Liquid Fuels Masterplan • Integrated Energy Plan • Etc. -Confidential-

  5. Departmental budget per Programme -Confidential-

  6. Budget per Economic Classification -Confidential-

  7. Departmental ENE Allocations -Confidential-

  8. Adopted Austerity Measures Restriction on international travelling Restriction of internal catering Review of international commitments for affiliations Stringent measures for control of tele- communication costs Review of internship programme Restriction of advertisement on commercial media Review of process for appointment of consultants -Confidential- 8

  9. Key unfunded activities -Confidential- 9

  10. Programme 1 (Admin): Budget per Economic Classification -Confidential-

  11. Programme 1: Key Projects • Filing of vacancies • Payment turn around time • Procurement spent on HDSA • Internship programme • Bursaries • Training • Presidential Hotline • Employment Equity -Confidential-

  12. Programme 1: Key Activities – Filling of Vacancies -Confidential- 12

  13. Programme 1: Key Activities Cont… -Confidential- 13

  14. Programme 2 (HEP): Budget per Economic Classification -Confidential-

  15. Programme 2 (HEP): Key Projects • Fuel strategic stock policy • LPG price regulations • Fuel specifications and standards • 25 year Fuel Liquid Infrastructure Plan • Petroleum pricing framework • Transnet Multi Product Pipeline • 20 Year Integrated Energy Plan • National Integrated Energy Modelling System • SANERI/SANEDI -Confidential-

  16. Electricity Chief Directorate: Progress Reporting. -Confidential-

  17. Electricity Chief Directorate: Progress Reporting. -Confidential-

  18. Electricity Chief Directorate: Progress Reporting. -Confidential-

  19. Electricity Chief Directorate: Progress Reporting. -Confidential-

  20. Electricity Chief Directorate: Progress Reporting. -Confidential-

  21. Programme 3 (ENCE): Budget per Economic Classification -Confidential-

  22. Programme 3 (ENCE): Key Projects • IRP 2010 • ISMO • Electricity Regulation Act, 2nd amendment bill • Independent Power Producers • REDs • Standard offer policy • INEP • Solar Water Heaters • Nuclear -Confidential-

  23. Electricity Chief Directorate: Progress Reporting. -Confidential-

  24. Electricity Chief Directorate: Progress Reporting. -Confidential-

  25. Programme 3 (ENCE): Key Projects Contin… -Confidential- 25

  26. Project report: Non Grid Electrification ProgrammeStart: 01 April 2010 Finish: 31 March 2011 -Confidential-

  27. SWH Roll-Out : tariff funded programme -Confidential-

  28. SWH Roll-Out : tariff funded programme -Confidential-

  29. SWH Roll-Out : fiscal funded programme -Confidential-

  30. Number of Units settled through Eskom rebate programme to date • A total number of 10 600 claims has been received as of end of August 2010 • Eskom confirmed that they have settled 8700 units through the rebate programme. • The reason for the variance (1900 units) between the two figures is because of the delays in the Measurement and Verification process. • Target of total 6500 units for October in Bloemfontein, Kroonstad, Mossel Bay, Potchefstroom and Saldanha -Confidential-

  31. Roll out of High Pressure Systems • DoE exploring programme with CEF to make funding available to cover the gap between the consumer willingness-to-pay and the installation cost. • Modelling exercise to be completed end-October 2010 -Confidential-

  32. Spending patterns- INEP (‘000) 2009-2010; 2% 2008-2009; 1% -Confidential-

  33. SWH Program Objective Presentation outline -Confidential-

  34. SWH Program Targets Presentation outline -Confidential-

  35. Presentation outline Experience with Tariff Based Rebate Program - Eskom -Confidential-

  36. Comments from market on rebate programme “We are currently averaging 100 – 200 per month (reflected in Eskom stats)” - One big national player “Burst geyser is not good time to sell SWH” “Rebate programme just isn’t doing it for market” “Market needs a serious shake-up” “It would be embarrassing to give you our sales numbers” 3126 installed on Eskom rebate from Jan 2009 – Apr 2010 Average for 3 months of new rebate level = 443 units per month -Confidential-

  37. Experience with new diversified approach Presentation outline -Confidential-

  38. What is in the pipeline? Presentation outline • Program funded from fiscus to install 40 000 systems – Eskom managed and due to start in November 2010 • Program involving local banks and insurance industry to install residential systems without any rebates • Voluntary program by industry in lieu of their contribution to energy efficiency -Confidential-

  39. What are the key challenges that will increase rate of rollout if addressed? Presentation outline • Capital cost of imported components and systems is too high (R18 000 for 150 liter) • Funding • Skills shortages – necessary for safe scaled up installations -Confidential-

  40. Presentation outline Addressing the challenges • Skills program initiated with CETA, eSETA, donors – unit standards developed and accredited training available • Various initiatives to manufacture locally – preference will be applied for local systems when rebates are applied for • Additional fiscal allocations applied for, plus tariff-based rebate cemented in Integrated Resource Plan (Nersa will be compelled to make adequate rebates available in the future) -Confidential-

  41. Programme 4: Associated Services -Confidential-

  42. END….. -Confidential- 42

More Related