Update on FCPS Construction/Renovation Projects. May 2009. Cassidy Elementary – Renovation. Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date: August, 2010 Contract Sum: $9,061,000 Change Orders to Date: $0
E N D
Cassidy Elementary – Renovation • Architect: Tate.Hill.Jacobs: Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • Contract Sum: $9,061,000 • Change Orders to Date: $0 • Current Phase: 1 (On Schedule)
Cassidy Elementary – Renovation Rendering of Final Façade
Cassidy Elementary – Renovation • Work Completed in Last 30 Days: • New staff parking lot @ Tates Creek Rd. cut to subgrade. • Subgrade for new 2-Story Administration/Classroom Addition completed and foundations begun. • Original Stage and Music Room demolition complete. • Miscellaneous interior demolition continued as needed. • Current Work Effort (May): • Stone installed in new parking lot for temporary staging area. • New Music Room/Mechanical Room Addition foundation and concrete slab will be complete. • New 2-Story Administration/Classroom Addition foundation and concrete slab will be complete. • Masonry to begin with concrete block walls on 2 additions. • Underground sanitary and plumbing rough-in work to start under new additions. • Underground electric feeds and below slab rough-in to continue.
Cassidy Elementary – Renovation New 2-Story Admin Addition foundation New Staff Parking Lot subgrading, Tates Creek Rd New Underground Detention System excavation New Music Rm./Mech. Rm. Addition site
Russell Cave Elementary – Renovation • Architect: Pearson & Peters Architects • General Contractor: Congleton-Hacker Construction • Substantial Completion Date: August, 2010 • Contract Sum: $5,001,150 • Change Orders to Date: $0 • Current Phase: 1
Russell Cave Elementary – Renovation Rendering of Final Façade
Russell Cave Elementary – Renovation • Work Completed in Last 30 Days: • Building pad and foundation bearing have been tested and approved. • Footings and foundation walls: 125 feet of footings have been poured and 61 feet of foundation wall have been poured. • Existing sprinkler line has been relocated. • Current Work Effort (May): • Additional work on footings and foundation at the new addition will continue. • Installation of the new leach fields for the septic system will begin installation in the front lawn of the building. • New electrical conduits will be installed in the existing crawlspaces to feed wiring to new addition and the existing kitchen. • New cooler/freezer and hood roof curb for kitchen renovation is scheduled for delivery the week of June 8th. Work will begin as soon as school is out.
Russell Cave Elementary – Renovation Foundation Work 5.5.09 Foundation Work 5.5.09 Foundation Work 5.5.09 Foundation Work 5.5.09
Arlington Elementary – Renovation • Architect: RossTarrant Architects • General Contractor: W/S Construction • Substantial Completion Date: August, 2010 • Contract Sum: $9,920,194 • Change Orders: $36,900 (#1--Demo) • Current Phase: 1
Arlington Elementary – Renovation Rendering of Final Façade
Arlington Elementary – Renovation • Work Completed in Last 30 Days: • Demolition completed • Work at Site to begin in mid-May
Arlington Elementary – Renovation Demo – Main Bldg. Demo – Main Bldg. Demo – Gym Demo – Gym
Bryan Station Middle – Renovation • Architect: Clotfelter-Samokar Architects • General Contractor: Preston Construction Group • Substantial Completion Date: August, 2010 • Contract Sum: $10,769,400 • Change Orders to Date: $0 • Current Phase: Phase 1 to begin June 1
Bryan Station Middle – Renovation Rendering of Final Façade
Bryan Station Middle – Renovation • Work Completed in Last 30 Days: • GC conducting preparatory activities • Work at Site to Begin June 1
Leestown Middle – Renovation • Architect: Lucas/Schwering Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • Contract Sum: $11,182,000 • Change Orders to Date: $0 • Current Phase: Phase 1a, 1b, 1c to begin June 1
Leestown Middle – Renovation Rendering of Final Façade
Leestown Middle – Renovation • Work Completed in Last 30 Days: • Pre-construction meeting held on 5/5/2009. • Work at Site to Begin June 1
Lafayette High Stadium – Replacement • Architect: Strand & Associates • General Contractor: Set to bid July 1 • Substantial Completion Date: July, 2010 • Contract Sum: TBD • Change Orders to Date: $0 • Current Phase: Construction Documents
Lafayette High Stadium – Replacement UPDATED – Existing Campus
Lafayette High Stadium – Replacement UPDATED – Existing Football Stadium
Lafayette High Stadium – Replacement UPDATED – New Football Stadium
Central Bus Garage – Adaptive Reuse • Architect: Lucas/Schwering Architects • General Contractor: James R. Leake & Sons, Inc. • Substantial Completion Date: August, 2009 • Contract Sum: $2,782,000 • Change Orders to Date: $0 • Current Phase: Construction
Central Bus Garage – Adaptive Reuse Proposed Floor Plan