An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on FCPS Construction/Renovation Projects May 2009

  2. Cassidy Elementary – Renovation • Architect: Tate.Hill.Jacobs: Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • Contract Sum: $9,061,000 • Change Orders to Date: $0 • Current Phase: 1 (On Schedule)

  3. Cassidy Elementary – Renovation Rendering of Final Façade

  4. Cassidy Elementary – Renovation • Work Completed in Last 30 Days: • New staff parking lot @ Tates Creek Rd. cut to subgrade. • Subgrade for new 2-Story Administration/Classroom Addition completed and foundations begun. • Original Stage and Music Room demolition complete. • Miscellaneous interior demolition continued as needed. • Current Work Effort (May): • Stone installed in new parking lot for temporary staging area. • New Music Room/Mechanical Room Addition foundation and concrete slab will be complete. • New 2-Story Administration/Classroom Addition foundation and concrete slab will be complete. • Masonry to begin with concrete block walls on 2 additions. • Underground sanitary and plumbing rough-in work to start under new additions. • Underground electric feeds and below slab rough-in to continue.

  5. Cassidy Elementary – Renovation New 2-Story Admin Addition foundation New Staff Parking Lot subgrading, Tates Creek Rd New Underground Detention System excavation New Music Rm./Mech. Rm. Addition site

  6. Russell Cave Elementary – Renovation • Architect: Pearson & Peters Architects • General Contractor: Congleton-Hacker Construction • Substantial Completion Date: August, 2010 • Contract Sum: $5,001,150 • Change Orders to Date: $0 • Current Phase: 1

  7. Russell Cave Elementary – Renovation Rendering of Final Façade

  8. Russell Cave Elementary – Renovation • Work Completed in Last 30 Days: • Building pad and foundation bearing have been tested and approved. • Footings and foundation walls: 125 feet of footings have been poured and 61 feet of foundation wall have been poured. • Existing sprinkler line has been relocated. • Current Work Effort (May): • Additional work on footings and foundation at the new addition will continue. • Installation of the new leach fields for the septic system will begin installation in the front lawn of the building. • New electrical conduits will be installed in the existing crawlspaces to feed wiring to new addition and the existing kitchen. • New cooler/freezer and hood roof curb for kitchen renovation is scheduled for delivery the week of June 8th. Work will begin as soon as school is out.

  9. Russell Cave Elementary – Renovation Foundation Work 5.5.09 Foundation Work 5.5.09 Foundation Work 5.5.09 Foundation Work 5.5.09

  10. Arlington Elementary – Renovation • Architect: RossTarrant Architects • General Contractor: W/S Construction • Substantial Completion Date: August, 2010 • Contract Sum: $9,920,194 • Change Orders: $36,900 (#1--Demo) • Current Phase: 1

  11. Arlington Elementary – Renovation Rendering of Final Façade

  12. Arlington Elementary – Renovation • Work Completed in Last 30 Days: • Demolition completed • Work at Site to begin in mid-May

  13. Arlington Elementary – Renovation Demo – Main Bldg. Demo – Main Bldg. Demo – Gym Demo – Gym

  14. Bryan Station Middle – Renovation • Architect: Clotfelter-Samokar Architects • General Contractor: Preston Construction Group • Substantial Completion Date: August, 2010 • Contract Sum: $10,769,400 • Change Orders to Date: $0 • Current Phase: Phase 1 to begin June 1

  15. Bryan Station Middle – Renovation Rendering of Final Façade

  16. Bryan Station Middle – Renovation • Work Completed in Last 30 Days: • GC conducting preparatory activities • Work at Site to Begin June 1

  17. Leestown Middle – Renovation • Architect: Lucas/Schwering Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • Contract Sum: $11,182,000 • Change Orders to Date: $0 • Current Phase: Phase 1a, 1b, 1c to begin June 1

  18. Leestown Middle – Renovation Rendering of Final Façade

  19. Leestown Middle – Renovation • Work Completed in Last 30 Days: • Pre-construction meeting held on 5/5/2009. • Work at Site to Begin June 1

  20. Lafayette High Stadium – Replacement • Architect: Strand & Associates • General Contractor: Set to bid July 1 • Substantial Completion Date: July, 2010 • Contract Sum: TBD • Change Orders to Date: $0 • Current Phase: Construction Documents

  21. Lafayette High Stadium – Replacement UPDATED – Existing Campus

  22. Lafayette High Stadium – Replacement UPDATED – Existing Football Stadium

  23. Lafayette High Stadium – Replacement UPDATED – New Football Stadium

  24. Central Bus Garage – Adaptive Reuse • Architect: Lucas/Schwering Architects • General Contractor: James R. Leake & Sons, Inc. • Substantial Completion Date: August, 2009 • Contract Sum: $2,782,000 • Change Orders to Date: $0 • Current Phase: Construction

  25. Central Bus Garage – Adaptive Reuse Façade

  26. Central Bus Garage – Adaptive Reuse Proposed Floor Plan

  27. Tonight’s Agenda Items