LISD Board of Trustees. Status Report Presentation to the. by the. Facility Construction Department. March 27, 2002. Projects Under Construction (as of March 18, 2002). Campus Start Date Sta. Maria Elementary School Oct. 2001
E N D
LISD Board of Trustees Status Report Presentation to the by the Facility Construction Department March 27, 2002
Projects Under Construction(as of March 18, 2002) Campus Start Date • Sta. Maria Elementary School Oct. 2001 • Farias Elementary School Oct. 2001 • Dovalina Elementary School Oct. 2001 • Sanchez/Ochoa Elem. School Oct. 2001 • J. W. Nixon High School Oct. 2001 • Milton Elementary School Jan. 2002
Santa Maria Elementary School • Architect: Cavazos & Associates Architects • Contractor: Leyendecker Construction, Inc. • Contract amount: $4,862,700.00 • Construction Start: Oct. 31, 2001 • Start of School: Aug. 15, 2002 • Completion Date: Aug. 31, 2002 • Change Order(s): Addition of Single Sex Restrooms at PK & K.
Santa Maria Elementary School LISD: Sta. Maria: Foundation construction on going. Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. All excavations is complete, all reinforcing is on jobsite. Masonry construction projected to commence 1-23-02. Metal building delivery scheduled to commence 3-01-02. THIS IS A VIEW LOOKING NORTH FROM THE SOUTH WEST CORNER OF THE NEW CAMPUS
Santa Maria Elementary School THIS IS A VIEW OF THE AIR CONDITIONING DUCT BEING ASSEMBLED FOR INSTALLATION
Santa Maria Elementary School LISD: Sta. Maria: Foundation construction on going. Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. All excavations is complete, all reinforcing is on jobsite. Masonry construction projected to commence 1-23-02. Metal building delivery scheduled to commence 3-01-02. ZONE “A” AND “B”
Santa Maria Elementary School LISD: Sta. Maria: Foundation construction on going. Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. All excavations is complete, all reinforcing is on jobsite. Masonry construction projected to commence 1-23-02. Metal building delivery scheduled to commence 3-01-02. KINDER AND FIRST GRADE
Santa Maria Elementary School LISD: Sta. Maria: Foundation construction on going. Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. All excavations is complete, all reinforcing is on jobsite. Masonry construction projected to commence 1-23-02. Metal building delivery scheduled to commence 3-01-02. EAST SIDE ENTRANCE
Farias Elementary School • Architect: Ashley Humphries, & Sanchez Architects • Contractor: Leyendecker Construction, Inc. • Contract amount: $4,926,997. • Construction Start: Oct. 31, 2001 • Days in Contract: 320 Calendar Days • Completion Date: Aug. 31, 2002 • Change Order(s): Addition of Single Sex Restrooms at PK & K.
Farias Elementary School FRONT VIEW OF BUILDING SECTION “E”
Farias Elementary School FRONT VIEW OF BUILDING SECTION “F”
Farias Elementary School INSIDE VIEW OF BUILDING SECTION “E”
Farias Elementary School VIEW LOOKING SOUTH AT HE FRONTS OF SECTIONS “B” AND “C” FFROM THE FLOOR PLAN
Farias Elementary School VIEW OF SECTION “A” LOOKING EAST FROM THE NORTH WEST CORNER OF THE SITE
Farias Elementary School VIEW OF THE REAR AREA OF SECTION B
Dovalina Elementary School • Architect: Design Group International, Inc. • Contractor: Leyendecker Construction, Inc. • Contract amount: $ 2,801,900. • Construction Start: Oct. 31, 2001 • Number Contract Days: 304 • Completion Date: Aug. 31, 2002 • Change Order(s): None
Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. THIS IS A VIEW LOOKING WEST AT THE HALF WALL THAT WILL DIVIDE THE GYMNASIUM AND THA CAFETERIA
Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. THIS IS A VIEW OF THE MASON’S FINISHING THE BLOCK WORK AROUND A STEEL COLUMN ON THE GYM SIDE WHERE THE FOLDING PARTITION WILL END
Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. THE A/C DUCT IS BEING PREPARED FOR INSTALLATION
Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. HALL NUMBER “7” LOOKING EAST
Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. ACCENTED CEILING INSIDE OF CLASSROOM #3, THE ART CLASSROOM
Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. ACCENTED CEILING INSIDE OF CLASSROOM #4, THE MUSIC AND FINE ARTS CLASSROOM
Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. VIEW LOOKING WEST AT THE EAST WALL OF THE NEW GYMNASIUM
Sanchez/Ochoa Elementary School • Architect: Sepulveda & Assoc. Architects • Contractor: Leyendecker Construction, Inc. • Contract amount: $ 5,132,719. • Construction Start: Oct. 31, 2001 • Number Contract Days: 320 • Completion Date: Sept. 16, 2002 • Change Order(s): None
Sanchez/Ochoa Elementary School FRONT VIEW OF SECTIONS “C” AND “D” FROM THE FLOOR PLAN
Sanchez/Ochoa Elementary School VIEW LOOKING INTO SECTION “C” OF THE FLOOR PLAN
Sanchez/Ochoa Elementary School VIEW LOOKING
J. W. Nixon High School • Architect: Cavazos & Associates Architects • Contractor: Leyendecker Construction, Inc. • Contract amount: $ 9,298,985. • Construction Start: Jan. 30, 2002 • Number Contract Days: 551 • Completion Date: August. 15, 2003 • Change Order(s): None
Milton Elementary School • Architect: Turner Hickey & Assoc. Arch. • General Contractor: To be determined • Asbestos/Demolition: M & M Contracting, Inc. • Contract amount: $ 183,978. • Construction Start: Jan. 27, 2002 • Number Contract Days: 47 Days • Completion Date: March 15, 2002 • Change Order(s): None